Documente Academic
Documente Profesional
Documente Cultură
TECHNOLOGY PROJECT
Saleem Sabir-22
Asadullah Bappi- 12
Talal Shahid-23
Arsalan- 34
Dysfunctional Decision
Making is a
Synopsis
Denver Airport Baggage handling
system failure is a classic example of
Dysfunctional decision making
This session will look upon:
1. Decisions that set the project on the
path to disaster
2. Forces behind those decisions
Background
Worlds largest automated baggage
handlings system
Need for greater airport capacity.
Need of new state of the art airport that
would cement Denvers position as an air
transportation hub
140Sq. Km airport was to be the largest
airport in US having capacity to handle
more than 50,000,000 passengers annually.
Background
By automating baggage handling,
the aircraft turnaround time will
reduce to as little as 30 Minutes I.e.,
more operations and a competitive
advantage for airport
System at a glance
1.
2.
3.
4.
5.
6.
7.
Background Continued
Despite the good intentions plan
rapidly dissolved as:
1. Underestimation of projects
complexity resulted in snowballing
the problems and public humiliation
for everyone involved
2. Airport opening was delayed by a
full 16 months
Background Continued
3. Expenditure to maintain empty airport
and interest charges on construction
loans cost the city of Denver $1.1
Million per day throughout delay
4. Media showed it highly thought
provoking milestone going to be
achieved but on opening day system
was just a shadow of original plan
Background Continued
Rather Than automating all 3
concourses into one integrated
system, the system was used in a
single concourse, by a single airline
and only for outbound flights.
Remaining baggage handling was
done via simple conveyor plus
manual tug and trolley system (built
as an alternative) when it became
clear that idea fully flopped.
1.Change in Strategy.
Two Years Late decision.
Timing of the decision extremely poor.
United Airline
Continental Airline
4. Acceptance of Change
Request
Among the major changes were; the adding of ski equipment
racks, the addition of maintenance tracks to allow carts to be
serviced without being removed from the rails and changes to the
handling of oversized baggage.
Rather than being separate entities, the baggage system and the
physical building represented a single integrated system. Sharing
the physical space and services such as the electrical supply the
designers of
the physical building and the designers of the
baggage system needed to work as one integrated team.
Estimates to change the physical structure to suit the needs of the
baggage system are reported to have been up to $100M).
Sharp turns is reported to have been one of the major problems
that lead to bags being ejected from their carts. These problems
ultimately proved so severe that the speed of the system was
halved from 60 cars per minute to 30 cars in order to reduce the
physical forces when negotiating tight turns.
Leadership Change
Architectural and Design issues
The system had more than 100 individual PCs that were
networked together. Failure of any one of the PCs could result
in an outage as there was no automatic backup for failed
components.
The system was unable to detect jams and as a result when a
jam occurred, the system simply kept piling up more and more
bags making the jam that much worse.
Conclusion
1. The Underestimation of Complexity
2. A lack of planning resulting in
subsequent changes in strategy
3. Excessive schedule Pressure
4. Lack of due diligence
5. Making firm commitments in the
face of massive risks and
uncertainty
6. Poor Stakeholder Management
Conclusion
7. Communication Breakdowns
8. Poor Design
9. Failure to perform risk management
QUESTIONS
?