Documente Academic
Documente Profesional
Documente Cultură
Agenda
Options Summary
FEMA Analysis
BIA Analysis
Options Timelines
Page 2
Page 3
Throughout the project Rapid have had difficultly meeting any plans that they
have created
The repeated late delivery has impacted the project timeline and the confidence
in Rapids clam that SwiftSuite is proven tool for Upgrading to R12
Unproven process still needs to go through rigorous testing cycles before go live
Limited documentation and inability to control the data migration of the static
data suggest that this incremental process is high risk and could have a serous
impact on the business units if any problems occur
Letter of breach of contact sent on Mar 20, were they had 30 days to remedy the
breach however only 3 points have been addressed by Rapid and those 3 are still
not completed
Page 4
Low
Med
Med High
High
Benefits
Options
Ris
k
Options
Risks
Rapid
Upgrade
Conversion Continue
with Current
approach
Data
Synchronization
for Phased golive
Traditional
Upgrade
Revenue risk to
sites with all sites
live at the same
time
Rapid Upgrade
Noncompliance
with Flowserve
reporting/auditin
g & possible
unsupported data
after go-live
Benefits
Cost &
Timeline
Additional
cost with
expected
Current data in
P11i will be
available in R12
version
Go Live
Aug Oct
2013
or
Jan Mar
2014
Current data in
P11i will be
available in R12
version
Additional
cost with
expected
No risk related to
Go Live
migration or
The consensus is that the benefits that thesynchronization
Rapid approach offersSep
is 2013
or
outweighed by the level of risk that has been
found as we progressed
of data
Jan - through
2014
Summary
Recommendations
Stop with current Rapid approach as the offers significant risk
even if we complete the testing cycles
Start the legal process to clam for damages based repeated
late delivery that extended the project with at least a 4
month delay and pushed the go live into 2014
Continue with Pilot for the technical upgrade and bring in
additional resources to fix the custom code
Re-plan project for Jan 2014 go live based on the technical
approach
Ramp-up project team for an IT testing phase in May/June
Page 7
Appendix
FEMA Analysis
FEMA Analysis
BIA Analysis
BIA Analysis
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Page 14
Page 15