Project Management

Plan
PROJECT:
BUS TRACKING SYSTEM

PREPARED BY:
PRINTECH CO SDN. BHD.

Project description
Twitterjaya company has recently approved PrinTech to develop
a bus tracking system which passengers and bus conductor can use
the tracking device to performs tracking function of the system.

This function should enable passenger and bus conductor to use


the device to track and get information of their location.

The tracking function of the bus tracking system server will


included highly capacity performance service.

The Twitterjaya company can leverage our capability and


experience in tracking system to increase their bus services by
capitalizing on new, effective and easy to use tracking technology.

Project Scope
The bus tracking system able to do tracking function and make
a record to the server database.

The tracking and displaying information service is able to


function correctly and avoid of lagging problem due to real-time
service and transaction.

The displayed information will be sorted correctly according to


the exact location.

Constant update and system maintenance to the system to clear


cache data and system capacity.

Milestone List
Milestone

Description

Date

Complete Requirements
Gathering

All requirements for bus tracking system must be determined to


base design upon

30/03/2015

Complete Bus Tracking System


Design

This is the theoretical design for the software and its


functionality

06/04/2015

Complete Develop Bus Tracking


System Hardware

Develop compact module of tracking device and integrate into


bus equipment.

08/05/2015

Complete Bus Tracking System


Coding

All coding completed resulting in software prototype after


connects with the hardware.

10/06/2015

Complete Bus Tracking System


Testing and Debugging

All functionality tested and all identified errors corrected

17/07/2015

Complete Integration of Bus


Tracking System

Completed system hardware and software being set up


documentation transitioned to operations group to begin
production

11/08/2015

Complete Training Session

Training session for the company technician and administrator.

21/08/2015

Project WBS

COST BASELINE
Project Phase

Budget Total

Comments

Planning

RM 5000

Includes work hours for all project


team members for gathering
requirements and planning project

Design

RM5000

Includes work hours for all project


team members for work on Bus
Tracking System conceptual design.

Coding

RM5000

Includes all work hours for coding of


Bus Tracking System.

Testing

RM2500

Includes all work hours for testing of


Bus Tracking System

Transition and Closeout

RM2500

Includes all work hour for transition


to operation and project closeout.

Total

RM20 000

QUALITY
MANAGEMENT PLAN
The Project Sponsor is responsible for approving all quality standards
for the Bus Tracking System Project. The Project Sponsor will also
review all project tasks and deliverables to ensure compliance with
established and approved quality standards.
The Project Manager is responsible for quality management throughout
the duration of the project. The Project Manager is responsible for
implementing the Quality Management Plan and ensuring all tasks,
processes, and documentation are compliant with the plan. The Project
Manager is also responsible for communicating and tracking all quality
standards to the project team and stakeholders.
The Quality Specialists are responsible for working with the Project
Manager to develop and implement the Quality Management Plan.
Quality Specialists will recommend tools and methodologies for tracking
quality and standards to establish acceptable quality levels.

RISK MANAGEMENT
PLAN

QUALITY BASELINE
* The Bus Tracking System project must meet the quality

standards established in the quality baseline. The quality


baseline is the baseline which provides acceptable quality
levels of the Bus Tracking System project. The software
must meet or exceed the quality baseline values in order to
achieve success.

Lesson learned
Project management plan is important in developing a
large project so that we can complete the project within
timeframe
It is crucial to make sure that one team can work
together and give cooperation. This is because if one
member did not do their work, it will effect the progress of
the project
Project manager should assign responsibility to the
correct people in completing a specific task.

THANK YOU!