Sunteți pe pagina 1din 64

August 14, 2003 Blackout

Summary Based on Interim Report of the


United States Canada Power Outage Task Force
November 19, 2003

U.S.-Canada Interim Report


Released November 19, 2003
Result of an exhaustive bi-national

investigation
Working groups on electric system, nuclear

plant performance and security


Hundreds of professionals on investigation
teams performed extensive analysis

Interim report produced by the teams

and accepted by the bi-national Task


Force
2

Overview
Overview of power system and

reliability
Pre-outage conditions on August 14
Trigger events and start of cascade
Wide area cascade
Root causes
Next steps

Power System Overview

Reliability Overview
Balance generation and demand
Balance reactive power supply and

demand
Monitor flows and observe thermal limits
Observe power and voltage stability limits
Operate for unplanned contingencies
Plan, design and maintain a reliable
system
Prepare for emergencies
Reliably operate the system you have!

3 Interconnections / 10 NERC Regions

NERC Control Areas

NERC Reliability Coordinators

Footprints of Reliability Coordinators in Midwest

NERC Immediate Response to Blackout


First hours
Worked closely with NERC Reliability

Coordinators
Identified what had tripped and extent
of outage
Assessed restoration efforts
Maintained open line with DOE/FERC
Communicated with DHS, White House,
and NRC

First days
Assigned project manager
Established Steering Group with

industry executive experts


Began organizing investigation teams
90+ volunteers + entire NERC staff

10

Investigation Organization Overview


U.S Canada
Task Force

Steering Group
Investigation
Team Lead
Project Planning and
Support

MAAC/ECAR/NPCC
Coordinating Group

Root Cause Analysis


Cooper Systems

NERC & Regional


Standards/Procedures
& Compliance

Sequence of Events

Restoration

Operations - Tools,
SCADA/EMS
Communications Op
Planning

NPCC

Data Requests and


Management

Frequency/ACE

MEN Study
Group

System Modeling and


Simulation Analysis

System Planning,
Design, & Studies

MAAC

ECAR

11

Investigation
Process Review

Vegetation/ROW
Management

Transmission System
Performance,
Protection, Control
Maintenance & Damage
Generator Performance,
Protection, Controls
Maintenance & Damage

Data Gathering and Analysis


Three fact-finding meetings
August 22
September 8-9
October 1-3
Onsite interviews and inspections
Secure database of outage information
Extensive corroboration of data to

determine facts
Analysis by teams of technical experts
12

Root Cause Analysis


Logical structure for investigating complex

problems
Identifies changes, conditions, actions, or
inactions at each causal step
Starts with final event and drills back
through each branch of causal tree.
Asks why? at each step.
Accurate, reliable, defensible understanding
of the root causes.

Successfully used to investigate root causes of PJM voltage stability condition


in July 1999 and established history in nuclear and defense industries.

13

Root Cause Analysis Phases


16:15

BLACKOUT

16:06
Initial Focus

Sammis Star
Star South Canton
Hanna Juniper
Chamberlin - Harding

15:05
Pre-Existing Conditions
E.g. voltages, wide- area transfers,
line and generator outages, etc.

14

August 14 Conditions Prior to Blackout


Planned outages
Cook 2, Davis Besse nuclear plants
East Lake 4, and Monroe 1
Transfers high to northeast U.S. + Ontario
Not unusually so and not above transfer limits
Critical voltage day
Voltages within limits
Operators taking action to boost voltages

Frequency
Typical for a summer day
System was within limits prior to 15:05, on

both actual and contingency basis

15

Warm But Not Unusual for August

16

August 14 Imports to Northeast-Central Compared


to 6/1 to 8/13/2003

17

Voltages Prior to 15:05 EDT August 14

18

Frequency Typical for Summer Day

19

Blackout was NOT Caused by

Heavy wide-area transfers


Low voltages, voltage collapse
Lack of IPP voltage/reactive support
Frequency anomalies
Cinergy outages starting at 12:08
East Lake 5 trip at 13:31
Contributing factor to later events, but not by

itself causal to the blackout

DPL Stuart-Atlanta trip at 14:02


Contributing factor to loss of MISO real-time
monitoring, but not electrically significant
20

Outage Sequence of Events


Transmission Map Key
ONTARIO

21

Transmission Lines
765 kV
500 kV
345 kV
230 kV

East Lake 5 Trip: 1:31:34 PM


ONTARIO

22

East Lake 5 Exciter Failure Causes Trip

23

Stuart Atlanta Trip: 2:02 PM


ONTARIO

24

MISO State Estimator and Reliability Analysis


MISO state estimator and contingency

analysis ineffective from 12:37 to 16:04


State estimator not solving due to missing

information on lines out in Cinergy then DPL


Human error in not resetting SE automatic
trigger

Using Flowgate Monitoring tool to

monitor conditions on previously


identified critical flowgates

25

FirstEnergy Computer Failures


14:14 Alarm logger fails and operators are not aware
No further alarms to FE operators

14:20 Several remote consoles fail


14:41 EMS server hosting alarm processor and other

functions fails to backup


14:54 Backup server fails

EMS continues to function but with very degraded

performance (59 second refresh)


FE system data passed normally to others: MISO and AEP
AGC function degraded and strip charts flat-lined

15:08 IT warm reboot of EMS appears to work but

alarm process not tested and still in failed condition


No contingency analysis of events during the day
including loss of East Lake 5 and subsequent line
trips

26

Phone Calls to FirstEnergy


FE received calls from MISO, AEP, and PJM

indicating problems on the FE system but did


not recognize evolving emergency
14:32 AEP calls regarding trip and reclose of Star-S.

27

Canton
15:19 AEP calls again confirming Star-S. Canton trip
and reclose
15:35 Calls received about spikes seen on system
15:36 MISO calls FE regarding contingency overload
on Star-Juniper for loss of Hanna-Juniper
15:45 FE tree trimming crew calls in regarding
Hanna-Juniper flashover to a tree
PJM called MISO at 15:48 and FE at 15:56 regarding
overloads on FE system

Chamberlin-Harding (3:05:41)

28

Chamberlin-Harding Indication of Ground Fault Due


to Tree Contact as Measured by DFR at Juniper

29

(3:05:41)

30

Hanna-Juniper
(3:32:03)

Hanna Juniper Confirmed as Tree Contact at


Less than Emergency Ratings of Line

31

Effects of Ambient Conditions on Ratings

32

(3:05:41)

Star- S. Canton (3:41:35)

33

(3:32:03)

Situation after Initial Trips 3:05:41 3:41:35

ONTARIO

34

Canton Central Tidd


(3:45:41)
35

138 kV Lines Overload and Cascade Near


Akron

36

60

16:05:55 EDT

15:51:41 EDT

15:32:03 EDT

Dale-W.Canton 138 kV
W.Akron 138 kV Breaker
Chamberlin-W.Akron 138 kV

E.Lima-N.Finlay 138 kV

20

Sammis-Star
120

Canton Central Transformer

W.Akron-Pleasant Valley 138 kV

Babb-W.Akron 138 kV

HannaJuniper

Star-S.Canton 15:41:35 EDT

40

HardingChamberlin 15:05:41 EDT

37

E.Lima-New Liberty 138 kV

80

Cloverdale-Torrey 138 kV

100

% of Normal Ratings

138 kV Cascade Contributes Further


to Overload of Sammis-Star
140

Sammis-Star
(4:05:57.5)

38

Sammis-Star Zone 3 Relay Operates


on Steady State Overload

39

Actual Loading on Critical Lines

40

Actual Voltages Leading to Sammis-Star

41

Major Path to Cleveland Blocked after Loss of


Sammis-Star 4:05:57.5 PM

Remaining
Paths

42

345 kV Lines Trip Across Ohio to West


ONTARIO

43

Generation Trips 4:09:08 4:10:27 PM


ONTARIO

44

345 kV Transmission Cascade Moves North into


Michigan 4:10:36 4:10:37 PM

45

Northern Ohio and Eastern Michigan Served Only


from Ontario after 4:10:37.5 4:10:38.6 PM

46

Power Transfers Shift at 4:10:38.6 PM

47

Eastern Eastern Michigan (Detroit) Unstable


Voltage and Frequency Collapse and Pole Slipping
Ontario Michigan Interface Flow and Voltages Beginning 16:10:38

48

Generator Trips to 16:10:38

49

Generator Trips Next 7 Seconds

50

Overloads on PJM NY Ties 4:10:39 PM

51

PJM NY Separating 4:10:44 PM

52

Cleveland Toledo Island 4:10:39 - 4:10:46 PM


Cleveland Blacks Out

53

Northeast Completes Separation from Eastern


Interconnection 4:10:43 4:10:45 PM
North of Lake
Superior

54

Conditions at Niagara Indicate Progressively


Worsening Stability Conditions with Prior Events

55

Island Breaks Up: 4:10:46 4:13 PM

56

Frequency in Ontario and New York during Breakup


Niagara Generation Stays with Western NY

57

Generator Trips After 16:10:44

58

End of the Cascade

Some Local Load


Interrupted

Areas Affected by the Blackout


Service maintained
in some area

59

Blackout Root Cause Group 1


FE Situational Awareness
FE did not ensure a reliable system after

contingencies occurred because it did not


have an effective contingency analysis
capability
FE did not have effective procedures to
ensure operators were aware of the status of
critical monitoring tools
FE did not have effective procedures to test
monitoring tools after repairs
FE did not have additional high level
monitoring tools after alarm system failed
60

Blackout Out Root Cause Group 2


Vegetation Management
FE did not adequately manage tree

growth in its transmission rights of


way

61

Blackout Cause Group 3


Reliability Coordinator Diagnostics
MISOs state estimator failed due to a data

error.
MISOs flowgate monitoring tool didnt
have real-time line information to detect
growing overloads
MISO operators couldnt easily link breaker
status to line status to understand
changing conditions.
PJM and MISO ineffective procedures and
wide grid visibility to coordinate problems
affecting their common boundaries

62

Near-Term Industry Actions


Responses from Control Areas and
Reliability Coordinators Due December 15

63

Voltage support/reactive supply

Reliability communications

Computer failure response &


notifications

Emergency action plans and capabilities

Operator training for emergencies

Vegetation management

Next Steps
U.S./Canada Power Outage TF hearings
Public hearings to allow comment on report and
input on recommendations
December 4
December 5
December 8 Toronto

Industry technical conference


December 10 Philadelphia

NERC next steps


NERC executive committees December 11
NERC committees meet January 13-14
Continue investigation

Near term analysis and recommendations in support of U.S.


Canada Task Force
Long term analysis and recommendations for NERC

64

S-ar putea să vă placă și