Documente Academic
Documente Profesional
Documente Cultură
investigation
Working groups on electric system, nuclear
Overview
Overview of power system and
reliability
Pre-outage conditions on August 14
Trigger events and start of cascade
Wide area cascade
Root causes
Next steps
Reliability Overview
Balance generation and demand
Balance reactive power supply and
demand
Monitor flows and observe thermal limits
Observe power and voltage stability limits
Operate for unplanned contingencies
Plan, design and maintain a reliable
system
Prepare for emergencies
Reliably operate the system you have!
Coordinators
Identified what had tripped and extent
of outage
Assessed restoration efforts
Maintained open line with DOE/FERC
Communicated with DHS, White House,
and NRC
First days
Assigned project manager
Established Steering Group with
10
Steering Group
Investigation
Team Lead
Project Planning and
Support
MAAC/ECAR/NPCC
Coordinating Group
Sequence of Events
Restoration
Operations - Tools,
SCADA/EMS
Communications Op
Planning
NPCC
Frequency/ACE
MEN Study
Group
System Planning,
Design, & Studies
MAAC
ECAR
11
Investigation
Process Review
Vegetation/ROW
Management
Transmission System
Performance,
Protection, Control
Maintenance & Damage
Generator Performance,
Protection, Controls
Maintenance & Damage
determine facts
Analysis by teams of technical experts
12
problems
Identifies changes, conditions, actions, or
inactions at each causal step
Starts with final event and drills back
through each branch of causal tree.
Asks why? at each step.
Accurate, reliable, defensible understanding
of the root causes.
13
BLACKOUT
16:06
Initial Focus
Sammis Star
Star South Canton
Hanna Juniper
Chamberlin - Harding
15:05
Pre-Existing Conditions
E.g. voltages, wide- area transfers,
line and generator outages, etc.
14
Frequency
Typical for a summer day
System was within limits prior to 15:05, on
15
16
17
18
19
21
Transmission Lines
765 kV
500 kV
345 kV
230 kV
22
23
24
25
26
27
Canton
15:19 AEP calls again confirming Star-S. Canton trip
and reclose
15:35 Calls received about spikes seen on system
15:36 MISO calls FE regarding contingency overload
on Star-Juniper for loss of Hanna-Juniper
15:45 FE tree trimming crew calls in regarding
Hanna-Juniper flashover to a tree
PJM called MISO at 15:48 and FE at 15:56 regarding
overloads on FE system
Chamberlin-Harding (3:05:41)
28
29
(3:05:41)
30
Hanna-Juniper
(3:32:03)
31
32
(3:05:41)
33
(3:32:03)
ONTARIO
34
36
60
16:05:55 EDT
15:51:41 EDT
15:32:03 EDT
Dale-W.Canton 138 kV
W.Akron 138 kV Breaker
Chamberlin-W.Akron 138 kV
E.Lima-N.Finlay 138 kV
20
Sammis-Star
120
Babb-W.Akron 138 kV
HannaJuniper
40
37
80
Cloverdale-Torrey 138 kV
100
% of Normal Ratings
Sammis-Star
(4:05:57.5)
38
39
40
41
Remaining
Paths
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
61
error.
MISOs flowgate monitoring tool didnt
have real-time line information to detect
growing overloads
MISO operators couldnt easily link breaker
status to line status to understand
changing conditions.
PJM and MISO ineffective procedures and
wide grid visibility to coordinate problems
affecting their common boundaries
62
63
Reliability communications
Vegetation management
Next Steps
U.S./Canada Power Outage TF hearings
Public hearings to allow comment on report and
input on recommendations
December 4
December 5
December 8 Toronto
64