a Case Study in New Australian Embassy in Jakarta (AEJ) Leighton Contractors Indonesia & Total Bangun Persada Joint Operation
Firdaus Basbeth
DMB Student of University of Padjadjaran Bandung QIK 2014 International Conference Ascot House Melbourne February 21 2014
LEAN
Chancery and Staff Residence, Jakarta Project Description The project is Total plot area 40,000m2, total covered floor area 50,106m2 of which 43,500m2 is building and 6,600m2 is pergola and parking. The scope of work includes Partial Design, Engineering, Procurement, Testing and Inspection, Construction a Compound, consisting of: o o o o o o o o o o Basement, plus 5 floor chancery building of approximately 26,700m2, Head of Mission residence, 32 number staff residences, Swimming pool, Recreation facilities, Guard houses, Ancillary service buildings, Landscaping, Security walls, All associated works in accordance with drawings, specifications.
The construction duration is 36 months until 2016. It is still ongoing and under close monitoring by project management.
INTRODUCTION
Construction traditional measure (Result Based) vs Performance Measurement System (Process Based) Construction Lean Improvement Program
Lean Thinking Seven Waste 5S Labor Competency Issue First Inspection Method
LITERATURE REVIEW
Reference
Saad Sarhan and Andrew Fox, (University of Plymouth, UK) (2012) Performance measurement in the UK construction industry and its role in supporting the application of lean construction concepts, Australasian Journal of Construction Economics and Building, 13 (1) 23-35
LITERATURE REVIEW
Reference
Alarcon and Serpell, 1996
LITERATURE REVIEW
Reference
Henny Pratiwi, M. Faiqun Niam, 2012.
Lean thinking is a philosophy based on the concepts of lean production, when applied to construction, it could lead to improved performance. Proposed the need to review construction production as a combination of conversion and flow processes to remove waste, when traditional thinking of construction was only focusing on conversion activities and ignoring flow and value considerations
LITERATURE REVIEW
Reference
FACTORS INFLUENCING CONSTRUCTION PRODUCTIVITY IN THE INDONESIAN CONTEXT
Sugiharto ALWI Senior Lecturer School of Graduate Studies Construction Management Program, Proceedings of the Eastern Asia Society for Transportation Studies, Vol.4, October, 2003
Henny Pratiwi, M. Faiqun Niam, 2012.
Lean Thinking
Lean thinking is a philosophy based on the concepts of lean production. Lean is focused on the achievement of three key outcomes: 1. Maximizing value from the view of the customer 2. Eliminating waste (non-value adding processes) 3. Creating smooth and reliable flow of activity.
Benefit
Tangible benefits Productivity 16 40 % Refurb lead time 25% Pre-construction lead time (time between client approval and start of works on-site) 48%
Intangible benefits Best practice set-up, methods introduced, operation & organization improvements, waste reduction, delays & disruptions reduced, snags reduced, communications improved, Team dynamics improved, partnering benefits, skills transfer in the industry
Implementation Strategy
1. 5S 2. Measuring and Monitoring the Performance of NCR Rework Waste 3. The First Inspection System 4. A Solid and updated QA Plan 5. Recruitment based on labor competency plus continual training.
5S
Strategy for creating a well organized, smoothly flowing process. It has been applied in the shop with great success. Masaaki Imai says, If one is not doing 5S, one is not doing lean.
Benefits of 5S
Increases organization and efficiency Avoids wasted motion Increases safety Eliminates unnecessary inventory Offers improvements at an inexpensive cost
METHOD
The research is a Case Study in Leighton Contractors Indonesia in New Australian Embassy Project (2013 2016) Primary and Secondary Data are gathered using both qualitative and quantitative approaches, and interview
RESULT
Total NCR and Root cause
RESULT
The Root cause
RESULT
Total NCR in Two Different Area
RESULT
Total NCR in Chancery
DISCUSSION
In the construction industry, defect or rework is a challenge that affects the productivity of a project. Additional resources are required ie: labor, materials, and energy beyond what is budgeted had the work been done right the first time not to mentioned potential risk with respect to quality and safety. The New Australian Embassy Project has in place and continually updates their Quality Plan. Improvement activities can be seen from the frequency of Non Conformance Report.(Rework required.) Training to up skill labor to LCI standards, Internal Quality Audits, and increased management attention has been a focus the last 6 months.
DISCUSSION
The New Autralian Embassy in Jakarta (AEJ) implemented the First Inspector System (FIS) by putting full responsibility of the quality of product delivered to the supervisor and foreman, so by the time the quality inspector come to check the work, the variation from specification will be the minimum. The results have seen the nonconformance reports reduce by 57%. The saving for the project is USD$20,000 or Rupiah 240mil.
DISCUSSION
The Construction Lean Improvement Program Works in Chancery Area in the Project. Suggestion to be Implemented in some others construction areas in the Project, with the additional strategy of : 5S, First Inspector System, Performance Monitoring (Process Based) Continual Training on the Labor to maintaining quality of the product. Buy in from Project Manager and its implementation strategy need to be in the first place stated in Quality Plan.
DISCUSSION
Rework / NCR Reduction in CLIP include the following processes: Rework tracking and main cause classification: detecting and identifying the rework that occurs and captured, investigate the causes in a database that used collaboratively by the client, contractors and designer.
Corrective action : developing options and actions that will bring about changes in the project management system with the goal of eliminating the root cause and reducing construction rework
Evaluation of the effectiveness of the corrective action taken.