Sunteți pe pagina 1din 117

Project Proposals & Tendering

Types of Contract
Prof. Debopam Roy

What is a contract
Agreement between competent parties enforceable at law Formation of Contract:
Object Proposal / Offer Acceptance Consideration Reciprocal promise

Typical Parties for Works Contract


Owners
Public Owner (Government bodies) Private Owner (also include quasi-public bodies)

Architect/Engineers (A/E) Prime/General Contractor Sub-contractors Suppliers Banks & Financial Institutions Specialized Service Agencies Labor Regulatory agencies General Public

Rules for the Participants


Contracts Tort Law Laws, Statutes, and Regulations of Government Agencies

Typical contractual relations between parties of a construction project


Owner A/E Contract for Professional Services (Design and Bid Plans and Specifications)

Advertisement for Bids Contractor Joint Venture Agreements Bids

Owner-Contractor Construction Contracts (Prime Contracts)

Surety Bonds

Insurance Contracts

Subcontractor Agreements

Labour Agreements

Purchase Order Agreements

Nature of Contractual Services


Design Only Construct Only Design & Construct Turnkey Construction Management Services

Nature of Contracts
Owner Architect Contracts and Owner Engineer Contracts Owner Construction Manager Contracts Owner Contractor Contracts

Subcontracts ; Purchase Orders; Insurance Contract

The Prime Contract

STANDARD FORMS OF CONTRACT-India


CPWD MES State PWD Model Standard Contract For Domestic Construction CIDC

ONE-OF-A-KIND CONTRACTS
Created for a particular project Little about them is standard or traditional

STANDARD FORMS-OF-CONTRACT International


American Institute of Architects (AIA) Contracts Standard form of Agreement Between Owner and Contractor Most widely used form for fixed-price building construction works in USA. FIDIC - International Federation of Consulting Engineers http://www1.fidic.org/resources/contracts/which_contrac t.asp

These Conditions of Contract are recommended for engineering and building work of relatively small capital value. However, depending on the type of work and the circumstances, the Conditions may be suitable for contracts of considerably greater value. They are considered most likely to be suitable for fairly simple or repetitive work or work of short duration without the need for specialist sub-contracts. This form may also be suitable for contracts which include, or wholly comprise, contractor-designed civil engineering, building, mechanical and/or electrical works.

Conditions of Contract for Construction, which are recommended for building or engineering works designed by the Employer or by his representative, the Engineer. Under the usual arrangements for this type of contract, the Contractor constructs the works in accordance with a design provided by the Employer. However, the works may include some elements of Contractor-designed civil, mechanical, electrical and/or construction works.

Conditions of Contract for Plant and Design-Build, which are recommended for the provision of electrical and/or mechanical plant, and for the design and execution of building or engineering works. Under the usual arrangements for this type of contract, the Contractor designs and provides, in accordance with the Employers requirements, plant and/or other works; which may include any combination of civil, mechanical, electrical and/or construction works

Conditions of Contract for EPC Turnkey Projects, which are recommended where one entity takes total responsibility for the design and execution of an engineering project. Under the usual arrangements for this type of contract, the entity carries out all the Engineering, Procurement and Construction: providing a fullyequipped facility, ready for operation (at the "turn of the key"). This type of contract is usually negotiated between the parties.

The purpose of these guidelines is to present the commonly used methods of consultant selection, to explain the respective procedures and to combine them all in one compact document, as well as to emphasize and explain FIDIC's policies on the subject of selection.

The terms of the Client Consultant Model Services agreement (The White Book) have been prepared by FIDIC and are recommended for general use for the purposes of pre-investment and feasibility studies, designs and administration of construction and project management, where proposals for such services are invited on an international basis: They are equally adaptable for domestic agreements.

TYPICAL DOCUMENTS COMPRISING THE CONTRACT


Bidding documents consisting of the Invitation to Bid, the Instruction to Bidders, and the Bid Form General Conditions of Contract Special Conditions of Contract Specifications Drawings Reports of investigations of physical conditions

BIDDING DOCUMENTS
Normally begins with an advertisement Identifies the project for which bids are desired The owner Time and place of bid opening Instructions to potential bidders on how to obtain a full set of contract documents Invitation for Bids (IFB) or Request for Proposals (RFP) IFB used when bidders must strictly confirm to drawing and specs. RFP when bidders may propose variations for the project

BIDDING DOCUMENTS
IFB or RFP typically include: A description of the contract work The identity of the owner The place, date, and precise time of the bid opening The penal sum of the required bonds (bid bond, performance bond etc.) A description of the drawings and specs, their cost, and where they may be obtained Rules regarding withdrawal, modifications, late bids etc.

BIDDING DOCUMENTS
Instructions to Bidders Bid Form Bidders complete this document, sign, seal and turn it in Constitutes the offer To constitute a responsive bid, the bid form must be completely filled, signed and sealed in accordance with the IFB or RFP and Instructions to Bidders

BIDDING DOCUMENTS
Bid Forms Contents A definitive statement of the general terms and conditions of the offer The format of the commercial terms applying to the offer Supplementary information that the owner may want to know about the bidder Requirement for public projects Bid security

GENERAL CONDITIONS OF CONTRACT


Very definitive statements, clause by clause, of all general terms and conditions that will govern the performance of the contract work The general concept of this section is to include all clauses that will remain the same, contract after contract, changing very infrequently

SPECIAL CONDITIONS OF CONTRACT


Also known as Supplementary Conditions Project specific matters

Those that are either site specific or in some other way apply only to the specific contract

SPECIFICATIONS
The technical requirements for each division of work in the contract will be completely detailed in specifications Conforms to Uniform Construction Index or Masterspec format Should be carefully drafted so that both parties to the contract have a mutual understanding of the precise technical requirements

DRAWINGS
Complement the specifications Should be sufficiently clear to adequately show exactly what is to be built Certain features may be shown in fairly general terms, requiring the contractor to prepare the detailed drawings In fixed-priced bids should be adequately sufficient and clear

REPORTS OF INVESTIGATION OF PHYSICAL CONDITIONS


Often concern the geotechnical aspects of subsurface conditions Usually appear in the form of written evaluations and soil boring logs Other examples are weather records, stream flow hydrographs etc. Is such material to be considered part of the contract documents? Owners often use disclaimers, to escape liability

Types of Prime Contract


Measurement Contract
Item Rate Percentage Rate

Fixed Price
Lump Sum EPC, Turnkey, Design Build

Cost Reimbursable
Cost plus percentage fee (CPPF) Cost plus fixed-fee (CPFF) Cost plus incentive fee (CPIF) (Also called as Target Estimate) Guaranteed Maximum Terms (GMP)

Concessions

Measurement Contract
Contract is Broken Down into a series of bid items, each for a discrete element of work of the project The two parties are not bound by the total value of work. They are bound by each individual rates Payment is based on actual measured quantity of work Most common type is Item Rate

Item Rate Contract


Also called unit-price contract Bid document includes a schedule-of-bid-items or Bill of Quantities The schedule contains the following columns:
Sl. No. Description of each item of work Unit of Measurement Estimated quantity Rate or Price per unit of work Value of the particular item of work Remarks if any

Item Rate Contract


Sl. No. Item Description UOM Quantity Rate Amount Remarks

Item rate Contract


The schedule with item description and quantities is given with bid form The bidders fill in the rate column for each of the item The rate or unit price includes the contractors overheads and profits By totaling all the arithmetic products (Quantity x Rate), the estimated total cost of the project is obtained The project is awarded to the lowest responsible and responsive bidder; i.e. the bidder with lowest estimated cost who satisfies all pre-conditions

Item Rate Contract


As the actual work progresses, the payment is made on quantity of work physically measured If no changes are made in nature of work, the quantity of work actually performed can vary from the quantities in BOQ (subject to limits), without change in rate If the quantity of work changes beyond limits, the rates may be revised The final contract price will depend on the actual quantity of work. The estimated value of contract is not binding For new items of work, not in original schedule, the rates need to be separately negotiated

Item Rate Contract


Bid Documents
Notice Inviting Tender Instruction to the Bidders Qualification Criteria General Conditions of Contract Special conditions of contract Project Details Bill of Quantities Basic Drawings Specifications Details of Bid Bonds

Item Rate Contract


Mode of Payment
The contractor has to take measurements of the work carried out, prepare and submit the bill periodically ( generally every month ) The engineer either accompanies the contractor or his representative while the measurements, or checks the quantities afterwards. If no discrepancy is found recommends the bill for payment. The amount recommended by the engineer is the cost of the work less retention money and the cost of material supplied to the contractor by the owner and actually used on the work during the period under consideration. If any item occurs during execution which is not included in the bill of quantities, It is usually possible construct that item by a combination of other items already in the bill, otherwise It is paid for as an extra item as a specially analyzed rate.

Item Rate Contract


Pros
The tender can be floated right after preparation of preliminary drawings Beneficial when there is lack of design information Tendering process, Mobilization, etc. can be carried out in parallel with design & drawing Easier to accommodate changes due to differing site conditions, change in requirements, etc. Less risk of contractor making error in quantity estimation during short time period available during bidding Less tendency of contractor to bid conservatively What the owner pays to the contractor is the actual cost of the work at the agreed rates. This arrangements is fair to both the parties

Item Rate Contract


Cons
Owner can not be sure of total cost till completion of project. Can lead to huge cost escalations Needs lot of book keeping. Increases overheads No incentive on contractor to reduce quantity / cost. No scope for value engineering Dispute regarding extra items Malpractices (Insider trading) Front loading

Item Rate Contract


Dispute regarding extra items
The contractor invariably presses for higher rates than he would have tendered in the beginning May threaten to not perform the extra items if his demand not made. Difficult to get the extra items done by another contractor In most cases owner has to meet the demands

Item Rate Contract


Malpractices
The bidder, by bribing an insider, can get information on an item, which has more probability of increase in quantity He may bid high rate for that particular quantity, and bid low for another which he knows may decrease in quantity He may be awarded the contract on becoming L1, and on actual completion, the payment made may be much more than what would have been made if project was awarded to the L2 bidder Through corruption the quantities can even be intentionally changed to facilitate such malpractice

Item Rate Contract


Front Loading
The contractor may put a higher rate for works to be completed earlier, and a lower rate for ending items This ensures that contractor becomes cash rich upfront, and can manage his working capital better However if the bid is heavily front loaded, contractor may run away, after completing the profitable items

Percentage Rate Contract


Another type of measurement contract Devised to get rid of unbalanced / front loaded bids The rates are estimated by the owner himself, and included in the BOQ, in addition to item description and quantity The bidder has to quote a percentage above / below / at par with the rates given in the BOQ Rates of all items will be increase/decreased by the percentage quoted by the bidder The bids will be compared based on value of work derived based on the revised rates

Percentage Rate Contract


No scope for
Unbalanced bids Front loading Malpractices through insider tips

used in preference to the item rate contract for the works where the estimated quantities are uncertain and likely to change considerably.

Percentage Rate Contract


Documents
Same as item rate, only rate column of BOQ filled by owner and not bidder

Mode of payment
Same as item rate

Lump sum Contract


It is a Fixed Price Contract, i.e. the contractor will be paid an agreed fixed price for the contractually stipulated services The lump sum amount can be decided by negotiation or competitive bidding The bidders quotations are compared on the basis of only one figure, the bottom-line or total estimated contract value The value of the works is estimated by the contractor based on the drawings and specifications provided.

Lump sum Contract


Fixed price contract needs complete and accurate set of drawings and specifications Even with complete drawings, estimation of the fixed price in short time available for bid preparation becomes difficult Contractor may quote very conservatively Sometimes, the agreement makes provision to adjust the fixed sum allowing for the cost of extra work, variation , omission, etc., through deviation schedule.

Lump sum Contract


Deviation schedule
The work is broken into a no. of items, as in a BOQ Gives a complete break-up of the fixed price, including item description, quantity and rate In case of variation, the amount payable for that particular item is decided based on the deviation schedule

Lump sum Contract


Even though the fixed price is for the total completion of job, working capital management becomes difficult if there is no interim payment Milestones are decided Payment is linked with completion of milestones Payment schedule is mostly back loaded In case the contractor abandons midway, he can only receive payment for completed milestones and not the actual portion of work done The engineers interim certificates form the basis of part payments to the contractor by the owner

Lump sum Contract


Bid Documents
Notice Inviting Tender Instruction to the Bidders Qualification Criteria General Conditions of Contract Special conditions of contract Project Details Complete set of Detailed Drawings & site investigation data Specifications Details of Bid Bonds Deviation Schedule Payment Schedule

Lump sum Contract


Pros
If no extras are contemplated the tenders tell the owner exactly what the project will cost him. This is a sound footing on which he can take the decision whether to start the project or abandon the same Owner need not employ too many staff to keep periodical accounts of the contractors materials, labour and output. All that the engineer has to do on his behalf is to see that the work is being executed exactly according to the terms of the contract and issue interim certificates to the contractor There is incentive on the contractor to save on quantity / cost. Considerable scope for value engineering and innovation

Lump sum Contract


Cons
Before a contract is let out the project has got to be thoroughly investigated and all the contract documents kept ready in every respect. This entails costly and time consuming work and which is often difficult to accomplish. If the nature , extent, and details of the work are not properly defined by the contract documents, many additional features may have to be determined and provided for as the work progresses. These features not being part of the original agreement give opportunity to the contractor for claiming payment at abnormal rates

Lump sum Contract


A lump sum contract can be used successfully for the construction of works with which the contractors have had considerable experience and whose cost they can predict with reasonable accuracy. Examples of such works are public and private building, warehouses, workshops , etc.

Lump sum Contract


This type of contract is not suitable for works of which extent and nature cannot be predicted in advance. It is then unfair to make the contractor assume all risks and uncertainties. Example of works unsuited to a lump sum contract are :
Works involving difficult foundations : Where it is no possible to know in advance the characteristics and quantity of excavation, dewatering of foundations, shoring etc. Emergency projects that have to be rushed through without time to prepare complete set of contract documents. Works, such as additions and alterations to existing structure which involves the maintenance of operations while the work is being performed. The works subjected to unusual and unpredictable hazards such as floods beyond the control of contractors.

EPC / Turnkey Contract


EPC Engineering Procurement Construction Turnkey Ready to be commissioned at turn of a key These projects include design as well as construction (i.e. Combination of A/E contract & Prime Contract) The owner only provides preliminary conceptual drawings (Front End Engineering) & specifications during bidding. Detailed Design & Working Drawings (Detailed Engineering) is done by the contractor as per specifications provided by owner In most cases specifications lay down the performance criteria only. Methods decided by the contractor A Construction Management Service or a Project Management Consultant may be employed by owner to check progress and quality of works

EPC / Turnkey Contract


Commercial Terms can be
Lump sum Item rate A combination of both Cost plus

Mode of payment can be


Measurement Based Milestone Base Combination of Both

EPC / Turnkey Contract


In case of LSTK (Lump Sum Turn Key), deviation schedule is mandatory since in absence of all drawings, it is impossible for bidder to estimate the final cost correctly Hence the bid documents include a BOQ, which contains rates of all items and initial quantities (estimated by the bidder), used as a back up to arrive at the Lump sum. The BOQ is revised after all drawings are completed, and the lump sum fixed based on previous rate Lump sum includes design fees

EPC / Turnkey Contract


In case of unit price EPC contract, the BOQ contains all items of work, including design services, escalation, etc. The quantities and rates are estimated and submitted by the bidders. The rates are fixed, but quantities may be changes depending on the drawing (to any extent) The payment is based on actual measured quantity

EPC / Turnkey Contract


In big projects, some portions may have lump sum price, and some other portions may be item rate (i.e. some related items may be bundled into a lump sum, other items stay unbundled and are paid on unit price) Example: In a highway contract, excavation, earthwork, WMM, asphalt, may be item rate (paid on per LM) whereas Flyovers, CD structures, Toll Plazas may be lump sum Invoicing schedule will contain both milestone and measurement

EPC / Turnkey Contract


Bid Documents
Notice Inviting Tender Instruction to the Bidders Qualification Criteria General Conditions of Contract Special conditions of contract Project Details Preliminary Drawings Specifications Details of Bid Bonds Invoice Schedule Bill of Quantities Milestone schedule Deviation schedule

EPC / Turnkey Contract


The work can be greatly expedited under such contracts as extensive plans and specifications need not be prepared by the employer. Project is fast track since design and construction can proceed in parallel There is no division of responsibility, hence contract management is simpler Owner needs to employ less no. of professional staff Enables the contractor, with specialized knowledge of his own techniques, to design so as to produce maximum economy, and therefore a leaner price, in a way that an architect or engineer without knowledge of these techniques would not be able to produce. More scope and incentive for innovation and value engineering

Cost Plus Contracts


In these contracts the owner agrees to pay the contractor the actual cost of carrying out the work, plus an additional amount which would cover his profits and indirect overheads Not as common as lump sum / item rate but sometimes may become necessary due to various circumstances
Unusual nature of work Lack of interest among contractors

Cost Plus Contracts


The items, expenses under which will constitute actual cost, are to be carefully defined in the agreement Generally the following are not included as cost, and is considered to be part of the percentage fee paid Salaries of he contractors supervisory staff. Contractors general office expenses such stationery, postage , telephone accounts etc. Salaries or portion of salaries or traveling expenses of the officials of the firm who may visit the work. Charges for the use of any equipment that the contractor would not normally use for the performance of the work.

Cost plus percentage fee (CPPF)


The owner agrees to pay to the contractor the actual cost of the work plus an agreed percentage of the actual or allowable cost

Cost plus percentage fee (CPPF)


Bid Documents
Notice Inviting Tender Instruction to the Bidders Qualification Criteria General Conditions of Contract Special conditions of contract Project Details Details of Bid Bonds

Cost plus percentage fee (CPPF)


Pros
Early completion of the work : The work can be started even before the drawings, designs, estimates and specifications are prepared; these being prepared as the work progresses. The decisions can be taken speedily. These factors lead to the rapid execution of the work.
Extra Works : No work or a portion thereof that the contractor is directed to perform can be called an extra work. This flexibility allows the adoption of alternative ways and methods of construction from which to choose the most economic one for the work as a whole. This may reduce the cost of the work. Disputes arising due to extra work are eliminated.

Cost plus percentage fee (CPPF)


Pros
Quality of Work : The contractor is assured of a reasonable amount of profit even though the prices of materials and the labour charges are subjected to fluctuations . Similarly , the use of inferior type of materials than specified and hurried completion resulting in poor workmanship do not increase the contractors profit. This induces him to perform the work in the best interest of the owner. The final result is therefore a better quality work.

Cost plus percentage fee (CPPF)


Cons
Lack of Incentive : Other than professional ethics and goodwill, There is no incentive for the contractor to complete the work speedily, and economically by proper planning and efficient management . On the contrary any increase in the construction cost due to delay, wastage of materials, changes in the drawings and designs result in increase of his profit.

Cost plus percentage fee (CPPF)


Cons
Unpredictability : The final cost is not known to the owner. This may lead the owner to financial difficulties. Since profits of the contractor are linked with cost of materials, labour and equipment, a high cost gives the contractor a higher amount of profits. This results in waste, inefficiency and extravagance by contractors

Cost plus percentage fee (CPPF)


Cons Accounts Keeping : Both the parties have to do a lot of accounts keeping regarding the materials purchased and used, the labour and plant employed and other miscellaneous expenses incurred on the work.

Illegal for Public Works : Where the owner happens to be a public body or government department this form of contract cannot be adopted except during emergencies.

Cost plus percentage fee (CPPF)


Suitability
When there is an emergency or any other condition that requires constructing a facility in a hurry without time to develop plans for it, neither the employer nor the contractor is sure about the cost of construction, a cost plus percentage contract is generally used
Works ( in situations which are no emergencies )Where no one can foretell with certainty just what troubles would be encountered in the work, and correct decisions cannot be taken except during the progress of the work Construction of expensive structures e.g. palaces, where the cost of the work is of no consequences but the materials to be used and the methods to be adopted are to suit the choice and taste of the owner

Cost plus percentage fee (CPPF)


The owner should exercise great care in selecting a contractor to carry out the work for him. A person or firm of known integrity , who will not exploit the weakness of this type of contract to his advantages, will be the best choice

Cost plus fixed fee (CPFF)


The contractor is reimbursed the actual cost incurred by him on materials and labour and is given a fixed amount of money as his fee. It has evolved because of the potential for abuse in CPPF format The profit of the contractor is not linked with the cost. The contractor receives only the stipulated sum for his part in overseeing and doing the job, no matter what the cost of the project may be The contractor will, therefore, try to complete the job as fast as possible, to reduce his overheads

Cost plus fixed fee (CPFF)


The agreement specifies the fixed lump sum to be paid to the contractor by the owner over and above the actual cost of the work. The employer can select a reliable contractor to execute the work. The parties can work in harmony and accomplish amazingly fine results. However, there is no incentive for the contractor to do the work economically

Cost plus fixed fee (CPFF)


Mode of Payment, Documents, Suitability
Same as CPPF

Cost plus incentive fee (CPIF)


A more sophisticated form of cost reimbursable contract The contractor is paid the actual costs for carrying out the work, and an incentive amount, worked out by a pre agreed formula, which is directly proportional to the savings over a target estimate

Cost plus incentive fee (CPIF)


The target estimate is an estimate agreed upon by the arties prior to entering into the contract, as the most probable cost of providing the contemplated services. A fee as payment for the services is also agreed to based on the magnitude of the target estimate, with the provision that the parties will share the benefits or penalties of any underruns or overruns in the actual costs incurred in providing the services, compared to the target estimate. The exact formula for sharing is also agreed to at the onset and may vary from contract to contract Usually there is a cap on the contractors share of overruns ( the agreed upon fee)

Cost plus incentive fee (CPIF)


By introducing an element of incentive for the contractor to carry out the work in the most economic way an attempt is made in this form of contract to overcome the main drawback of the previous two types of cost-plus contracts. This is achieved by suitably changing the nature of the agreement in respect of the fee is determined by reference to some form of sliding scale. Thus higher the actual cost, lower will be the value of the fee that the contractor receives and vice versa.

Guaranteed maximum price (GMP)


The parties agree on an initial estimate for the cost of the contemplated services and on a fee for the provider The estimated cost ; fee ; contingencies are added to yield the Guaranteed maximum price The GMP is the owners maximum financial exposure The owner reimburse the contractor for all costs incurred and pays the fees pro-rata No further payment after GMP is reached If the cost exceeds the GMP, the contractor suffers a loss If cost is less than GMP, owner receives total benefit of savings Contractors may be interested in GMP only in case of very high fees

Concession
The contractor undertakes to design, finance , construct , operate and maintain the works for a concession period The contractor recuperates his cost from the collection of charges levied on the beneficiaries who use the work and in some cases annuity payment each year. The facility is returned back to the government and all rights of concessionaire cease to exist Depending on the type of ownership, this may be further subdivided into different formats used in different countries at different times

Concession
BOT BOOT BTO DBFO BOLT ROT LOO Annuity FBOOT BOOST BRT BOO

Concession
Build Operate Transfer Build Own Operate Transfer Build Transfer Operate Design Build Finance Operate Build Operate Lease Transfer Rehabilitate Operate Transfer Lease Own Operate Annuity Finance Build Own Operate Transfer Build Own Operate Subsidies Transfer Build Rent Transfer Build Own Operate

Concession
The cost of construction of the project is ascertained in the manner of a lumpsum or item rate contract The bidder then works out the cost of financing the project and its recovery from the collection of toll or similar method till the cost of construction together with the cost of finance and expected profit is fully recovered The cost of maintenance of the project during the period in question has also to be added to the basic cost Each years income will recover the cumulative investment till the net becomes zero or negative

Concession
The concession period worked out by each bidder will depend upon the cost of construction worked out by each bidder and also the rate of interest considered for financing the project and expected profit. The bidder who submits the cash flow projections seeking the minimum period of concession is generally awarded the contract.

Concession
In some cases the total income predicted over any reasonable concession period does not adequately cover the total cost (EPC + O&M)+ interest + profit The authorities can provide some grants to bridge the gap Known as Viability Gap Funding The authority fixes the period of concession and seeks offers on the basis of grant expected from the employer The bidder expecting the least grant is generally awarded the contract The grant may be in the form of annuity payment or released in a phased manner as mutually agreed by the parties

Concession
In some cases, the bidders do not need grant, and the cumulative income from the years of concession fixed by the authority, far exceeds the total cost In these cases, the concessionaire may quote an upfront negative grant, or a share in revenues to the authority The bidder offering maximum negative grant or share in revenues will be awarded the contract

Concession
Documents
In addition to the usual contract documents cash flow projections giving details of how the contactor intends to generate finance and use it till the recovery of his capital, investment cost and profit during the concession period , forms an integral part of the contract

Concession
The main agreement contains several schedule describing
the project site project facilities site delivery schedule design requirements construction requirements operation and maintenance requirements cash flow projections annuity / grant payment schedule performance security state support agreement substitution agreement hand back requrements

Concession
Pros
public authority is not required to finance the project immediately project is made to generate the funds and be self financing to the extent possible greater autonomy for the contractor more scope for value engineering and innovation quality is assured since poor quality means increased maintenance cost for the contractor

Concession
Cons
greater risk on contractor Contractor needs expertise in not only construction but other areas like finance, O&M as well

Concession
Ideal type of contract for highways and expressways, bridge , tunnels , electricity power generation and supply etc that save the cost of operation or time of travel for which users will pay reasonable charges Not suitable for works that are not likely to generate capital for self financing eg. rural water supply projects, village roads , city roads, etc.

Subsidiary Agreements Required for Main Contract


Insurance Surety Purchase Orders Subcontracts

Surety Bonds / Guarantees

RELEVANT PARTIES AND SURETY BOND TERMS


Surety: A financial institution/entity possessing great wealth, and will pay up on default of the principal Principal: The entity that actually furnishes the bond Obligee: The entity who is guaranteed payment by the bond. For example, in case of bonds furnished by the prime construction contractor, the owner of the project is the obligee

RELEVANT PARTIES AND SURETY BOND TERMS


Guarantee: The promise made by the surety to the obligee, essentially underwriting the performance of the principal Penal Sum: The monetary limit to the guarantee is called the penal sum. May vary from 10% in bid bonds to 100% in performance bonds Premium: The fee that the principal pays to the surety in exchange for providing the guarantee Indemnitor: A person or entity, who promises to pay the surety back for any cost that the surety incurs if called upon to make good the guarantee

HOW DO SURETY BONDS WORK?


The potential liability assumed by a surety greatly exceeds the premium charged for underwriting the performance of the principal The considerations lying behind the willingness of the surety to assume the liability are:
Indemnity Agreement: Will provide that the principal and/or the indemnitors will pay the surety back for an losses that the surety incurs in making good the guarantee Surety bonds v/s Insurance contracts: Surety bonds are called on only when the principal fails to perform How good is the guarantee? Surety must be reputed and at the same time be financial stable for the obligee to have confidence in the guarantee Suretys belief in the Contractors ability to perform

BID BONDS
The bid bonds protects the interests of the owner against the potential loss that it may incur upon the refusal of the lowest bidder to sign the contract Bid bond guarantee The surety guarantees to the obligee that the principal will enter into a contract in the event of an award The principal will furnish the performance bond and insurance policies required by the contract

BID BONDS
Bid bond penal sum: can be expressed in either of the two ways: As either a fixed amount of money or as a percentage of the bid total It can be stated in the form of actual damages suffered, up to a stated limit

PERFORMANCE BONDS
Invoking the performance bond: Requires proof of default Delay may be because of conditions of force majeure In most cases, proof of actual default leads to litigation

Ways to make good the guarantee: (once default is established) Assist principal to remedy default by providing financial assistance Take control of contract and complete project by hiring another contractor or by the principal itself Allow obligee to get it completed and pay the obligee

PERFORMANCE BONDS
How much does surety pay? Penal sum is 100% of the contract price Determination of suretys obligation can be reached in various ways: Surety and obligee agree on a fixed amount (upto the penal sum limit). If actual costs are higher, surety doesnt pay anything, if costs are lower, oblige keeps the difference Another way would be to pay: actual costs incurred any unpaid contract balance + liquidated damages (due under contract), subject to maximum (penal sum)

PERFORMANCE BONDS
Owners misconception about performance bonds Possessing the bond does not imply absolute power over contractor Surety wont act until they believe principal is truly in default. If surety pays up and later it is discovered that there really wasnt any default on part of the principal, the surety cant recover the paid up money from indemnitors To collect eventually on the performance bond guarantee, the obligee must be legally correct on the facts of the default

PERFORMANCE BONDS
Excess early contract payments In cases when the contract is heavily front loaded, the obligee may actually not recover all costs incurred Surety is not liable to pay for such losses and will contest excess early payment Contractor protection of bonding capacity Small contractors wont want the surety to receive complaints about their performance If surety takes control of project (after default), the contractor will have to pay up later for all expenses incurred by surety

PURCHASE ORDER AND SUBCONTRACTOR AGREEMENTS


Additional contracts closely related to the construction contract between owner and prime contractor. On similar lines but fundamentally different in purpose.

Need to understand clearly the purpose and key features of each in order to decide which should be used for a particular business transaction

PURCHASE ORDERS
Intended for transactions that involve the sale of goods by a seller and delivery of those goods to a contractor buyer at the site of a construction project. Should be distinguished from the provision of services or the performance of work involving labour at or on the construction site

For example, providing fabricated structural or reinforcing steel

PURCHASE ORDERS
Goods or Provision of Services? Whether a particular transaction constitutes the sale of goods or the provision of services? Treat all transactions involving the provision of significant amounts of on-site construction labour as a construction operation requiring the use of a subcontract agreement Transactions that do not involve the provision of significant amounts of labour at the site should be treated as the sale of goods. It should be handled with a purchase order In India, Sale of Goods Act. 1930 applies

PURCHASE ORDERS
Use of purchase orders for certain jobsite services That involve minimal labor like provision and collection of trash containers Purchase order quantity limitations PO can be limited to a one-time transaction or may provide for a continuing supply of goods on an asrequired basis PO for continuing supply may be open ended or limited to stipulated maximum quantity.

PURCHASE ORDERS
Conflicts with sellers sales quotations The fine print on the back of the preprinted vendors sales quotation document conflicts with similar fine print on the back of preprinted purchase order document boilerplates Both vendors and contractors/purchasers try to obtain the most favorable terms Drafter of PO should ensure that the conflicts are avoided Flow-Down Language from Prime Contracts PO may contain explicit flow-down language intended to make all applicable provisions of the prime contract also apply to the PO

RED FLAG PURCHASE ORDER PROVISIONS


Necessary Identifying information Construction project for which the prime construction contract is held by the buyer Owner for that project A/E Contractor buyer Seller Description of the Goods Purchased Accurate and complete description of each separate item including appropriate references Quantity of each separate item

RED FLAG PURCHASE ORDER PROVISIONS


Shipping Instructions Exact name and address of the intended receiving party and instructions on how the goods are to be packaged and marked. Pricing and Basis for Quantity Measurement May contain flow-down provisions Prime contractors often purchase many items for which payment will be completely unrelated to the provisions of the prime contract

RED FLAG PURCHASE ORDER PROVISIONS


Payment and Retention Provisions Issues similar to the conditions under the prime contract to the owner No pay until paid clause Does not excuse the prime contractor from eventually paying Presence of condition precedent It is specifically understood and agreed that the payment to the trade contractor is dependent, as a condition precedent, upon the construction manager receiving contract payments, including retainer from the owner.

RED FLAG PURCHASE ORDER PROVISIONS


Specified Delivery Schedule Equivalent to the statement of allowed contract time in prime contract Required Delivery Point Example, F.O.B. construction jobsite Sales and Service Taxes Purchase Order General Conditions Contain most of the general clauses for prime contracts Special/Supplementary Provisions Courts give more weight to specially recorded terms than to preprinted terms

SUBCONTRACT AGREEMENTS
A prime contract between an owner and a prime contractor must exist before a construction subcontract can exist Prime contractor decides to lay off or subcontract, a portion of the work to another contractor called a subcontractor Prime contractor still retains the original liability to the owner for the performance of the work. Subcontract work can be directly spelled out in the prime contract or it may be work incidental to the contractor

SUBCONTRACT RED FLAG PROVISIONS


Necessary Identifying Information Project for the prime contract Owner for that project A/E Prime contractor Subcontractor Description of the Subcontract Work Must be carefully and completely described Should incorporate direct references to all applicable drawings and technical specifications and sections of the prime contract

SUBCONTRACT RED FLAG PROVISIONS


Pricing and Basis of Quantity Measurement If the subcontract work is incidental than payment is not related to the provisions of prime contract Payment and Retention Provisions Contractor Control of Performance Time Requirements Subcontractor shall perform the subcontract work on a schedule to be determined by contractor Damages in the Event of Late Completion Subcontract often explicitly states the flow of contract liability

SUBCONTRACT RED FLAG PROVISIONS


Subcontract Changes Clause Most subcontracts will give the prime contractor the right to make changes unilaterally in the subcontract work, delay, suspend or terminate it in the same manner as the owner can in prime contracts Insurance and Bond Requirements The subcontract may or may not require the subcontractor to furnish a performance bond and a labor & material payment bond Indemnification Owner may be protected by sovereign immunity, the prime contractor is not and thus requires indemnification

SUBCONTRACT RED FLAG PROVISIONS


48-Hour and 72-Hour Clauses Pertains to the contractors right, after directing the subcontractor to remedy some default, to perform the necessary work with contractors forces for the account of the subcontractor if the subcontractor fails to remedy the default within 48 hours of receipt of contractors directive

INSURANCE CONTRACTS
Primary parties Construction Contractor the insured Insurance Company the carrier Additional Parties additional named insured Policies for the construction industry Workers compensation and employers liability policies Public (or third-party) liability policies Builders risk policies Equipment floater policies Miscellaneous policies for special situations and needs

WORKERS COMPENSATION AND EMPLOYERS LIABILITY POLICIES


Statutory liability on employers which occurs when the employees are killed or injured in the course of performing their duties. The Workmens Compensation Act 1923 provides for compensation to workmen or their survivors in cases of industrial accidents and occupational diseases, resulting in disablement or death compensation in case of death ranges from Rs 50,000 to Rs 4.56 lakh and in the case of permanent total disablement from Rs. 60,000 to Rs. 5.48 lakh Employer's Liability Act, 1938

PUBLIC LIABILITY POLICIES


Public Liability Insurance Act, 1991 The essence of the public liability insurance contract is that the insurance company, in exchange for the premium, agrees to assume the liabilities of the insured contractor subject to a stated deductible amount, up to stated monetary limits of the policy. These policies do not protect contractors aginst contractually assumed business risks such as failure to complete the project.

PUBLIC LIABILITY POLICIES


Exclusions, Endorsements and Deductibles Exclusions like XCU Hazards ( Explosion, Collapse and Underground) Endorsements are special provisions added to the policy to extend its coverage Deductible is an amount stated in the policy that must be exceeded before the insurance company has any liability Monetary limits Primary and Umbrella policies Primary: tailored to meet the monetary limit requirements of the prime contract Umbrella: designed to raise the monetary limits to a much higher level

BUILDERS RISK POLICY


Also called as installation floater insurance Does not include consequential damages such as lost time or increased cost of performance It can be obtained as either a named peril or an all risk policy Traditionally cover losses to the contractors temporary structures in addition to the losses to the permanent work Does not cover contractors construction equipment or tools

EQUIPMENT FLOATER POLICIES


Protects the contractor against physical damage or loss to tools and construction equipment (including theft) Method of determining loss: Replacement value Book value Pre-agreed value Equipment floater insurance for Marine Equipment Operations Called as hull insurance http://www.uiic.co.in/mhull.jsp

MISCELLANEOUS POLICIES FOR SPECIAL SITUATIONS


Railroad protective insurance Transit insurance Business interruption insurance Fidelity and forgery insurance

Owner provided insurance programs

S-ar putea să vă placă și