Documente Academic
Documente Profesional
Documente Cultură
: GENITRPP13A-01
VITRIFIED TILING
Engineering cum Quality assurance manual
Name
Date
Prepared by
Vaibhav Kapoor
12-7-2014
Validated by
Ravi Kumar
14-7-2014
Table of contents
Classification of Tiles
Site storage / site handling
Tools and equipments required for
tiling
Laying of Tiles - Guidelines
Installation procedure
Pre installation
During installation
Post installation
Handover documentation
Common defects and remedies
Best Practices
References and Links
Classification of Tiles
Broadly Tiles Are Classified on the Basis
: 10 - 18 %
:36%
Classification of Tiles
While ordering;
Site store;
Tiles should be stored on a raised
platform to avoid staining of tiles
Vitrified tiles are heavy, need to be
stored in such a way that it doesnt
have adverse affect on structural slab
due to excess loading (as far as
possible vitrified tiles should be
stored at ground level)
Tiles of sizes more than 500 X 500
should
be
stored
in
vertical
conditions, with not more than 15
boxes in one line
Tiles of smaller sizes can be stored in
horizontal condition, with not more
than 10-12 tile boxes in one pile
As far as possible, re-handling /
shifting of stored tiles should be
avoided
Seek
guidance
/
help
from
Plumb bob
Laser level
Tile file
Measurement
tape
Spirit Level
Hoe
Shovel
Wheel barrow
Tile cutter
Trowel
Mortar mixing
tub
Grinder
machine
Cutter
machine
Rubber
hammer
Sponge
Tagari
Lay out a row of dry tile along one line from center to
the right wall.
If the last space is less than 1/2 a tile wide, return to the
center and move the first tile 1/2 a tile width to the left.
Mark the new "center point" and strike a new crossing
line at this mark (see Figure 2B)
Installation
Installation
Installation
Pre-installation
Installation
Installation
Quality of grout material
For flooring, use of epoxy grout is advised.
For walls and low traffic areas, use of cementitious
grout is advised.
In any case, specifications given by client / PMC
supersedes above given recommendations; take
necessary approvals before hand from client
Grouting material to be of approved make and shade
For walls, 2 mm spacer is recommended and for floors,
use of 3mm spacers is recommended
Installation
During installation
Floor tiles
Wet the base surface / substrate (Otherwise it would soak
water from the mortar; Also required for proper hydration of
cement mortar)
Provide proper bull marks on the floor and reference lines on
the walls
Check the start point of the tile from the drawing (Start point is
chosen in such as way that all cut tiles are either at the far end
of the entry, So that they not prominently visible or are hidden
below the furniture)
Determine the sizes of cut tiles; Reuse cut tiles in skirting /
flooring in other areas
Mortar mix should be preferably 1:6 (1 part cement mixed with
6 part sand)
Mortar spread should at least be up to arms stretch
Mortar mix should be well compacted before laying the tiles (If
not done properly, hollowness issue will occur)
Soak tiles in water for at least 2 hours to prevent it from
Installation
During installation
Floor tiles
Use cement slurry with cement content 2 kg per sqm slurry spread
Tiling direction is specified on the back surface of tiles; always to follow that
direction marking while doing tiling
Use rubber / wooden hammer to bring tile at exact level (With respect to adjoining
tiles)
Use rubber hammer to check the hollowness below the tiles
If found hollow, take out the tile and provide additional mortar bedding below the
tile
Check the level with spirit level with respect to adjoining tiles
Use appropriate spacers for tiling works
For raceway junction boxes, cutouts should be neatly plugged using cloth or plastic
Make sure the size of cut out in tile matches the exact location and requirement
Do not use pencil for marking on tiles, it may leave a permanent stain on tile
IMP: Masons and civil team should be educated to keep a check on defective tiles
while doing installation, if any deviations or bend is observed while setting out tiles
it should be immediately taken out. These tiles can be used for cut tiles / skirting.
Once the tiling is done, clean the top surface using sponge / cloth
Freshly done tiling should be barricaded for at least 2 days; no traffic / man entry
should be allowed during these 2 days
Installation
During installation
Wall tiles
Wet the base surface / substrate (Otherwise it would soak water
from the mortar; Also required for proper hydration of cement
mortar)
Check the start point of the tile from the drawing (Start point is
chosen in such as way that all cut tiles are either at the far end of
the entry, So that they not prominently visible or are hidden below
the furniture)
For wall tiling, proper curing is to be done for wall plastering before
proceeding with tiling, otherwise plaster would sock water from
cement paste and weaken the bonding with wall tiles)
Soak tiles in water for at least 30 minutes to prevent it from
soaking water from cement paste / mortar
Cement paste composition should be 1:1 (1 part cement and 1 part
water) {depends on tile sizes also}
Installation
During installation
Wall tiles
Use rubber / wooden hammer to bring tile at exact level
(With respect to adjoining tiles)
IMP: Masons and civil team should be educated to keep
a check on defective tiles while doing installation, if any
deviations or bend is observed while setting out tiles it
should be immediately taken out. These tiles can be
used for cut tiles / skirting.
Once the tiling is done, clean the top surface using
sponge / cloth
1/4 inch*3/16inch(6*5mm.)
Installation
Post installation
Barricade the area for at least 48 hours. No man entry
should be allowed during this time.
Clean the floor with sponge and a wiper after 2-3 hours
of flooring (Should not clean immediately otherwise it
would affect the tile quality)
If grouting is to be done, it should be taken up during the
end only.
Protect the floor with POP / bubble sheet / rubber sheet
Jointing
and finishing
Reason
Remedy
Joints should be
properly filled
Stain by other
trades if left
unprotected
Proper protection
once the work is
finished
Efflorescence (salts
with in substrate or
cement mortar)
Avoid excessive
wetting
Improper grouting
Proper grouting
material should be
used
Spillage of
chemicals
Avoid spillage
Reason
Remedy
Special treatment
required for cracks
External vibration
Allow movement
joints to avoid
damages due to
external vibration
(design
consideration)
Damage by other
trade after laying if
left unprotected
Proper protection
required
Reason
Remedy
Tiles with
dimensional defects
Mason to be
educated to check
tile dimensions
before final laying
Premature loading
onto freshly
completed tiling
No traffic
movement for initial
2 days after tile
laying
Insufficient /
excessive tapping of
tiles into position
Use rubber /
wooden hammer or
flat edge to avoid
unevenness
Insufficient leveling
of each tile
Reason
Remedy
Concrete surface /
substrate not
properly cured and
cleaned
Proper surface
preparation to be
done as specified in
installation checklist
Incorrect installation
of tiles; direction not
followed / improper
tapping / delay in
laying after mortar
has dried up
Tiles to be installed
as per installation
checklist
Tile surface to be
cleaned before final
laying
Hollow sound
Reason
Remedy
Air entrapped or
void inside the
cement mortar
bedding
Ensure proper
workman ship to
avoid void formation
Cement grouting /
nipple grouting
through joints
Separation of
adhesive membrane
between mother slab
and cement mortar
Use sufficient
bonding agents /
cement slurry while
laying tiles
Separation of
adhesive membrane
between cement
mortar and tile
Ensure proper
workmanship to void
non adhesion
Knowledge Portal
bca.gov.sg
iso.org
bis.org.in
cpwd.gov.in
https://www.youtube.com/results?search_query=how+to+
lay+tiles+on+floor+using+cement+mortar