Documente Academic
Documente Profesional
Documente Cultură
Expressway
Is
It the
model project for all
Submitted
By:Shailesh Aggarwal, Sumit Aggarwal ,Rahul Tiwari, Mukesh
Sharma,
Vivek Parmar
stakeholders
INTRODUCTION
Stakeholders
Salient Features
Primary Issues
Traffic Congestion
Pedestrian Safety
WHY PPP??
Government Resources are not able to keep up with rising demand for social goods
Rapid Economic Growth, Growing Urban Population, Increased Rural-Urban Migration & All
round Socio-Economic Development are some causes
The above have led to increased the Infrastructural Pressures leading to a widened
demand-supply gap in Infrastructure
Political Economy of Infrastructure Shortages
Constrained Public Resources
Rising Civilian Pressure
Greater Efficiency
Greater Value for Money for Public Procurement (by reducing Lifecycle Costs)
Better Project Design & Implementation
Better Access to Project Finance (in light of drying government funding sources)
Rigorous Risk Appraisal (as benefits are reaped by Private party only if project
performs to its optimum standard)
Optimal Allocation of Resources leading to Better Cost Estimation & Investment
Decisions
Concession
Agreement
Issues
Single Independent Consultant for both Design & Construction Phase and Operations
& Maintenance Phase
High Expertise Consultant for D&C Phase and Low Expertise Consultant for O&M Phase were
generally selected. This practice was not adhered to.
There was provision of only 1 IC: RITES Corporation
The bidding process for Consultants was also anti-competitive and probably Unfair
Little or No Documentation Existed at the time of Contract for BOT basis (2002)
No inclusion of possible risks and complexities that could prop up in the project
Toll Charges fixed without basing it on Road Volume (Also included a Positive
Inflationary Tool for Toll Charges Increase insulated from the Traffic Volume)
Construction
Phase Issues
Land Acquisition
Precedent Conditions
Delay in shifting of cables and power lines which were pre-construction activities
No major residential relocation was envisaged as project was about highway upgradation
Majority of time spent on dealing with illegal commercial operations along the highway
Breach of Conditions Precedent related to Land handover, delays were made by NHAI
Further claims were made by DS Constructions. The initial cost to NHAI was INR 3 cr.
Additional claims also made. Excuse used to cover up 4 months delay in FC approval.
Relocation
Outdated DPR made in 1996 which had just the basic alignment drawings
Concession
Agreement
New Model
Tolling prohibited till Land used for Highway was made usable
Right of Way provision implemented, whereby 80% of the land acquired originally would be all
the land needed to obtain provisional certificate
A monthly paid pass could be charged for local traffic leading to lower toll revenues
Increased VGF mechanism to make projects viable
Local Acceptance important to mitigate potential for protests for Project to become a Model
Project
Claims in case of authoritys inability to provide resources were better dealt with
Safety Issues were clearly tackled
Based on Phased Development instead of High Cost Roads for catering to Projected Growth in
the Long Term
Concession Period determination was based on present and predicted future traffic
Cost of tree-felling and drawing up proper DPRs were made critical points with authorities
assisting in the former too
Financial Analysis
Toll Charges were received and not shared by the private party
If the total traffic count increased to more than 130,000, half the
total revenue would be shared with NHAI
Upfront Cost: INR 686.4 Cr (Concessionaire: INR 555 Cr)
Grant: INR (61) Cr.
NHAI Borne Cost: INR 131.4 Cr
Corporate Tax Rate: 33.66%, Minimum Alternate Tax: 11.2% ; Tax
Holiday for the 1st 10 years {Section 80(1a)}
Huge Profit Potential for Private Party, as estimated traffic count was
76000 while the actual was around 96000 passenger vehicles daily
An increase of 10,000 vehicles would lead to additional income of
INR 7.3cr @ Rs 20/car
No toll charges revision or concession period revisions were
envisaged creating huge possibility of profiteering by the private
party for a long time
Impact on
stakeholders
More than desired profits could be skimmed by DS Constructions
due to incorrect traffic projections
As toll prices could be changed with changes in WPI, DS Constructions
could also benefit if inflation rose, leading to perpetual growth in income
while the costs were more one time and upfront in nature
Greater Traffic counts could lead to huge gains being made by DS
Constructions
NHAI
No financial reward directly from Toll Collection till traffic count is below
130,000 leading to loss of potential income
RITES Corporation
No Financial implication on the performance of the highway
Patrons
With rise in inflation, toll prices would rise leading to greater outflow of
disposable income
Multiple/Local users of the highway had to fork out a huge amount till
the Model Concession Agreement was put in place
THANKS