Sunteți pe pagina 1din 59

CONNECTION TURKEYUCTE

TEA
TURKISH ELECTRICITY
TRANSMISSION CO.
By YILDIZ DURUKAN

MEDELEC/ 20-21 March 2008, Casablanca

Turkish Power System

MEDELEC/ 20-21 March 2008, Casablanca

Generation & Demand


(2007)

Installed Capacity

Annual Consumption

Hydro+Renewable
(13394+147)MW
Thermal
(27235MW)

40,777 GW
33,21 %
66,79 %

189.45 TWh

8,8 % increase

Peak Demand

29,249 MW

(24th Dec.2007. 17:40h)

MEDELEC/ 20-21 March 2


008, Casablanca

Transmission System
(2007)
Transmission

Voltages
400, 154 & 66 kV
Transmission Lines

OHL

46,150 km.

400kV
220kV
154kV
66kV

No.220
No.2
No.1010
No.25

14307km.
84km.
31279km.
477km.

Cables

400kV
154kV

No.1
No.34

MEDELEC/ 20-21 March 2


008, Casablanca

12.8km.
142.2km.

Transmission System
(2007)
Substations
Voltage (kV)

S/S No.

Transformer No.

Installed Capacity (MVA)

380

61

152

28.465

154

458

957

52.345

66

15

56

662

TOTAL

534

1165

81.472

Installed Capacity for the Customers


MEDELEC/ 20-21 March 2
008, Casablanca

53.007
5

Load Forecast (08-10)


Year

Peak Demand Consumption

GW

TWh

2008

33

206

2009

36

223

2010

39

242

MEDELEC/ 20-21 March 2


008, Casablanca

400 kV Network
BULGARIA

BLACK SEA

DIMODICHEV

HABPLER

BATUM

GEORGIA

BABAESK
HAMTABAT
KTELL

EC
E
GR
E

FILIPPI

ALBEYKY
A.ALANI

D.PAA

KAPTAN
UNIMAR

AMASRA

Y.TEPE

AMBARLI

BEYKOZ PAAKY
Z.KY
MRANYE
TEPEREN
ADAPAZARI

EREL
OSMANCA

AYIRHAN

KARABGA

SNCAN

GKEKAYA

ALTINKAYA

HOPA
BORKA

ARAMBA

ANKIRI

ADA-GEBZE

BOYABAT

KARABK

Armenia

KARS

YUSUFEL

KALKANDERE

TREBOLU

H.UURLU

KAYABAI

HSAR

GUMRI

DERNER

BURSA
BALIKESR
TUNBLEK
SOMA

KARGI
SEYTMER

TEMELL

GLBAI

ARI

SVAS
DEEKO

KANGAL

D.BEYAZIT

ERZURUM

BAZARGAN

VAN

KEBAN

KOCATEPE

BABEK

HORASAN

ZLCE

KAYSER

GRST

IDI
R

KHOY

ELBSTAN

ALAA
MANSA

YELHSAR
KONYA

IIKLAR
UZUNDERE

HLVAN

DYARBAKIR

DENZL

AYDIN

YENKY

IRAN

KARAKAYA

YATAAN

ADANA

OYMAPINAR

KEMERKY

ATATRK

ANDIRIN

KAVAK

SEYDEHR

G.ANTEP
ERZN

BRECK

ERMENEK
VARSAK

BATMAN
ILISU

DOANLI

.URFA
KIZILTEPE

CZRE

HAKKAR
UKURCA

PS3
ZAKHO

KESEK
MERSN

SKENDERUN

SDEMR

IRAQ

TEA 2008
TPP (PLANNED)

HATAY
HALEP

TPP (EXISTING)
HPP (PLANNED)

MEDITERRENEAN

SYRIA

HPP (EXISTING)
TL (EXISTING)
TL (PLANNED)
220 kV TL
154 kV TL

MEDELEC/ 20-21 March 2


008, Casablanca

Synchronous Blocks
UCTE
Turkiye
SEMB
NORDEL
UK
IRELAND
IPS/UPS+Baltic States

MEDELEC/ 20-21 March 2


008, Casablanca

Interconnections
Bulgaria
3000 MW
300 MW

Georgia

2000 MW

Armenia
100 MW
100 MW
100 MW
Iran

Turkey
450 MW
350 MW
1000 MW

400 kV Exisitng
220 kV Esisting
154 kV Existing

Iraq
Syria

MEDELEC/ 20-21 March 2


008, Casablanca

Connection to UCTE

MEDELEC/ 20-21 March 2008, Casablanca

10

Objective
Get benefit of synchronous parallel
operation
Integration of the Turkish Electricity
Market in to Internal Electricity Market of
EU

MEDELEC/ 20-21 March 2


008, Casablanca

11

Background

Since the 70s studies have been performed for


various interconnection options between the
networks of GR, TR & BG.
Tie lines were built with all neighbouring
countries.

None of the tie lines have been operated in


synchronism.

By 90s the studies revealed that the projects for


the synchronous connection of the Turkish power
system to UCTE is feasible and viable.

through Bulgaria and Greece

MEDELEC/ 20-21 March 2


008, Casablanca

12

Background-2
Following the request of TEA for
synchronous connection and membership,
relevant application made by PPC to UCTE
Decision of UCTE Steering Committee:

Consider all possibilities of synchronously


interconnecting the Electric Power System of
Turkey to the UCTE Network.

A subgroup was formed in the frame of


WG System Development of UCTE to
tackle with the issue of connection of
Turkey
MEDELEC/ 20-21 March 2
008, Casablanca

13

Subgroup
Identified strategies, technical
prerequisites and sequence of operation
Defined further studies & preliminary tests
needed
Prepared Terms of Reference (TOR) of
Second Phase Activities
Approved by UCTE Steering Committee
Meeting of Bratislava on April 2002

MEDELEC/ 20-21 March 2


008, Casablanca

14

Activities

Complementary Technical Studies (Static-Dynamic)

Prepare some reports about the Turkish Power system

PG revised and added some more reports to the ones defined


in TOR

Tests on Generation Units

Preliminary monitoring of the Turkish Power System

MEDELEC/ 20-21 March 2


008, Casablanca

15

Projects Developed
1.

2.

Complementary Studies for the


Synchronisation of Turkish Power System
with UCTE System
Rehabilitation of the Frequency Control
Performance of Turkish Power System for
Synchronous Operation with UCTE

MEDELEC/ 20-21 March 2


008, Casablanca

16

Details about Project-1

MEDELEC/ 20-21 March 2008, Casablanca

17

Project 1

Service Contract
was signed on 28 Sept.
2005

Project was finalized and


Final Report was submitted
20 April 2007

MEDELEC/ 20-21 March 2


008, Casablanca

18

Studies
Budget

: 1.5 Million

According to decision of UCTE Steering


Committee meeting in Vienna-June 2002

Static studies by local TSOs in the Balkans


Stability studies by central UCTE TSOs under
the leadership of RWE-Germany

MEDELEC/ 20-21 March 2


008, Casablanca

19

TURKEY-UCTE connection
scheme
MARITSA 2

HAMTABAT S/S
400kV

90 km 3B 954 MCM

PLOVDIV
MARITSA 3 S/S
400kV

ALIBEYKY
250 MVA 380/154
77 km 2B 954 MCM
21 km 2B 954 MCM

BULGARIA
GREECE

THESSALONIKI

51.3 km, 3B 954 MCM

12 km 2B 954 MCM

THESSALONIKI
FOSFORKA PP

60 km, 3B 954 MCM

KAPTAN D.
S/S
400kV

ENELKO PP

FOSFORKA PP

KEHROS S/S
400kV

ENELKO PP

87 km 2B 954 MCM

2 x 150 MVA
380/154

148 km, 2B 954 MCM

148 km, 2B 954 MCM

PHILIPPI S/S
400kV

TURKEY

1 km 2B 954 MCM

14 km 2B 954 MCM
14 km 3B 954 MCM

BABAESK S/S
400kV

HABPLER
74 km, 3B 954 MCM

KTELL

MEDELEC/ 20-21 March 2


008, Casablanca

UNIMAR S/S
400kV

20

Exchange patterns

Ukraine

Slovakia

Austria
Slovenia

Austria

Moldova

Hungary

Ukraine

Slovakia

Moldova

Hungary

Slovenia

Romania

Romania

Croatia

Croatia
BIH

BIH

SCG
Bulgaria

Italy

Black Sea

SCG
Black Sea

Italy

Bulgaria
Georgia

Georgia
Makedonia
Albania

Makedonia
Albania
Arm
Greece

enia

Arm

Azerbajan
Greece

Turkey

enia

Iran

Iran

MEDELEC/
20-21 March 2008, Casablanca
Syria

Azerbajan

Turkey

Iraq

Iraq

Syria

21

Transfer Capability
results

MEDELEC/ 20-21 March 2008, Casablanca

22

limiting factors

Two main limiting factors were identified for exchange patterns:


between Turkey and Northeast Europe the transfer capability is
limited by :
the thermal limit of lines in the Serbia-Romania
interconnection area.
betweenTurkey and Southeast Europe the transfer capability is
limited by:
contingencies in the Bulgaria 400 kV ring
contingencies in the 400 kV interconnection lines between
Bosnia and Serbia.

MEDELEC/ 20-21 March 2


008, Casablanca

23

Summary Results of Static


Studies
The interconnection of the Turkish
EPS with the UCTE system is
technically feasible from the static
security point.

The connection of Turkish EPS to


UCTE by three lines provides the
necessary technical conditions for
import/export of significant amount
of electricity:
NTC for the import to Turkey is
within the range of 8001300 MW;
NTC for the export from Turkey is
within the range of 10001100 MW.

MEDELEC/ 20-21 March 2


008, Casablanca

24

Organisation of Stability Study


TASK 1

TASK 2

WAMS

MODEL OF TURKISH
POWER SYSTEM

TASK 3

TRANSIENT
STABILITY

TEIAS

RTE
RWE
TEIAS

RWE
NEK
HTSO
TEIAS

Yildiz Durukan
(TEIAS)

Philippe Carpentier
(RTE)

Martin Lsing
(RWE)

TASK 4

STEADY STATE
STABILITY

TASK 5

DAMPING
MEASURES

E.ON
RWE

RTE
E.ON
RWE
TEIAS

Wilhelm Winter
(E.ON)

Christian Lemaitre
(RTE)

MEDELEC/ 20-21 March 2


008, Casablanca

25

TASK 1: WAMS
BULGARIA

BLACK SEA

HABPLER
BABAESK
HAMTABAT

BATUM

GEORGIA

ALBEYKY
KTELL
KAPTAN

A.ALANI
D.PAA

BEYKOZ PAAKY

FILIPPI

UNIMAR

AMASRA

Y.TEPE
Z.KY
MRANYE
TEPEREN
ADAPAZARI

AMBARLI

EREL
OSMANCA

AYIRHAN

KARABGA

SNCAN

GKEKAYA

ALTINKAYA

HOPA
BORKA
ARAMBA

ANKIRI

ADA-GEBZE

BOYABAT

KARABK

ARMENIA

KARS

YUSUFEL

KALKANDERE

TREBOLU

H.UURLU

KAYABAI

HSAR

GUMRI

DERNER

IDIR

BURSA
BALIKESR
TUNBLEK
SOMA

KARGI
SEYTMER

TEMELL

GLBAI

ARI

SVAS
DEEKO

KANGAL

D.BEYAZIT

ERZURUM

KAYSER

GRST

UZUNDERE

MANSA

KOCATEPE

BAZARGAN

VAN

KEBAN
ALAA

BABEK

HORASAN

ZLCE

KHOY

ELBSTAN

IRAN

KARAKAYA

IIKLAR

YELHSAR
KONYA

DENZL

HLVAN

DYARBAKIR
BATMAN

AYDIN
YENKY

KAVAK

SEYDEHR

DOANLI

ILISU

ATATRK

ANDIRIN

HAKKAR
UKURCA

YATAAN

PS3

KEMERKY

OYMAPINAR
VARSAK

G.ANTEP

ADANA
ERMENEK

ERZN

.URFA

BRECK

KIZILTEPE

CZRE
ZAKHO
KESEK

SKENDERUN

IRAQ

SDEMR

MERSN

TEA 2006

HATAY

TPP (PLANNED)
HALEP

MEDITERRANEAN SEA
Presently Remote-Access to Sincan, Borca, Yatagan, Babaeski, Keban

MEDELEC/ 20-21 March 2


008, Casablanca

TPP (EXISTING)

SYRIA

HPP (PLANNED)
HPP (EXISTING)

WAMS

400 Kv TL (EXISTING)
400 kV TL (PLANNED)
220 kV T/L

26

1: WAMS Records (1)

10 sec.
Karakaya HEPP 600MW generation loss (7
March 2oo6)
MEDELEC/ 20-21 March 2
008, Casablanca

27

1: WAMS Records (2)

T1,45 sec.

1 sec.

1.45sec intraarea oscillation

MEDELEC/ 20-21 March 2


008, Casablanca

28

TASK 2: Modelling of Turkish Power


System
Approach

Static Data (PSS/E NETOMAC)

Dynamic Data

Collection and Survey of Dynamic Data

Set up of individual models with detailed representation of


generators, turbine and excitation control

Individual Check of generating units based on adequate test


scenarios (simulation)

Validation of the dynamic model by WAMS recordings

Close cooperation with manufacturers and operators


during whole study period
MEDELEC/ 20-21 March 2
008, Casablanca

29

TASK 2: Model of Turkish Power


System
Generation Outage
Elbistan (150MW) on
22-03-2006

Generation outage
Karakaya (660MW) on
07-03-2006

MEDELEC/ 20-21 March 2


008, Casablanca

30

TASK 3: Transient Stability


Objectives

Verify the transient stability of the parallel operation of the


UCTE Power System with the Turkish Power System

for maximum permissible exchange

in case of credible contingencies (design criteria


contingencies)

Analyse the system performance in case of more extreme


contingencies to

identify the most critical dynamic effects in the interface area

make preliminary proposals for the deployment of a defence


plan against extreme contingencies
MEDELEC/ 20-21 March 2
008, Casablanca

31

TASK 3: Transient Stability


Interconnection Lines

(pre-disturbance)

P-transfer
(static)

CFCT

N-scheme
Hamitabat-Maritsa 1
1100 MW 300ms - 400ms
Hamitabat-Maritsa 2
Babaeski-N.Santa
(N-1) schemes (maintenance or after contingency)
Hamitabat-Maritsa 1
1100 MW 300ms - 400ms
Hamitabat-Maritsa 2
Hamitabat-Maritsa 1
1100 MW
110ms
Babaeski-N.Santa
Hamitabat-Maritsa 2
1100 MW
160ms
BabaeskiN.Santa

Prevention of fast
Transmission
P-transfer
voltage collapse
Reliability Margin admissable
required RFCT Limitation P-transfer
(stability)
< 120ms

not necessary

250 MW

850 MW

< 120ms

not necessary

250 MW

850 MW

not possible

750 MW

250 MW

500 MW

not possible

750 MW

250 MW

500 MW

RESULTS (1)
BG TR two tie lines in service
MEDELEC/ 20-21 March 2
008, Casablanca

32

TASK 3: Transient Stability


Interconnection Lines

(pre-disturbance)

P-transfer
(static)

CFCT

N-scheme
Hamitabat-Maritsa 1
1100 MW 300ms - 400ms
Hamitabat-Maritsa 2
Babaeski-N.Santa
(N-1) schemes (maintenance or after contingency)
Hamitabat-Maritsa 1
1100 MW 300ms - 400ms
Hamitabat-Maritsa 2
Hamitabat-Maritsa 1
1100 MW
110ms
Babaeski-N.Santa
Hamitabat-Maritsa 2
1100 MW
160ms
BabaeskiN.Santa

Prevention of fast
Transmission
P-transfer
voltage collapse
Reliability Margin admissable
required RFCT Limitation P-transfer
(stability)
< 120ms

not necessary

250 MW

850 MW

< 120ms

not necessary

250 MW

850 MW

not possible

750 MW

250 MW

500 MW

not possible

750 MW

250 MW

500 MW

Maritsa

Hamitabat

BG TR only one of the tie lines is in service

Babaeski
N.Santa

Felipi
MEDELEC/ 20-21 March
2
008, Casablanca

TURKEY

33

TASK 3: Transient Stability


Requirement: SPS

Interface

SPS-PHASE 1:

SPS-PHASE 2:

Actions within Turkey to


maintain synchronism, e.g.

Controlled System
Separation
based on angel separation between
Turkey and UCTE
Maritsa

Generator Rejection

PMU

Turbine fast valving

Gas Turbine / Pumping Storage Start-Up


Underfrequency Load Shedding
Under Voltage Load Shedding
.

PMU

Hamitabat

Babaeski
N.Santa/
Thessaloniki

TURKEY

MEDELEC/ 20-21 March 2


008, Casablanca

34

TASK 4: Steady State Stability


Eigenvalue Analyis
Objectives

Analysis of the damping performance/stability


margin

Identification of reasons/risks for poor damping

Identification of optimal locations for damping


measures

Determination of permissible power exchanges

MEDELEC/ 20-21 March 2


008, Casablanca

35

Global Mode U1 (UCTE-0.22Hz)

MEDELEC/ 20-21 March 2


008, Casablanca

36

Global Mode T1 (UCTE+TURKEY - 0.15Hz)

MEDELEC/ 20-21 March 2


008, Casablanca

37

TASK 4: Steady State


Stability
Results (1): Mode shape

Calculated Eigenvalues (Power


Flow Spain France)

MEDELEC/ 20-21 March 2


008, Casablanca

38

TASK 4: Steady State


Stability
Results (2): Effectiveness of Damping Measures

MEDELEC/ 20-21 March 2


008, Casablanca

39

TASK 4: Steady State Stability


Results (3)

new critical UCTE-Turkey inter-area mode by 0,15 Hz with


insufficient damping
highest (positive and negative) effect on the damping of the
0,15 Hz mode in the Turkish system
insufficient damping mainly caused by the dynamic
characteristics of

existing AVR

governors of hydraulic turbines

deterioration of the existing UCTE inter-area oscillation mode


(0,2 Hz)

MEDELEC/ 20-21 March 2


008, Casablanca

40

TASK 4: Steady State


Stability
Results (4)

damping performance highly dependent on


power exchange Turkey - UCTE
power export from Turkey to UCTE has to be
limited by 500 MW for the trial operation
phase

MEDELEC/ 20-21 March 2


008, Casablanca

41

TASK 5: Damping Measures


Objectives

detailed analysis of selected units

Assessment of existing AVR/PSS

Design of new PSS

feasibility check in cooperation with operators and


manufactors

MEDELEC/ 20-21 March 2


008, Casablanca

42

TASK 5: Damping Measures


Results

positive (small) damping effect for 0,15 Hz oscillations


can be achieved by modern PSS

results confirmed by manufactures for selected


generation units

positive damping effect of AVR of the majority of units


has to be assured by

new parameter settings of existing voltage controllers

and/or

implementation of new PSS

adjustment of turbine governors


MEDELEC/ 20-21 March 2
008, Casablanca

43

Conclusions

The system interconnection of Turkey to UCTE is feasible under


following conditions:

the existing inherent frequency control problem is resolved

positive damping effect of AVR for the 0,15 Hz inter-area


oscillations is assured in the majority of generation units (new PSS)

A System Protection Scheme at the interface is necessary to


manage extreme contingencies

The power transfer from Turkey to UCTE must not exceed 500
MW during the trial operation

MEDELEC/ 20-21 March 2


008, Casablanca

44

Some Info about Project-2

MEDELEC/ 20-21 March 2008, Casablanca

45

Introduction of the Project2

Project: Rehabilitation of the Frequency Control


Performance of Turkish Power System for
Synchronous Operation with UCTE

Budget: 2.5 Million

Objective:

Turkish Power System is prepared for future parallel


operation with UCTE regarding power and frequency
control, steady state and transient stability.

MEDELEC/ 20-21 March 2


008, Casablanca

46

Organisational chart
TASK 1 (20%)
Survey of the
power plants
Field tests
EMS
ESO
EUAS
RTE
TEIAS (TUBITAK,
ABB; VaTech)

TASK 2 (25%)
Design of governor
control and
parameter
optimization
ESO (Univ. Varna)
RTE
RWE (Univ. Rostock)
TEIAS (TUBITAK, ABB,
VaTech)

Task leader: TEIAS

Task leader: RWE

TASK 4 (20)

TASK 5 (15%)

Design/
Optimisastion of
AVR/PSS
ESO (Univ. Varna)
RWE
TEIAS (VaTech, TUBITAK)
SwissGrid (Univ. Rostock,
ABB )
Task leader: SwissGrid

Special Protection
Scheme
Restoration Plan
ESO
HTSO
TEIAS(METU, Univ.
Rome)
TERNA
Task leader: ESO

MEDELEC/ 20-21 March 2


008, Casablanca

TASK 3 (10%)
Secondary Control

EMS
ESO
HTSO
Swissgrid (Univ. Rostock)
TEIAS (METU, Siemens)
Task leader: HTSO

TASK 6 (10%)
Training
RTE (EDF)
TEAIS (TUBITAK, METU)

Task leader: RTE

47

Next Steps

Since signing of the Service Contract the period


will be the pre-project phase to have a clear
picture to start the project

Task Share, Budget


Identification of the PPs to be considered in the Project

Draft Contracts will be finalized

Association Agreement
Service Contract

Meeting with CFCU organised

Studies in Task 1, 2, 3, 4 and 5 will continue


meanwhile
MEDELEC/ 20-21 March 2
008, Casablanca

48

Project Group

On the basis of the UCTE Steering


Committee decision

Technical Committee renamed as UCTE Project


Group (PG) for Interconnection of Turkey

PG was formed in March 2006

MEDELEC/ 20-21 March 2


008, Casablanca

49

Tasks and Duties of PG

Make the project go forward in the most efficient way


Elaborate a comprehensive document entitled Contractual
Agreement,

It will include all technical, organizational and legal issues,


needed as preconditions for the interconnection of the Turkish
Power System to the UCTE network,
It will reflect the results and the recommendations of the
Complementary Static and Stability Studies.

After the SC approval and decision, the PG will monitor

The implementation of the measures stated in the Contractual


Agreement,
The mandatory Final Tests of the Turkish Power System and
The trial parallel operation till the final interconnection to the
UCTE Network.

MEDELEC/ 20-21 March 2


008, Casablanca

50

Project Group Activities completed by the


end of 2007

MEDELEC/ 20-21 March 2


008, Casablanca

51

Time table

MEDELEC/ 20-21 March 2


008, Casablanca

52

Regional Interconnection
Project

MEDELEC/ 20-21 March 2008, Casablanca

53

Medring
Turkey-UCTE
Recent developments

11

Turkey-Syria
6 years delay in
Syrian side

1997
Connecti
on of
MoroccoTunusiaAlgeria to
UCTE

Tunusia-Libya
Trial operation
with UCTE, on
21 November
2005

1998
Egypt-Libya
connection

MEDELEC/ 20-21 March 2


008, Casablanca

54

UCTE Strategy on
MEDRING
Synchronous parallel operation of

UCTE

MASREK

MAGREP

IRAQ
TURKEY

Turkish block with UCTE system


Closing the Libya-Tunisia links
Closing the Turkey-Syria link
after detailed analyses

11

3
2
MEDELEC/ 20-21 March 2
008, Casablanca

55

Turkey-Syria Connection
Until Closing MEDRING
UNIT COMMINTMENT
2006
Max. 400MW power export from Birecik
PP
Total 134.4GWh/(Nov.-Dec.2006)
2007
Max. 400MW power export from Birecik
PP
Total 972.2GWh/yearMEDELEC/ 20-21 March 2
008, Casablanca

56

Turkish-Iraq Connection
Until Closing MEDRING
Passive Island mode
2006

Passive Island

Max. 300MW power export from Turkey


Total 1668.8GWh/year
2007
Max. 300MW power export from Turkey
Total 1349.8GWh/year

MEDELEC/ 20-21 March 2


008, Casablanca

57

Conclusions-1

Regarding the interconnection projects it has to be noted


that the standards has to get compliant and the realisation
of the regional interconnections has to be achieved step by
step.
Synchronous parallel interconnection of Turkish Power
System to UCTE is seen as:

the prerequisite for the realisation of MEDRING project.

The studies/activities for the synchronous parallel


interconnection of Turkish Power System to UCTE is
going on successfully based on the decision of the UCTE
SC.

MEDELEC/ 20-21 March 2


008, Casablanca

58

Conclusions-2

Following the interconnection of Turkish Power


System with UCTE, TEA supports the MEDRING
Project under the conditions that;

Technically and economically feasible,


Approved by UCTE.

During the transitory period till the


synchronisation, the tie lines apart from the UCTE
connections, would be operated through;

Isolated region method,


Unit direction method,
And/or asynchronous connection.
MEDELEC/ 20-21 March 2
008, Casablanca

59

S-ar putea să vă placă și