Illustration 1
A production line operating 450 minutes per
day is to have an output of 250 units per
day. Find the cycle time.
Illustration 2
The precedence diagram for assembly activities A through H is shown
below, with the element time requirements shown in minutes. The line
operates 7 hours per day, and an output of 600 units per day is desired.
Compute cycle time and (b) the theoretical minimum number of
stations.
Illustration 3
Using the data and precedence diagram from Illustration 2
(a) group the assembly-line tasks into an appropriate number
of workstations using the longest work-time rule, and (b)
compute the balance efficiency and (c) the idle time.
Illustration 4
Suppose the activities shown in Fig. are to be grouped into a threestation assembly line.
(I)What is the target cycle time?
(II) Which grouping of activities results in the largest output per
hour?
(III) What output will result in a 7 -hour day?
Illustration 5
Tasks A through I have the predecessor and time requirements
shown in Table. Output is to be 200 units per day, and operating
time is 450 minutes per day. Using the most successors rule to
assign tasks to work centers, and the longest work-time rule as a
tie breaker, (0) group the tasks into work centers, WCs, and
compute (b) the balance efficiency, (c) the idle time, and (d) the
balance delay.
Task
A
B
C
D
E
F
G
H
I
Predecessor
None
A
None
C
D
None
F
G
H
Time (see)
40
20
60
40
30
35
45
60
40
Fig. B
Time
Preceding
(sec)
Task(s)
10
None
24
None
17
49
12
14
27
20
F, G
23
D, H, I
36
18
J, K