Documente Academic
Documente Profesional
Documente Cultură
CONSTRUCTION
KISHANPUR 20/08/2009
By.
MAN MOHAN RAINA
MANAGER T/L
PANIPAT
INTRODUCTION
INTRODUCTION
Foundation
Tower Parts
Conductor
Earth Wire
Insulator
Hardware & Accessories
INTRODUCTION
Route Alignment
Detail Survey
Check Survey
Soil Investigation
Casting of Foundations
Erection of Towers
Stringing of Conductor and Earth Wire
Testing and commissioning of project.
INTRODUCTION
For next few hours we will be mainly discussing the following
components of Transmission Line Project:
a) Soil Investigation
b) Tower Foundations
c) Earthing of Towers
d) Tower Erection
f) Stringing
h) Statutory Clearances
i) Right of Way Issues.
SOIL INVESTIGATION
Why required?
When required?
SOIL INVESTIGATION
Purpose:- Technical:
- Economic:
-Inadequate design/conservative
choice of foundation may cause failure
-To carry out pre-design of foundation
as large variety of soil encountered in
long line with voltage going up
-Foundation costs a major portion
- Considerable saving by way of
devolving a Techno/ Economic
foundation design as per actual soil
Field Investigation:1.
Boring
Required to have knowledge of sub-soil profile, its
nature & strength etc.
To collect soil samples for strata identification and for
conducting laboratory tests
Minimum diameter of bore 150 mm
Depth of 7/10 mtr for normal soil conditions
Depth of 40 mtr for river crossing/ spl locations
Type of Boring
Augur Boring
For soft to stiff cohesive soil above water table
Rotary Boring
For all types of soil below water table
Classification of Soils
Classification of Soils
Soil Investigation
Type of Soil:
Depth (mtr)
2, 3, 5, 7, 10
2, 3, 5, 7, 10 and every 3
mtr intervals up to 40 mtr
Sampling
Disturbed SampleJar sample of 1 Kg for every 0.5 mtr intervals starting from 0.5 mtr
from GL & every change of strata
Undisturbed SampleTo be collected at change of strata & at depths:Location
Normal loc
River X-ing/ Spl
Location
Depth (mtr)
1, 4, 6, 8 & 10
1, 4, 5, 8, 10 & every 3 mtr up to 38 mtr
Tests
Undisturbed & Disturbed Sample
Undisturbed Sample
Visual
Sieve analysis
Liquid, Plastic & Shrinkage limits
Specific gravity
Chemical analysis
Swell pressure
Bulk density & moisture content
Physical bearing capacity settlement properties
Chemical Analysis of Sub-Soil water
SOIL INVESTIGATION
Soil Resistivity
-
Measured in ohm-meter
Soil Resistivity
Indian Standards
Title
1.
IS : 1498
2.
IS : 1892
3.
IS : 1904
4.
IS : 2131
5.
IS : 2132
6.
IS : 2720
7.
IS : 2809
8.
IS : 3025
Methods of Sampling and Testing (Physical & Chemical) for water used in
Industry
9.
IS : 4078
10.
IS : 4434
11.
IS :4453
Indian
Standards
Title
12.
IS : 4464
13.
IS : 4968 (PartII)
14.
IS : 5313
15.
IS : 6403
16.
IS : 6926
Code of practice for Diamond core drilling for site investigation for river valley
projects
17.
IS : 6935
18.
19.
IS : 8764
20.
IS : 9143
21.
IS : 9179
TOWER
FOUNDATIONS
KISHANPUR
20/08/09
MAN MOHAN RAINA
MANAGER T/L
PANIPAT
Downward load
Uplift load
Lateral Load (Horizontal thrust)
Overturning moments
Uplift load
CLASSIFICATION OF FOUNDATION
1.
2.
Classification of Foundation:Normal Dry - where normal dry cohesive or non-cohesive soils are met
NC/ Sandy Dry where cohesion less pure sand or negligible cohesion
CLASSIFICATION OF FOUNDATION
TYPE OF FOUNDATION
Type of Foundation:-
X+x
Pit
C
PIT
B
X+x+y
00
Pit
D
Pit
A
Dewatering
- Required for wet locations both during concreting &
24 hrs after placing concrete
Concreting
RF Steel
Concreting
Concreting:-
Concreting
Form Boxes
-
Concreting
Cement
Concreting
Type of Concrete
- Design Mix
- mix be designed to achieve required workability & strength
not less than appropriate value
- Nominal Mix
- proportion of materials prefixed
- used for M-20 or lower
- Used in normal foundation of TL
Proportion of Nominal Mix Concrete
Grade
M-10 480
M-15 330
M-20 250
1:2
1:2
1:2
Water
34
32
30
Concreting
Transportation
-
Placing
-
Concreting
Compaction
-
Curing
-
Concreting
Form Work
To remain sufficiently rigid during placing &
compaction of concrete
To prevent loss of slurry from concrete
Insides to be cleaned from all rubbish, i,e, chippings,
shavings before concreting.
Insides to be treated with form release agent.
To be removed after at least 24 hrs of concreting
Concreting
Pouring of concrete & vibration
-
Concreting
Testing of concrete
- Slump Test
- To determine consistency of concrete/work ability
(water /cement ratio.
Apparatus for slump test
Concreting
Compressive Strength
- To be tested for 28 days compressive strength
-
TOWER
ERECTION
KISHANPUR
20/08/09
MAN MOHAN RAINA
MANAGER T/L
PANIPAT
33
39
44
47
50
55
TOWER ERECTION
Deviation limit
Remarks
A, DA
02
Tangent tower
B, DB
2 - 15
15 - 30
30 - 60
C, DC
D, DD
Body Extension
Leg Extension
A, DA
-4.5,-3, -1.5, 0,
+1.5,+3,+4.5,
+6,+7.5,+9
B, DB
+3,+6,+9
-Do-
C, DC
+3,+6,+9
-Do-
D, DD
-Do-
Tower Configuration
Loads on Tower
Transverse Load
i) Wind on structure, conductor, insulator & hard
wares
ii) Deviation in the angle
Longitudinal Load
- Dye to unbalanced tension in conductor, produced
either due to dead-ending of conductor on the structure or
due to broken wire conditions. It acts along the direction
of the line and the component at right angle to the
longitudinal axis of the X-arm is considered for design
Loads on Tower
Vertical Load
- Loads due to:i) weight of conductor, ground wire, insulator strings,
hard wares, accessories
ii) Unbalanced vertical loads under broken wire
conditions
iii) Dead weight of the structure and the provision for the
weight of the maintenance crew
Torsional Load
- Produced either due to dead-ending of conductor on the two
sides, e.g, due to broken wire or due to dead ending of the
conductor on single circuit lines
AVAILABILITY OF DRGS
CHECKING OF FOUNDATION
PIECEMEAL METHOD
SECTION METHOD
HELIECOPTER METHOD
PIECEMEAL METHOD
Section Method:-
Helicopter Method:-
Verticality Check:-
Tower Erection
Assembling
-
Tower Erection
-
D Shackle (3)
- 6No
Hexagonal box spanner with fixed liver and
end of the liver pointed to use hole bar
(Tommy bar)
- Reqd. sizes
Safety Helmets
Safety Belts
Safety shoe
Welding goggles
First aid box
- 40No
- 10No
-50pairs
-2No
- 1No
Tower Earthing
Tower Earthing
Earthing in TL
1) Pipe Type Earthing
Used in dry, wet, black cotton,
submerged soil where soil resistivity
is less
Earth strips are fixed to the
stub during concreting of the
chimney & taken out
horizontally below GL
Generally provided in one leg,
i.e, leg A
A galvanized flat of size around
3 mtr is fixed during casting
A perforated MS galv pipe of
25 mm dia, 3 mtr long is buried
in
300 mm dia hole with
charcoal
& salt
Tower Earthing
2) Counterpoise Earthing
-
Tower Earthing
To study the effect of earthing it is mandatory to record
Tower Footing Resistance (TFR), before and after earthling
After earthing, Tower Footing Resistance in all the cases
should be less than 10 ohm.
STRINGING
TOWER SCHEDULE
Weight Span - HOT
Type Of
S.No.
Loc. No.
Kaitkal
T
o
w
e
r
GANTRY
Angle Of
Deviati
on
Span In
AP 1/0
DDE+9
12 22 ' 48 '' LT
AP 2/0
DB+0
11 29 ' 34 '' RT
2/1
DA+0
245
327
2/2
2/3
DA+3
2/4
DA+0
2/6
DA+3
2/7
DA+3
Right
Total
Left
Right
Total
30
30
27
27
155
50
156
206
53
157
210
245
152
178
330
151
174
325
202
207
409
206
211
417
1112
400
1512
2262
400
2662
CT
183
178
361
179
170
349
222
213
435
230
217
447
187
200
387
183
199
382
2No. CT , 5 No 11 KV
390
1862
400
727
DA+3
Remarks
Left
400
385
350
2/5
Section Length
In
Mts.
155
DA+0
Cummu-lative
Span
In
Mts
02 45 ' 24 '' LT
155
m
t
s
190
390
201
194
395
11 KV ,CT
170
192
362
166
188
354
198
174
372
202
174
376
3052
STRINGING - METHODS
TENSION STRINGING
TOOLS AND PLANTS
TENSION STRINGING
TOOLS AND PLANTS
TENSION STRINGING
TOOLS AND PLANTS
TENSION STRINGING
TOOLS AND PLANTS
TENSION STRINGING
TOOLS AND PLANTS
Marking Roller
Mismatch Roller
Joint protector
Walkie Talkie set
Theodalite with stand
Hydraulic conductor cutter
Flags(Red & Green)
Crow bar (1.8m length)
TENSION STRINGING
TOOLS AND PLANTS
TENSION STRINGING
TOOLS AND PLANTS
SAFETY GADGETS
Safety helmets
Safety belts
Safety Shoe
First Aid Box
TENSIONER
PULLER
STRINGING
Steps involved
STRINGING ROUGH
SAGGING
STRINGING FINAL
SAGGING
Final Testing
a) Pre-commissioning of lines:
Readiness of lines for pre-commissioning
i) Completeness of line.
ii) Meggar test of line
b) Commissioning of lines:
Readiness of lines for commissioning
Final Testing
i) Digital photograph of each tower to ascertain
the completeness of tower.
ii) Electrical Inspectors clearance from CEA.
STATUTORY
CLEARANCES
KISHANPUR
20/08/09
MAN MOHAN RAINA
MANAGER T/L
PANIPAT
Forest Land : Sec.-II, FC Act 1980, all RF, PF or any other area
recorded as forest in Govt. records and land notified u/s -IV and V
under this act termed as forest land even it is privately owned.
Social forestry
National Park/Wild life area
Bird sanctuarybed)
Road Xing
DELIGATION OF POWERS
COMPOSITION :-
CONCERNED STATE
:
:
:
:
:
:
:
210 days
10 days
90 days
30 days
60 days
90 days
300 DAYS.
ROUTE SELECTION
Does not involve any human rehabilitation
Monuments of cultural or historical importance
Threat to survival of any community
Public utility services
Avoid WL Sanctuary, National Park, Biosphere Zone etc.
No Infringement with area of natural resources
Minimum Involvement of Road/canal/River/Railway X-ing.
Minimum Involvement of RF/Forests etc.
ROW (Mtrs.)
Maximum
11
33
15
66
18
110
132
220
400
+/- 500 KV HVDC/400 S/C
800
22
27
35
46
52
64-85
The purpose of NOC is to notify the aviation and Air Force authorities the
exact location of towers along the line route.
The purpose of NOC is to notify the these departments about the project so
that the concerned department gets the knowledge of the project and in
case of any proposed scheme in process may advise accordingly, which
otherwise can result into shifting of a part of the route causing loss of
investment..
Cross profile of the existing Power Line has also to be generated and
minimum clearance under worst conditions ahs to be guaranteed
9
1.
With this copy site has to meet the concern Divisional Engineers and get marked
the P&T ckts/ Co-axial cables on the route map submitted by us on the width of 8
Kilometers on the both sides of our line under construction.
Same will be forwarded by the Divisional Engineer to their GM/ Telecom District.
6.
After compilation of the reports received from the GMs of all the Telecom Districts
Divisional Engineer Telecom/ PTCC, T &D CIRCLE of the Region will forward the
same to the DIRECTOR (PTCC), CEA, NEW DELHI
a) For the comments regarding LF Induction on the paralleling Telecom Lines under
worst fault conditions due to proposed power line.
b) In Case of Railway Block Circuits, the break up figures of the L.F. Induced voltage
on station-to station basis and the value of the mutual coupling for each section).
9.
10
10
THANK YOU
We End The Session
Here.