Documente Academic
Documente Profesional
Documente Cultură
MRP
Lecturer:
Associate Professor Dr. Faieza Binti Abdul Aziz
GROUP 6
N
O.
NAME
MATRIC NO.
1
2
3
4
GS44687
GS46019
GS46236
GS45602
For example, the parts and materials that go into the production of an automobile are examples of
dependent demand, because the total amount of parts and raw materials needed during any time
period is a function of the number of cars that will be produced. Conversely, demand for the
finished cars is independent. A car is not a component of another item
Material Requirement
Planning (MRP)
It is a production planning process that starts from the demand for
finished products and plans the production step by step of
subassemblies and parts
It is also a set of techniques that takes the Master Production
Schedule and other information from inventory records and
product structure records as inputs to determine requirements and
schedule of timing for each item.
Purpose of MRP
Control inventory levels
MRP Structure
MRP INPUTS
BOM Example
AMIN SHAFANEJAD
MRP Processing:
Gross Requirement: The total expected demand for an item or raw material
during each time period without regard to the amount on hand.
Schedule Receipt: Existing orders that arrive at beginning of period.
Projected on Hand: Inventory balance that will be on hand at the beginning of
each time period.
Net Requirement: The actual amount needed in each time period.
Planned-order Receipts: The quantity expected to be received by the
beginning of the period.
Planned-order Release: Indicate a plan amount to order in each time period or
offset by lead time.
A.
Required date
Order release date
B.
Required date
Order release date
C.
Required date
Order release date
E.
Required date
Order release date
F.
Required date
Order release date
G.
Required date
Order release date
G.
Required date
Order release date
Lead Time
50
100
100
150
200
300
200
300
300
600
300
600
300
300
200
200
150
50
1 week
2 weeks
1 week
2 weeks
3 weeks
1 week
2 weeks
On + Scheduled
hand
receipts
Available inventory
Net
requirements
AHMED FAISAL
Lot Sizing
the process of modifying the net requirement quantities before
they are translated into planned orders in an MRP system.
If net requirements were translated directly into planned orders,
it would result in manufacturing component schedules and
purchasing schedules that did not take any account of the cost
of machine setups or the cost of ordering.
Example:
The company that makes a table want to ship 100 units at the beginning of the
day 4,150 units at the beginning of day 5, and 200 units at the beginning of
day 7, receipts of 100 wood sections are scheduled at the beginning of day 2.
On hand balance: braces = 60 and legs = 120.lead times in days for all items
are shown as table below, the product structure also show as table below:
FIND: prepare a material requirements plan using lot for lot ordering for all
items.
Quantity
Lead time
1-200
201-550
551-999
Example cont.
Example cont.
Master
Schedule for
table
Day
Table
100
150
200
Beg inv
100
100
0
100
100
150
150
0
150
150
200
200
0
200
200
Beg inv
100
100
400
200
100
100
100
300
0
300
300
400
400
0
400
400
Table
Lot size : Lot for lot
Gross requierment
Scheduled reciepts
Projected on hand
Net requierment
Planned-order-reciepts
Planned-order-releases
Wood section (2)
Lot size : Lot for lot
Gross requierment
Scheduled reciepts
Projected on hand
Net requierment
Planned-order-reciepts
Planned-order-releases
Example cont.
Braces (3)
Lot size : Lot for lot
Gross requierment
Scheduled reciepts
Projected on hand
Net requierment
Planned-order-reciepts
Planned-order-releases
Legs(4)
Lot size : Lot for lot
Gross requierment
Scheduled reciepts
Projected on hand
Net requierment
Planned-order-reciepts
Planned-order-releases
Beg inv
60
60
100
60
240
300
60
240
240
450
450
0
450
450
600
600
0
600
600
Beg inv
120
120
880
120
400
120
280
280
800
600
0
600
600
800
0
800
800
MRP OUTPUT
Primary reports
Secondary reports
Safety Stock
Benefits of MRP
Backflushing
Requirements of MRP
Thank You
43