Documente Academic
Documente Profesional
Documente Cultură
Management
EMBA
Strategy Implementation
Overview
Morning
Afternoon
Two advanced exercises
What is a project?
A project is a temporary endeavor undertaken
to create a unique result
What is PM?
Project management is the application of
knowledge, skills, tools, and techniques to
meet project requirements.
Now an IEEE Standard (IEEE1490)
Project Management Institute
Guide to the Project Management Body of Knowledge
(PMBOK)
Benefits
PM can:
Critical Variables
Scop
e
Time
Cost
Qualit
y/
Risk
Stages of PM
Initiating
Planning
Executing
Controlling
Closing
Project charter
A written statement of project scope that is
formally agreed with stakeholders and
shared with the team
Project Charter
Problem/opportunity
Project name, sponsor, manager
Singular Project Goal
Objectives that are Specific, Measurable,
Assignable, Realistic, Time based (SMART)
Work Breakdown Structure (WBS)
Success criteria
Assumptions, risks, obstacles
Scope Change
A process should also be defined for how scope
can be adjusted and the resulting impacts on
cost, time, and risk quantified.
WBS Process
Ideally a team-based activity (offline with
whiteboard)
Break the project into phases
By lifecycle, milestones, or obligations
Screen clipping taken: 10/29/2007, 12:43 PM
WBS by Output
Screen clipping taken: 10/29/2007, 12:56 PM
WBS by Phase
Exercise
In your teams, create a WBS for the EMBA
trip next year
Use MS Project to determine how early the
planning needs to start if the trip must start no
later than December 4, 2008
MS Project Skills
Extras
Risk, quality, staffing, communications
Note on Activities
Technically, the WBS contains only
deliverables not activities
The work packages need to be
decomposed into activities (even subactivities)
Choos advice is useful 1 person for 1
to 10 days
Activity Sequencing 1
Once the activities have been defined
they need to be sequenced
Activity Sequencing 2
Constraints (see advanced tab)
Do what? Start/Finish
When? No earlier than/ No later than/ On
this date / As Soon as Possible /As Late as
Possible
Lag time is also possible
Double click on a task to set all task
information
Activity Duration
Once sequencing has been done, the
work required for each activity has to
be estimated
Estimates based on experience/history
Time units m, h, d, w, mo
Work is the total number of actual, physical,
hands-on time required to complete an
activity or task
MS Project
By default,
One day equals 8 hours, one week equals 40
hours, and one month equals 20 working days.
8:00 A.M. to 5:00 P.M. is the default work day.
Change Tools:Options:Schedule
Default task type: Fixed work
Show assignment units as: Decimal
Calculating Duration
Duration = Work/Resource Units
If a resources workday is eight hours and he or she is
assigned to work on a task at 100% Units (for eight hours of
work), then the Duration is eight hours (one day by default).
Now lets say you change the Units to 50%. Then the
Duration becomes 16 hours or two days, because if a
person is working half of an eight-hour day on this task,
then it will take them 16 hours (two days) to complete eight
hours of work.
Network Diagrams
Working with units of time rather than
specific dates allows more flexibility
We have used Gantt charts, a project
network diagram is an alternative way of
representing a project.
Establishes the critical path
Contingency planning
Allows the team to tinker with alternate
dependencies and constraints
Network Diagram Example
Crashing
More resources but not all tasks can be
shortened with more resources
Management Reserve
Always reflect the accurate amount of time it
should take to complete a task
Dont inflate time to allow for mistakes, rework,
and late activities
Parkinsons law work will expand to fill the time
available
Assigning Resources
A resource is defined as any people, equipment,
or materials
View Resource Sheet, Table: Entry
Key variables
Type work (per hour), material (per unit), or cost (per
activity)
Max Units: 50% or 3 engineers
Rates per time period (m, d, mo, y) or per use
Double click for resource information
Flexible availability, costs, calendar
Accrual methods start, prorated, end
Exercise
Take your WBS from the first exercise
and convert it to a project schedule by
adding activities using the 8/80 rule
Assign resources
Keong, Dean Jarley, Jan, Bob, Travel Agent,
Other Internal & External Parties
Tracking
Tools to track include:
E-mail, spreadsheets, web forms, MS project
direct, MS project server
Tracking Finances
Term
Definition
Sample
Value
Budget at Completion
(BAC)
$100,000
20%
25%
%A x BAC
$20,000
%P x BAC
$25,000
$15,000
Tracking Finances
Term
Definition
Sample Value
Cost Variance
EV-AC
+$5000
Schedule Variance
EV-PV
-$5000
EV/AC
20/15 = 1.33
Schedule performance
index (SPI)
EV/PV
20/25=0.8
Estimate at completion
(EAC)
BAC/CPI
100/1.33=75.19
Estimated time
Total Est
time/SPI
6 mths/.8=7.5mths
Exercise
Complete Exercise 3b on page 310
AFTERNOON ACTIVITIES
In your teams, complete
the Blue Zuma Project Parts 1-5
The Conveyor Belt Project