Documente Academic
Documente Profesional
Documente Cultură
McGraw-Hill/Irwin
Master Production
Scheduling
An effective Master Production
Schedule (MPS) provides the basis
for making good use of
manufacturing resources, making
customer delivery promises,
resolving trade-offs between sales
and manufacturing, and attaining
the firms strategic objectives, as
reflected in the Sales and
Operations Plan.
5-2
Agenda
5-3
5-4
5-6
Resource
planning
Rough-cut capacity
planning
Detailed material
planning
Demand
management
Front End
Engine
5-7
MPS Algorithm
Aggregate production plan
Change production
plan?
Master production
schedule
Change requirements?
Change capacity?
Change master
production schedule?
No
Realistic
Is capacity
plan being
met?
Is execution
meeting the
plan?
Yes
Execute capacity plans
Execute material plans
5-8
January
Demand forecast
according to Aggregate
Plan for electrical motors
Week
February
1,500
1
1,200
4
100
100
500
100
500
300
100
450
450
100
5-9
Master Production
Scheduling Linkages
The MPS is the driver of all detailed
manufacturing activities need to meet output
objectives
The MPS is the basis for key inter-functional
trade-offs
Production
and sales
5-11
Time-Phased Record
10
15
25
30
32
32
27
10
10
10
10
10
Forecast
Projected available balance
Master production schedule
20
5-12
Period 1 5 plan
Period
On hand
Forecast
Projected available balance
20
10
15
15
10
32
22
30
hand
stockstock
=
Lot sizeOn
= 30
Safety
=5
On hand actual demand + production
= (20 + 0 10)
Period 2 6 plan
Period
On hand
Forecast
Projected available balance
10
20
20
20
15
20
-10
-20
-35
-55
30
Period
On hand
Forecast
Projected available balance
10
20
20
20
15
20
20
30
10
25
30
30
30
Additional production
orders in periods 2 and
5 to meet safety stock
requirements
5-14
Available-to-Promise
When immediate delivery is not expected (or
is not possible due to stockouts), a promised
delivery date must be established
The order promising task is to determine
when the shipment can be made
Available-to-promise (ATP) procedures
coordinate order promising with production
schedules
5-15
Available-to-Promise Logic
Discrete
Forecast
Period
Orders 1: Projected
available = Previous
Projected +
available
available
MPS balance
MAX(Forecast,
Orders)
Available-to-promise
Master production schedule
20
Period 3: Total
customer demand
Period
before next
3 production
4
5 = 2 units
10
15
15
10
32
22
12
Period 1: ATP =
Lot size = 30 Safety stock = 5 available balance
customer orders =
20 -8
28
30 Period 3: ATP =
MPS customer
orders = 30 -2
5-16
Available-to-Promise Logic
Cumulative
Forecast
Period
Orders 1: Projected
available = Previous
Projected +
available
available
MPS balance
MAX(Forecast,
Orders)
Available-to-promise
Master production schedule
20
Period 3: Total
customer demand
Period
before next
3 production
4
5 = 2 units
10
15
15
10
32
22
12
Period 1: ATP1 =
Lot size = 30 Safety stock = 5 available balance
customer orders =
20 - 8
40
30 Period 3: ATP =
3
ATP1 + MPS
customer orders =
12+ 30 - 2
5-17
ATPConsuming the
Forecast
is a conservative approach
Assumes that we will eventually sell at least the
forecast quantity
Adjusts for periods where demand exceeds the
forecast
5-18
MPS in Assemble-to-Order
Environments
In an assemble-to-order (ATO) environment, the
possible combinations of end items can be huge
Specific end item bills of materials (BOM) are
replaced with a planning bill of materials, which
represents the potential product combinations
One type of planning BOM is the super bill,
which describes the usage of options and
components that make up the average product
5-19
Wheels (2)
P/N 1003
Frame (1)
P/N 1004
5-20
Parts used in
all
configurations
are listed with
usage
probability of
1.0
orbs
s
b
a
ock
t
s
l mi x
a
y
t
u
t
e
f
c
Sa
in a
s
n
o
i
t
varia
5-21
Available-to-Promise Logic
with Planning BOM
Are the common
parts on the BOM
available?
Common Parts
Available?
No
Yes
Is the requested
gear option
available?
Gear
Available?
No
Try 1 period
later
Yes
Is the requested
Taylor option
available?
Taylor
Available?
No
Yes
Book order
5-22
Two-Level Master
Production Schedules
5-23
Period
On hand
40
40
40
40
40
Orders
42
37
23
48
88
48
88
48
Available-to-promise
48
20
80
80
80
80
10
Planning BOM
orders are the sum
of FAS orders
For planning BOM items
projected available
balance is always zero
because the item doesnt
actually exist
Period
On hand
Production Plan
100
100
100
100
100
Orders
100
72
54
Available-to-promise
28
46
100
100
100
100
100
100
100
Safety stock = 0
5-24
5-25
Planning Time
Fence
Minor changes
Sum
5-27
Principles
The MPS unit should reflect the business
environment and the companys chosen approach.
If a common ERP database is implemented, the
MPS function should use that data.
Regardless of the firms environment, effective
scheduling is facilitated by common systems, timephased processing, and MPS techniques.
Customer order processing should be closely linked
to MPS.
5-28
Principles
ATP information should be derived from the
MPS and provided to the sales department.
An FAS should be used to convert the
anticipated build schedule into the final build
schedule.
The master production scheduler should
ensure that the sum of the parts (the MPS) is
equal to the whole (the operations plan).
5-29
Quiz Chapter 5