Documente Academic
Documente Profesional
Documente Cultură
Basic Concept
In last lecture, we studied on how to use
CPM and PERT to identify critical path
for a project problem
Now, the question is:
Question:
Can we cut short its
project completion
time?
If so, how!
1
Project Crashing
Solution!
Yes, the project duration can be reduced
by assigning more resources to project
activities. But, doing this would somehow
increase our project cost!
How do we strike a balance?
Project crashing is a method for
shortening project duration by reducing
one or more critical activities to a time
less than normal activity time.
Non-critical activities need not be speeded
up, since their crashing is not going to
decrease the project duration further.
2
Trade-off concept
Here, we adopt the Trade-off concept
We attempt to crash some critical
events by allocating more resources to
them, so that the time of one or more
critical activities is reduced to a time
that is less than the normal activity
time.
How to do that:
Question: What criteria should it be
based on when deciding to crashing
critical times?
3
OBJECTIVE
Many times it becomes necessary to complete the project earlier than the
normal time (latest allowable time), determined from the CPM, to meet a
specific deadline, with the least cost.
In addition to that it might be necessary to finish the project in a specific
time to:
- Finish the project in a predefined deadline date.
- Recover early delays.
- Avoid liquidated damages.
-Free key resources early for other projects.
- Avoid adverse weather conditions that might affect productivity.
- Receive an early completion-bonus.
- Improve project cash flow
CPM makes use of the cost estimate along with the time estimate and
4
provides a schedule for completing the activities at the minimum total cost
10
Project Crashing
Projects will sometimes have deadlines
that are impossible to meet using
normal procedures
By using exceptional methods it may
be possible to finish the project in less
time than normally required
However, this usually increases the
cost of the project
Reducing a projects completion time is
called crashing
12
1. Find the normal critical path and identify the critical activities
2. Compute the crash cost per week (or other time period) for all activities in
the network using the formula
3. Select the activity on the critical path with the smallest / lowest crash cost
per week and crash this activity to the maximum extent possible or to the
point at which your desired deadline has been reached
4. Check to be sure that the critical path you were crashing is still critical. If
the critical path is still the longest path through the network, return to step
3. If not, find the new critical path and return to step 2.
When there are multiple critical paths, find the sum of crashing the
least expensive activity on each critical path
If two or more critical paths share common activities, compare the least
expensive cost of crashing a common activity shared by critical paths with the
sum for the separate critical paths