Documente Academic
Documente Profesional
Documente Cultură
Objectives
Contents:
I.
Flood
1. Definition of flood
2. Different causes of flood
3. Various types of flood
II. Design of Flood Control Structures
(Dike/Embankment/Revetment)
1. Design Data Required
2. Design Criteria and Standards
3. Design Procedures
4. Hydrology
III. Design of Drainage Structures
1. Design data required
2. Design Criteria and Standards
3. Design Procedures
I. Flood
What is a flood?
Flood is a temporary covering of land by water
outside its normal confines. This includes floods
from rivers, mountain torrents and floods from
the sea in coastal area.
Causes of Flood
Excessive Rainfall (inland flooding)
Excessive
Rainfall
Causes of Flood
Excessive Rainfall (inland flooding)
Storms (Storm Surge)
Causes of Flood
Excessive Rainfall (inland flooding)
Storms (Storm Surge)
Earthquakes (Tsunamis)
Causes of Flood
Excessive Rainfall (inland flooding)
Storms (Storm Surge)
Earthquakes (Tsunamis)
Flood Control Structure Breaks (man induced)
Causes of Flood
Excessive Rainfall (inland flooding)
Storms (Storm Surge)
Earthquakes (Tsunamis)
Flood Control Structure Breaks (man induced)
Types of Flood:
Coastal Flood
Urban Flood
Pluvial Flood (Ponding)
Fluvial Flood (Rise of river water surface)
Flash Flood
Semi-Permanent Flood (Land Subsidence)
movie.wmv
Aftermath of a flash
flood
C. Other Requirements
1. Topographic map of the proposed project area with
0.50 m contour interval at a scale of 1:10,000 m.
2. Ground profiles along the banks at horizontal and
vertical scales of 1:1,000 m and 1:100 m respectively.
3. Water surface profile indicating maximum experienced
flood level, design water level, and minimum water
level at horizontal and vertical scales of 1:1,000 m.
1:100 m respectively.
4. Profile of the riverbed along the centerline of the river
channel at horizontal and vertical scales of 1:1,000 and
1:100 m respectively.
5. Cross-sections facing downstream at 100 meters interval
for straight and uniform section, 25 meters for river bends
and 20 meters for sharp bends, indicating thereon the
Design of Dikes/Embankments
A ridge constructed of earth, stone, or other material to
Prevent water from passing beyond desirable limits.
Also known as bank.
A. Location and Alignment
B. Freeboard
C. Slopes
D. Height
E. Top Width
F. Berms
Design of Revetments
Revetments are flood control structures constructed along
river banks subjected to direct attack of the river flow
and along second dike slopes for protection against
scouring and wave wash.
A. Location and Alignment
B. Freeboard
C. Slope
D. Height
1. Design of Dikes/Embankments/Levees
B. Freeboard
The freeboard allowance corresponding to the
Design flood discharge
DESIGN DISCHARGE, Q
(M3 /S)
FREEBOARD, Hf
(m)
0.60
0.80
1.00
1.20
1.50
2.00
C. Top width
Top width of the embankment may not be of special importance
if ample freeboard and side slopes are already provided. However,
adequate widths of the top embankment may be required to serve as
a road for facilitating the transport of materials during the
construction stage and maintenance operations. Below are the
recommended top widths for the given design discharges.
3.00
4.00
5.00
6.00
7.00
D. Slope
1.
the
E. Height
The height of the embankment is reckoned from the design flood
elevation plus an additional freeboard allowance depending on
design discharge as shown in Table 3.1.
D.Slopes
Hf
Hf
DFWL
1
RIVERSIDE
DFWL
1
EMBANKMENT
1
2
LANDSIDE
RIVERSIDE
Hf
EMBANKMENT
DFWL
1
RIVERSIDE
EMBANKMENT
LANDSIDE
LANDSIDE
F. Berm
Berm are provided along the slopes of high embankments as an erosion
control measure and also to improve the stability of the side slopes:
1. Riverside
When the crest height from river bed is more than
6.00 metres, berms
shall be provided at every 3.00 to 5.00 metres in height from crest elevation
with a width of 1.00 metre or more.
2. Landside
When the crest height from existing ground is more than 4.00 metres,
berms shall be provided at every 2.00 metres to 3.00 metres in height from
crest elevation with a width of 3.00
metres or more.
3.
Masonry dike may have a minimum berm width of 1 metre
necessary, for stability purposes.
when
2. Design of Revetment
A. Location and alignment
1.
Scouring and
Degradation Part
Sand Bar
Formation
B. Freeboard
Generally, a minimum free board allowance of
0.60 m above the maximum experienced flood
level or design flood level, as the case may be, is
provided for revetments confining flood flows.
C. Slope
Slope of revetment will depend on the kind of
materials used and protection works required for
the structures. Table 3.3 shows the recommended
slopes of revetment with respect to the kind of
materials to be used in the construction of said
structure.
D. Height
Heights of revetment will depend on the maximum experienced
flood level or design flood level. For other cases when combined
with flood control works such as levee/embankment, the height of the
revetment is up to the designed height of the structures due to the
possibility of the occurrence of floodwaters that may exceed the
design flood level or the crest of the dike. If the height of revetment
is more than 5.0 meters, berm must be provided in order to separate
the revetments into segments, as well as in consideration of site and
geological condition and structural stability of the revetment. Berms
shall be at least 1.0 meter in width for maintenance purposes.
Freeboard
DFL
Berm
(banquette)
H
E. Depth of Foundation
.
Revetment
Toe
1.0 M
1.0 M
Deepest riverbed
> 20.0 M
F. Segment Length
The length of one segment of revetment along the longitudinal
direction should not be more than 50 meters in order to prevent
damage on the adjoining section of the revetment once it
collapses. Edge of the segment shall be provided with end
protection and adequately filled with joint filler or sealer to
connect with the adjoining section.
G. Thickness
The thickness of revetment is generally based on the flow
velocity, sediment runoff, topography, geological conditions,
scouring and degradation and soil and groundwater pressure at
the back of revetment and other factors. Minimum thickness
should be 300 mm for all types of revetment, except for
reinforced concrete type.
H. Weepholes
Revetment should be provided with weepholes ranging from
50 75 mm in diameter PVC pipes spaced at 2.00 meters on
center and staggered. Pervious materials consisting of graded
gravel or geo-textile is placed between the revetment and
original ground.
Original bank
End protection
PLAN
50 cm
SECTIONA-A
Design Procedures
For Revetments
1. Gather all survey and hydrologic information needed
for the design of revetments.
2. Compute the velocity of flow based on the design
flood discharge and the river profile and the crosssection using the Mannings formula.
3. Determine the type of revetment to be adopted
based on the design flood level and the quality
and quantity of available construction materials
at the project area.
4. For dry boulders riprap, the size of boulders to be
used can be determined from the graph (show Fig.4.2).
For Dikes/Embankment/levees
1. From the location or topographic map of the
project area, establish the alignment of the
embankment (s) considering the present course
and probable meander of the river.
2. For confining dikes, the width of the floodway or
distance between parallel dikes shall be
determined
with due consideration to non-silting and/or
non-scouring velocity in the channel.
3. Then, establish the design flood level at a particular
section, using the Stage Discharge Relationship or
Rating Curve, if available, or by the Mannings
Formula.
Hydrology
Design Frequency
Bridge
- 50 years (100)
Rivers
HEC-HMS Software
A. Rational Method
Delineated
Watershed Parameters
Area,
Km2
Length
of Stream, Km
Highest
Elevation
Length
at Point of Interest, m
Lag
Unit
Rainfall Data
- Table 4-Rainfall Depth Duration Data
Read Rainfall Depths at every computed time
interval/increment
RANGE
0.90 1.00
0.30 0.60
0.30 0.60
0.20 0.50
0.70 0.90
0.70 0.90
0.30 0.50
0.50 0.70
0.30 0.50
Flooded Paddies
0.70 0.80
HYDRAULICS ANALYSIS
DESIGN DATA:
DISCHARGE, Q50 = 33 m3/s
SLOPE, S
= 0.0025
ROUGHNESS COEF., n
= 0.03
FIGURE:
DFL
d
6.0 m
Bed Elev. = 25.30 m
F.B.
HYDRAULICS ANALYSIS
DESIGN DATA:
DISCHARGE, Q25 = 33 m3/s
SLOPE, S
= 0.0025
ROUGHNESS COEF., n
= 0.03
FIGURE:
M.F.L = 28.10 m
DFL
d
6.0 m
Bed Elev. = 25.30 m
F.B.
Q = AV
V = 1/n R 2/3 S
WHERE:
TRY:
R = A/P
d = 2.62 m
A = (2.62)(6.0) = 15.72 m2
P = 2.62(2) + 6.0 = 11.24m
R = 1.72 = 1.4
11.24
V = __1__ (1.4)2/3 (0.0025)1/2
0.03
= 2.08 m/s
Q = AV = 32.78 m3/s 33 m3/s
Therefore:
DESIGN FLOOD LEVEL, DFL = 27.92 m
SCOUR ANALYSIS
by Blench Method
DESIGN DATA:
DISCHARGE, Q50
= 33 m3/s
BED ELEV.
= 25.3 m
VELOCITY
= 2.08 m/s
SCOUR ANALYSIS
by Laceys Regime Formula
DESIGN DATA:
DISCHARGE, Q = 33 m3/s
DESIGN FLOOD LEVEL, DFL = 27.92
RIVERBED ELEV. = 25.3
dm = 0.47 (Q/f)1/3
= 0.47 (33/1.25) 1/3
f = 1.25 for straight reach channel
= 1.40 m
ds = dm f silt factor
f = 1.75(0.50)1/2
= 1.237 for grain size
d50 = 0.50 mm
ds = 1.40 (1.237)
= 1.73 m
ELEV. OF SCOUR = 27.92 1.75
= 26.20 M
Therefore: Scour cannot be expected
RCBC
- 25 years (50)
Pipe Culvert
- 15 years (25)
- 2 years