Documente Academic
Documente Profesional
Documente Cultură
TEA
TURKISH ELECTRICITY
TRANSMISSION CO.
By YILDIZ DURUKAN
Installed Capacity
Annual Consumption
Hydro+Renewable
(13394+147)MW
Thermal
(27235MW)
40,777 GW
33,21 %
66,79 %
189.45 TWh
8,8 % increase
Peak Demand
29,249 MW
Transmission System
(2007)
Transmission
Voltages
400, 154 & 66 kV
Transmission Lines
OHL
46,150 km.
400kV
220kV
154kV
66kV
No.220
No.2
No.1010
No.25
14307km.
84km.
31279km.
477km.
Cables
400kV
154kV
No.1
No.34
12.8km.
142.2km.
Transmission System
(2007)
Substations
Voltage (kV)
S/S No.
Transformer No.
380
61
152
28.465
154
458
957
52.345
66
15
56
662
TOTAL
534
1165
81.472
53.007
5
GW
TWh
2008
33
206
2009
36
223
2010
39
242
400 kV Network
BULGARIA
BLACK SEA
DIMODICHEV
HABPLER
BATUM
GEORGIA
BABAESK
HAMTABAT
KTELL
EC
E
GR
E
FILIPPI
ALBEYKY
A.ALANI
D.PAA
KAPTAN
UNIMAR
AMASRA
Y.TEPE
AMBARLI
BEYKOZ PAAKY
Z.KY
MRANYE
TEPEREN
ADAPAZARI
EREL
OSMANCA
AYIRHAN
KARABGA
SNCAN
GKEKAYA
ALTINKAYA
HOPA
BORKA
ARAMBA
ANKIRI
ADA-GEBZE
BOYABAT
KARABK
Armenia
KARS
YUSUFEL
KALKANDERE
TREBOLU
H.UURLU
KAYABAI
HSAR
GUMRI
DERNER
BURSA
BALIKESR
TUNBLEK
SOMA
KARGI
SEYTMER
TEMELL
GLBAI
ARI
SVAS
DEEKO
KANGAL
D.BEYAZIT
ERZURUM
BAZARGAN
VAN
KEBAN
KOCATEPE
BABEK
HORASAN
ZLCE
KAYSER
GRST
IDI
R
KHOY
ELBSTAN
ALAA
MANSA
YELHSAR
KONYA
IIKLAR
UZUNDERE
HLVAN
DYARBAKIR
DENZL
AYDIN
YENKY
IRAN
KARAKAYA
YATAAN
ADANA
OYMAPINAR
KEMERKY
ATATRK
ANDIRIN
KAVAK
SEYDEHR
G.ANTEP
ERZN
BRECK
ERMENEK
VARSAK
BATMAN
ILISU
DOANLI
.URFA
KIZILTEPE
CZRE
HAKKAR
UKURCA
PS3
ZAKHO
KESEK
MERSN
SKENDERUN
SDEMR
IRAQ
TEA 2008
TPP (PLANNED)
HATAY
HALEP
TPP (EXISTING)
HPP (PLANNED)
MEDITERRENEAN
SYRIA
HPP (EXISTING)
TL (EXISTING)
TL (PLANNED)
220 kV TL
154 kV TL
Synchronous Blocks
UCTE
Turkiye
SEMB
NORDEL
UK
IRELAND
IPS/UPS+Baltic States
Interconnections
Bulgaria
3000 MW
300 MW
Georgia
2000 MW
Armenia
100 MW
100 MW
100 MW
Iran
Turkey
450 MW
350 MW
1000 MW
400 kV Exisitng
220 kV Esisting
154 kV Existing
Iraq
Syria
Connection to UCTE
10
Objective
Get benefit of synchronous parallel
operation
Integration of the Turkish Electricity
Market in to Internal Electricity Market of
EU
11
Background
12
Background-2
Following the request of TEA for
synchronous connection and membership,
relevant application made by PPC to UCTE
Decision of UCTE Steering Committee:
13
Subgroup
Identified strategies, technical
prerequisites and sequence of operation
Defined further studies & preliminary tests
needed
Prepared Terms of Reference (TOR) of
Second Phase Activities
Approved by UCTE Steering Committee
Meeting of Bratislava on April 2002
14
Activities
15
Projects Developed
1.
2.
16
17
Project 1
Service Contract
was signed on 28 Sept.
2005
18
Studies
Budget
: 1.5 Million
19
TURKEY-UCTE connection
scheme
MARITSA 2
HAMTABAT S/S
400kV
90 km 3B 954 MCM
PLOVDIV
MARITSA 3 S/S
400kV
ALIBEYKY
250 MVA 380/154
77 km 2B 954 MCM
21 km 2B 954 MCM
BULGARIA
GREECE
THESSALONIKI
12 km 2B 954 MCM
THESSALONIKI
FOSFORKA PP
KAPTAN D.
S/S
400kV
ENELKO PP
FOSFORKA PP
KEHROS S/S
400kV
ENELKO PP
87 km 2B 954 MCM
2 x 150 MVA
380/154
PHILIPPI S/S
400kV
TURKEY
1 km 2B 954 MCM
14 km 2B 954 MCM
14 km 3B 954 MCM
BABAESK S/S
400kV
HABPLER
74 km, 3B 954 MCM
KTELL
UNIMAR S/S
400kV
20
Exchange patterns
Ukraine
Slovakia
Austria
Slovenia
Austria
Moldova
Hungary
Ukraine
Slovakia
Moldova
Hungary
Slovenia
Romania
Romania
Croatia
Croatia
BIH
BIH
SCG
Bulgaria
Italy
Black Sea
SCG
Black Sea
Italy
Bulgaria
Georgia
Georgia
Makedonia
Albania
Makedonia
Albania
Arm
Greece
enia
Arm
Azerbajan
Greece
Turkey
enia
Iran
Iran
MEDELEC/
20-21 March 2008, Casablanca
Syria
Azerbajan
Turkey
Iraq
Iraq
Syria
21
Transfer Capability
results
22
limiting factors
23
24
TASK 2
WAMS
MODEL OF TURKISH
POWER SYSTEM
TASK 3
TRANSIENT
STABILITY
TEIAS
RTE
RWE
TEIAS
RWE
NEK
HTSO
TEIAS
Yildiz Durukan
(TEIAS)
Philippe Carpentier
(RTE)
Martin Lsing
(RWE)
TASK 4
STEADY STATE
STABILITY
TASK 5
DAMPING
MEASURES
E.ON
RWE
RTE
E.ON
RWE
TEIAS
Wilhelm Winter
(E.ON)
Christian Lemaitre
(RTE)
25
TASK 1: WAMS
BULGARIA
BLACK SEA
HABPLER
BABAESK
HAMTABAT
BATUM
GEORGIA
ALBEYKY
KTELL
KAPTAN
A.ALANI
D.PAA
BEYKOZ PAAKY
FILIPPI
UNIMAR
AMASRA
Y.TEPE
Z.KY
MRANYE
TEPEREN
ADAPAZARI
AMBARLI
EREL
OSMANCA
AYIRHAN
KARABGA
SNCAN
GKEKAYA
ALTINKAYA
HOPA
BORKA
ARAMBA
ANKIRI
ADA-GEBZE
BOYABAT
KARABK
ARMENIA
KARS
YUSUFEL
KALKANDERE
TREBOLU
H.UURLU
KAYABAI
HSAR
GUMRI
DERNER
IDIR
BURSA
BALIKESR
TUNBLEK
SOMA
KARGI
SEYTMER
TEMELL
GLBAI
ARI
SVAS
DEEKO
KANGAL
D.BEYAZIT
ERZURUM
KAYSER
GRST
UZUNDERE
MANSA
KOCATEPE
BAZARGAN
VAN
KEBAN
ALAA
BABEK
HORASAN
ZLCE
KHOY
ELBSTAN
IRAN
KARAKAYA
IIKLAR
YELHSAR
KONYA
DENZL
HLVAN
DYARBAKIR
BATMAN
AYDIN
YENKY
KAVAK
SEYDEHR
DOANLI
ILISU
ATATRK
ANDIRIN
HAKKAR
UKURCA
YATAAN
PS3
KEMERKY
OYMAPINAR
VARSAK
G.ANTEP
ADANA
ERMENEK
ERZN
.URFA
BRECK
KIZILTEPE
CZRE
ZAKHO
KESEK
SKENDERUN
IRAQ
SDEMR
MERSN
TEA 2006
HATAY
TPP (PLANNED)
HALEP
MEDITERRANEAN SEA
Presently Remote-Access to Sincan, Borca, Yatagan, Babaeski, Keban
TPP (EXISTING)
SYRIA
HPP (PLANNED)
HPP (EXISTING)
WAMS
400 Kv TL (EXISTING)
400 kV TL (PLANNED)
220 kV T/L
26
10 sec.
Karakaya HEPP 600MW generation loss (7
March 2oo6)
MEDELEC/ 20-21 March 2
008, Casablanca
27
T1,45 sec.
1 sec.
28
Dynamic Data
29
Generation outage
Karakaya (660MW) on
07-03-2006
30
31
(pre-disturbance)
P-transfer
(static)
CFCT
N-scheme
Hamitabat-Maritsa 1
1100 MW 300ms - 400ms
Hamitabat-Maritsa 2
Babaeski-N.Santa
(N-1) schemes (maintenance or after contingency)
Hamitabat-Maritsa 1
1100 MW 300ms - 400ms
Hamitabat-Maritsa 2
Hamitabat-Maritsa 1
1100 MW
110ms
Babaeski-N.Santa
Hamitabat-Maritsa 2
1100 MW
160ms
BabaeskiN.Santa
Prevention of fast
Transmission
P-transfer
voltage collapse
Reliability Margin admissable
required RFCT Limitation P-transfer
(stability)
< 120ms
not necessary
250 MW
850 MW
< 120ms
not necessary
250 MW
850 MW
not possible
750 MW
250 MW
500 MW
not possible
750 MW
250 MW
500 MW
RESULTS (1)
BG TR two tie lines in service
MEDELEC/ 20-21 March 2
008, Casablanca
32
(pre-disturbance)
P-transfer
(static)
CFCT
N-scheme
Hamitabat-Maritsa 1
1100 MW 300ms - 400ms
Hamitabat-Maritsa 2
Babaeski-N.Santa
(N-1) schemes (maintenance or after contingency)
Hamitabat-Maritsa 1
1100 MW 300ms - 400ms
Hamitabat-Maritsa 2
Hamitabat-Maritsa 1
1100 MW
110ms
Babaeski-N.Santa
Hamitabat-Maritsa 2
1100 MW
160ms
BabaeskiN.Santa
Prevention of fast
Transmission
P-transfer
voltage collapse
Reliability Margin admissable
required RFCT Limitation P-transfer
(stability)
< 120ms
not necessary
250 MW
850 MW
< 120ms
not necessary
250 MW
850 MW
not possible
750 MW
250 MW
500 MW
not possible
750 MW
250 MW
500 MW
Maritsa
Hamitabat
Babaeski
N.Santa
Felipi
MEDELEC/ 20-21 March
2
008, Casablanca
TURKEY
33
Interface
SPS-PHASE 1:
SPS-PHASE 2:
Controlled System
Separation
based on angel separation between
Turkey and UCTE
Maritsa
Generator Rejection
PMU
PMU
Hamitabat
Babaeski
N.Santa/
Thessaloniki
TURKEY
34
35
36
37
38
39
existing AVR
40
41
42
and/or
43
Conclusions
The power transfer from Turkey to UCTE must not exceed 500
MW during the trial operation
44
45
Objective:
46
Organisational chart
TASK 1 (20%)
Survey of the
power plants
Field tests
EMS
ESO
EUAS
RTE
TEIAS (TUBITAK,
ABB; VaTech)
TASK 2 (25%)
Design of governor
control and
parameter
optimization
ESO (Univ. Varna)
RTE
RWE (Univ. Rostock)
TEIAS (TUBITAK, ABB,
VaTech)
TASK 4 (20)
TASK 5 (15%)
Design/
Optimisastion of
AVR/PSS
ESO (Univ. Varna)
RWE
TEIAS (VaTech, TUBITAK)
SwissGrid (Univ. Rostock,
ABB )
Task leader: SwissGrid
Special Protection
Scheme
Restoration Plan
ESO
HTSO
TEIAS(METU, Univ.
Rome)
TERNA
Task leader: ESO
TASK 3 (10%)
Secondary Control
EMS
ESO
HTSO
Swissgrid (Univ. Rostock)
TEIAS (METU, Siemens)
Task leader: HTSO
TASK 6 (10%)
Training
RTE (EDF)
TEAIS (TUBITAK, METU)
47
Next Steps
Association Agreement
Service Contract
48
Project Group
49
50
51
Time table
52
Regional Interconnection
Project
53
Medring
Turkey-UCTE
Recent developments
11
Turkey-Syria
6 years delay in
Syrian side
1997
Connecti
on of
MoroccoTunusiaAlgeria to
UCTE
Tunusia-Libya
Trial operation
with UCTE, on
21 November
2005
1998
Egypt-Libya
connection
54
UCTE Strategy on
MEDRING
Synchronous parallel operation of
UCTE
MASREK
MAGREP
IRAQ
TURKEY
11
3
2
MEDELEC/ 20-21 March 2
008, Casablanca
55
Turkey-Syria Connection
Until Closing MEDRING
UNIT COMMINTMENT
2006
Max. 400MW power export from Birecik
PP
Total 134.4GWh/(Nov.-Dec.2006)
2007
Max. 400MW power export from Birecik
PP
Total 972.2GWh/yearMEDELEC/ 20-21 March 2
008, Casablanca
56
Turkish-Iraq Connection
Until Closing MEDRING
Passive Island mode
2006
Passive Island
57
Conclusions-1
58
Conclusions-2
59