Documente Academic
Documente Profesional
Documente Cultură
TM 420 Notes
TM 420 Notes
TM 420 Notes
Resource Planning
The nature of the project and the
TM 420 Notes
TM 420 Notes
Cost Estimating
An important output of project cost
When Done
Why Done
How Accurate
Rough Order of
Magnitude
(ROM)
Provides rough
figure of cost for
selection
decisions
25%, +75%
Budgetary
Early, 12 years
out
10%, +25%
Definitive
Later in the
project, < 1 year
out
Provides details
for tendering,
estimate actual
costs
5%, +10%
TM 420 Notes
estimates:
analogous or top-down: use the actual
cost of a previous, similar project as the
basis for the new estimate;
bottom-up: estimate individual work
items and sum them to get a total
estimate;
TM 420 Notes
10
11
Computerized
design
Analysis of
Items & Costs
Cost Estimate
TM 420 Notes
12
TM 420 Notes
13
14
Cost Budgeting
Cost budget involves allocating the project cost estimate to individual work items and providing a
cost baseline;
A project budget provides information on the expected expenditure per project planning period;
A typical cumulative cost curve presents the expected cumulative project budget
TM 420 Notes
15
Cost Control
Project cost control includes
16
TM 420 Notes
17
18
Table 10-2 Earned Value Calculations for One Activity After Week One
Week 1
Week 2
Site Establishment
10,000
10,000
Weekly Plan
10,000
10,000
Weekly Actual
15,000
5,000
20,000
Cost Variance
-7,500
Schedule Variance
-2,500
Cost Performance
Index
50%
Schedule
Performance Index
75%
Activity
Total
TM 420 Notes
% Complete
after Week 1
Earned Value
after Week 1
(BCWP)
75%
7,500
19
Formula
Earned Value
Cost Variance
Schedule Variance
CPI=BCWP/ACWP
Schedule Performance
Index
SPI = BCWP/BCWS
20
TM 420 Notes
21
Excel file
TM 420 Notes
22
100,000
90,000
80,000
70,000
BCWS
60,000
50,000
ACWP
40,000
30,000
BCWP
20,000
10,000
1
10
11
12
Month
BCWS or Cumulative Plan
BCWP or Cumulative EV
Excel file
TM 420 Notes
23
TM 420 Notes
24