Documente Academic
Documente Profesional
Documente Cultură
Group 5
School of Mining Engineering
Aidan Blockley
Max Jones
Tyler Kaplan
Anthony Sara
Albert Young
Project Overview
Open Pit
Underground
Total
1.5
0.46
1.59
NPV (AUD B)
2.7
1.4
4.1
IRR (%)
15.3
15.3
15.3
Reserve (Mt)
161
50.6
211.6
13
22
1.06
1.25
161
43.4
204.4
Regional Geology
30-50 SSE dipping
100-120MPa rock strength
Underground
Sub level stoping versus sub
level caving comparison
Nicholas Algorithm analysis
Backfill
Transition
Open pit stability
In pit transition
Development scheduling
simultaneous with open pit
production
Grade-Tonnage Curves
Open Pit Grade-Tonne Curve
350000000
300000000
250000000
200000000
Tonnage (Mt) 150000000
100000000
50000000
0
0.2
0.4
0.6
Cutoff
Tonnage
cu
0.8
1.6
1.4
1.2
1
0.8 Grades
0.6
0.4
0.2
0
1.2
Surface Operations
Open Pit Summary
Capital Expenditure (CAPEX) ($AUD)
NPV ($AUD)
Life of Mine (years)
Operating Expenditure (OPEX) ($AUD/t)
13
Surface Operations
Whittle Input Assumptions
Optimisation
Pushback Selection
Pit-by-Pit Graph
Pushback Optimisation
Pit 16
Pit 13
Pit 9
Pit 6
Final Pit
Drawbacks
Modified Schedule
Annual Open Pit Production
Open Pit Production Schedule
25
20
15
Waste
Ore
TOTAL
Tonnes (Mt)
10
0
1
10
11
12
13
Equipment Selection
Equipment
Unit ID
Specifications
Number of
Units
Hitachi EX5600
34 m3
Hitachi EX1900
7.8m3 11.9m3
CAT Trucks
CAT793D
218t
28
CAT Grader
CAT14M
14m
CATD8T
300kW
CAT Drill
MD6240
<270mm
CAT777G WTR
75, 000 L
Hitachi Excavator/s
Surface Infrastructure
Tailings Dam
Waste dump 1
Waste Dump 2
ROM Pad
Processing Plant
Workshop
Substation
Crib Room
Go Line
Open Pit
Administration
Concrete Plant
Design Parameters
Pit Design
Parameter
Value
16
7.5
35
OSA ()
46
ISA ()
43
BFA ()
50
Road gradient
10%
Grade-Tonnage Curves
Underground Grade Tonnage Curve
45000000
2.5
40000000
2
35000000
30000000
1.5
25000000
Tonnage (Mt)
Grades
20000000
15000000
10000000
0.5
5000000
0
0.2
0.4
0.6
0.8
1.2
1.4
Cutoff
Tonnage
Cu
1.6
1.8
0
2.2
Shaft
Developmen
t
Required
development
(m)
Profiles
Total Cost
Decline
8860
5m x 6m
$35.4 M
Stope Levels
45835
5m x 6m
$183.3 M
Materials
Shaft
716
7m
(diameter)
$21.5 M
Ventilation
Shaft 1
400
5m
(diameter)
$11.4 M
Ventilation
Shaft 2
460
5m
(diameter)
$13.1 M
Ore Passes
1960
3.2m
(diameter)
$39.2 M
Total Cost
$303.9 M
Stope Design
Height = 40m
Width = 15m
Length = 30m
10m Sill pillar
Tonnes per stope =
50400
Average grade =
1.25% Cu
Underground Operations
Geotechnical Considerations
Underground Scheduling
Tonnes per Stope per Level
Number of Stopes
120
100
80
60
40
20
120
100
80
60
40
20
0
9810494 79 78 75 91 71 59 50 46 16
6
5
4
3
2
1
0
Ventilation
Stage
Power (kW)
Quantity
Required (
Decline
2640
148
Production
2100
151
1868
134
Development
834
60
Total
(accountable)
9362
560
Total Cost
Equipment Fleet
Equipment
Total Units
Type
(where
applicable)
Specification
s
Crusher
Gyratory
1000
tonne/hour
Winder
Double Drum
800 tonne/hour
Conveyor
1150mm Belt
Width
800 tonne/hour
LHD
CAT 2900G
7.2m3
Truck Fleet
12
CAT AD45B
22.9m3
Integrated Tool
Carrier
IT14G2
71kW
Jumbo Drill
Boomer 282
Twin Boom
Simba 364
165mm
Backfill
Paste Backfill
Processing
Crushing
Grinding
Froth flotation
Chalcopyrite from coarse
grained sulphide ores
floats readily with xanthate
collectors
Particle size, aeration,
collector, pH
Product thickening
Tailings disposal to TSF
Copper-gold concentrate
34% Cu
15g/t Au
Processing
Capacity
Tailings
Year
Processing
Capacity (Mt)
2.5
7.5
10
Financial Model
Assumptions
Sensitivity Analysis
Sensitivity Open Pit
FTM Sensitivity Analysis by Percent Change in NPV
110.00
90.00
70.00
50.00
30.00Change (%)
NPV Percent
10.00
0.85
(10.00)
0.9
0.95
1.05
1.1
(30.00)
(50.00)
Ore Production
Processing Recovery Au
Au Price Forcast (1)
Debtors delay
Mining Cost per Tonne
Fixed Costs (admin and other costs)
Discount Rate
Sensitivity Multiplier
Head Grade Au
Processing Recovery Cu
Cu Price Forcast
Initial Capital Costs
Processing Cost per Tonne
State Royalties
Head Grade Cu
Gold in Circuit
Exchange Rate
Ongoing Capital Costs
Smelting Refining, Transport and sales per Tonne
Company Tax Income Rate
1.15
Sensitivity Analysis
Sensitivity Underground
FTM Sensitivity Analysis by Absolute NPV
5.5
5
4.5
4
3
2.5
2
0.85
0.9
Ore Production
Head Grade Cu
Gold in Circuit
Cu Price Forcast
Debtors delay
Mining Cost per Tonne
0.95
Sensitivity Multiplier
Polynomial (Ore Production)
Processing Recovery Au
Au Price Forcast (1)
Exchange Rate
Initial Capital Costs
Processing Cost per Tonne
1.05
1.1
1.15
Head Grade Au
Processing Recovery Cu
Polynomial (Au Price Forcast (1))
Polynomial (Exchange Rate)
Ongoing Capital Costs
Smelting Refining, Transport and sales per Tonne
Logistics
(Aurizon, 2014)
Parameter
Rail
Road
$/ntkm
0.025
0.07
Cost ($/nt)
20.00
56.00
Implementation
(AU$M)
60,000,
000
18,000,
000
29.83
58.95
Underground
36.43
60.93
Technical
Socio-Environmental
Recommendations
Moving Forward