Documente Academic
Documente Profesional
Documente Cultură
the start of the project with all the members of the project
team to identify all the risks.
Benefits:
Projects that utilize Risk Management to manage their risks are more
likely to receive benefits such as:
adherence to user requirements;
higher quality deliverables;
maintenance of project schedules;
Risk Assessment
Risk Assessment
Risk Assessment
Risk Assessment is the first of two stages in Risk Management and
includes three main steps as follows:
Identify: Review all the project plans and identify areas of uncertainty.
Analyze: Define how the identified areas of uncertainty could effect the
These steps are to be repeated in an iterative process until all known risks
are addressed.
Risk Identification
Risk Identification consists of determining which risks are likely to affect
the project and then defining the characteristics relating to each risk.
Risk identification is not a one-time process. It should be performed on a
regular basis throughout the course of the project. Identification of risks
should be an ongoing question at each project status meeting.
Risk identification needs to address both internal and external risks.
and roles;
The proposed technology has less functionality than promised;
The length of a project or project phase;
HIGH Likelihood and HIGH Impact: These are critical risks that will
have a severe impact and are more likely to occur.
2. LOW Likelihood and HIGH Impact: These are significant risks that
are not likely to occur but will have a material impact to the project if
they do.
3.
HIGH Likelihood and LOW Impact: These are significant risks that
may be able to be avoided with careful planning and monitoring.
Those that do occur however will have a low project impact which is
likely to be manageable.
4. LOW Likelihood and LOW Impact: Although these risks should still
Risks Priority
Using the risk categories, prioritize each risk for action in the order that it
is to be addressed (1 to 4).
Prioritization of risks enables the Project Manager and project team to
focus on the areas that are most likely to have the greatest impact to the
project.
Risk Control
Risk Control
Risk Control
Risk Control is the second stage in Risk Management and includes four
main steps as follows:
Risk Mitigation: Identify the necessary actions that can be carried out
in advance to reduce (or eliminate) the impact of the risk.
Risk Monitoring: Monitor and track all the risks identified and manage
them to successful resolutions.
Risk Mitigation
Risk identification, analysis and prioritization is only beneficial if actions
are defined and executed to mitigate the risk.
Risk mitigation actions must be defined individually for each risk. In
some cases, immediate action will be necessary. For other risks, future
plans and considerations will be more appropriate.
Risks can be mitigated not only by eliminating the risk but also by
reducing their degree of occurrence and/or lessen the Impact to the
project. It can be broken down into two components:
Risk Elimination
Risk Reduction
Risk Elimination:
Aggressive, proactive risk mitigation for top priority (1) risks is essential to
achieve the full benefits of Risk Management. For these critical risks it is
ideal if the risks can be eliminated entirely as they will have the greatest
negative impact to the project.
Example:
Risk: Project Sponsor has not been appointed.
Priority:1, High impact to the success of the project.
Mitigation: Appoint an executive member, with available time to devote to
the project as Project Sponsor.
Risk Reduction:
A reduction of the degree of occurrence, or lessening of the impact, can
be attained by actions early in the project.
Example:
Risk: Lack of training for testers
Priority:2, Low Likelihood and High Impact.
Mitigation: training should be provided prior to testing.
Risk Planning
A plan of action should be prepared for each high priority risk that is not
able to be proactively eliminated. An action plan will enable the project to
recover from or survive a risk's occurrence (a problem).
A plan should be prepared for each risk, identifying:
High priority risks are still likely to remain a High Risk. Even after being
addressed once, it may still re-occur at some time in the future
(eg: Staff leaving the project).
Risk Monitoring
Each risk that requires mitigation plan to be prepared should be assigned
to a member of the project team to monitor. The Risk Monitor will be
responsible to the Project manager for monitoring the risk, reporting any
change in condition, taking the agreed contingency action (Plan) if the
risk occurs.
Monitoring of Project Risks can be achieved by using the following
actions:
Risk Communication
Project decision makers and project team members are more likely to
respond to formally written information than on verbally communicated
project concerns.
A formally documented process will enable anyone involved or interested
in the project to be aware of the project risks.
It also assists the Risk Monitor's commitment to the monitoring and
mitigation of an individual risk.
Example
Sl. #
Risk Element
Sl. #
Risk Elements
Sl. #
Risk Elements