Overview of a DAM
Dam is the most expensive
multipurpose civil engineering
construction.
It delivers beneficial results for a long
time to mankind
A dam failure can create
unprecedented gargantuan havoc to
life and property through lightning
floods.
Geotechnical Considerations
The exact location where the dam
should be placed against the river
along its longitudinal profile.
The type of dam that will be most
suitable for that particular site.
The availability, cost and quality of
the materials required for the
construction of the dam.
Selection of sites
Topography: The most suitable site should have
a narrow gorge or a small valley with enough
catchment area available behind it to ensure
minimum uprooting of population, loss of
cultivable land due to submergence.
Technically the site should be strong,
impermeable and stable.
Availability of construction materials
Economically realistic and justified.
Environmentally, the site should not cause
ecological disorder.
Detailed Investigation
Surface Investigation:
Lithology: The important factor in the lithological studies is
to prepare a geological map of the area by undertaking
extensive field work and noting carefully the outcrops,
their attitudes, thicknesses of different beds, their
succession, intrusion if any, and their arrangement
Weathering, soil occurrences, their extent and depth,
availability of construction materials should be recorded
Laboratory studies: provide engineering properties such
as compressive and tensile strength, porosity, ,
permeability, and durability
Petrograhical analysis of thin sections of rocks to
determine the mineralogy.
Detailed Investigation
Structure: Study in detail and mark accurately on
the map the various rock types, the attitude of the
beds (strike and dips) and structural features such
as folds, joints, foliation, rock cleavage and
unconformities.
These details indicate the scope of leakage of water,
the stability and the durability of the dam
Topography: detailed topographical studies help in
knowing the stability, economy and safety of the
site.
Ground water conditions: detail investigation of
aquifer characteristics.
Detailed Investigation
Subsurface Investigation: Planned
geological and geophysical
investigations help in interpreting the
subsurface conditions fairly
accurately.
Suitable trenches, pits, boreholes
and coring are made at a few places
to get information about the actually
existing geological conditions at
those places.
Practical Problems
An earth dam with a 45000 cubic meters is to be built
from a sandy clay soils trucked from a borrow pit. The
water content of the sandy clay soil in the borrow pit is 15
% and its void ratio is 0.69. the specification requires the
earth dams embankment be compacted to a dry unit
weight of 18 kN/cu.m. Specific gravity of solid particles
=2.7
Determine a) the weight of sandy clay soil from the
borrow pit required to construct the embankment.
B) the number of 10,0 cubic meter truckloads of sandy
clay soil required for the construction
C) the weight of water per truckload of sandy clay soil.
D) the degree of saturation of the sandy clay soil in situ
Earth dams
Solution:
Step 1. calculate the unit weight for the borrow pit material
d =Gsw/(1+e) = 2.7 *9.8/(1+0.69) =15.7kN/cu.m
Step 2 Determine the weight of borrow pit soil required. d
reqd./d borrowed =18*45000 = 81000 kN
Step 3. Determine the number of trucks required.
Number of trucks =18*45000/157=5159.24 =5160
Step 4. Determine the weight of water required.
Weight of dry soil in one truckload (Wd) = 10*15.7 =157 KN
Weight of water wWd =0.15*157 = 23.6 kN
Step 5 Determine the degree of saturation s=wGs/e
0.15*2.7/0.69 =59 %