Documente Academic
Documente Profesional
Documente Cultură
CHITALIYA KEVAL(13SOECV13011)
SOLANKI VIJAY(13SOECV13013)
CHUDASAMA DHARMA RAJ
SAGPARIA SAHIL
Introduction
Concrete is the 2nd most consuming material
or
the wall through spikes or bolts and then covering it suitably. Several
alternatives have been used.
Injecting epoxy like material, which is strong in tension, into the cracks in
Deficiency in design
If the structural member is slender, there will
IMPROPER REINFORCEMENT
DETAILING:
i. Abrupt changes in section
ii. Insufficient reinforcement at reentrant
Preventation:
Detailing of reinforcement should be
unequal.
5mm more than the nominal maximum size of
coarse aggregates.
For slabs:
1. Main reinforcement: i) 3d
ii) 300mm
(d= effective
depth)
Whichever is smaller
2. Distribution steel:
i) 5d
ii) 450mm
depth)
Whichever is smaller
(d= effective
Requirement Of Reinforcement
i) Minimum reinforcement
1. for slab:
Shear reinforcement:
inclined
stirrup
For column
Longitudinal reinforcement:
The cross- sectional area of longitudinal reinforcement shall not less
than0.8% nor more than6%of the gross C/S area of the column.
The bars shell not be less than 12 mm in diameter.
The minimum number of longitudinal bars provide in a column a Shall be
four in rectangular and six in circular column.
Spacing of longitudinal bars measure along the periphery of the column
shall not exceed 300mm.
A reinforcement concrete column having helical reinforcement shall have at
least 6 bars of longitudinal reinforcement.
Lateral ties:
Pitch:
Pitch not more than smaller of three values:
1. Least lateral dimension of the column
2.16Xdia. of smaller longitudinal bar
3.300mm
Helical reinforcement:
a) Pitch:
i) 75mm
ii) 1/6XCore diameter
Pitch shall not exceed smaller of
two values.
materials.
Variation in mix proportion due to batching
process.
Variation in the quality of batching and mixing
equipment.
the quality of overall workmanship and
supervision at site
Honeycombing
lack of cover
blowholes
CORROSION OF
REINFORCEMENT
The damage to the concrete due to corrosion
DAMAGE DUE TO SETTLEMENT OF FOUNDATION:
Preventation:
1. increase the soil bearing capacity by:
increase the depth of footing
construct UNDER REMED PILE foundation
Proper compaction before construction
expensive type of soil should be replace up to
certain depth
DAMAGE DUE TO VEGETATION GROWTH:
1.When soil under the foundation of a building
Preventation:
load path)
Damage due to soft story
Damage due to short column
Damage of masonry building are:
1. Out of plane failure
2. In plan failure
3. Connection failure
4. Diaphragm failure
5. Failure due to opening in the walls.
FLOATING COLUMN
3. Damage due to short column effect
During past Earthquake, RC frame buildings
short column
Masonry
unit:
Well burnt brick and solid concrete blocks having a crushing strength not less than 3.5Mpa shall be
used. However, higher strength of masonry units may be required depending upon number of story
and thickness of wall.
Mortar:
Since tensile and shear strength are important for earthquake resistance, use of mud or very weak
mortar is not suitable. a mortar mix of cement: sand (1:6) by volume at least should be used.
Where steel reinforcing bars are provided in masonry, the bars shall be embedded with adequate cover
in cement-sand mortar not leaner than 1:3 or in cement concrete of grade M15 so as to achieve good
bond and corrosion resistance.
Walls:
The thickness of load bearing walls shall not be less than 190 mm and wall length should be greater
than 15m.
The bearing walls in both directions shall be straight and symmetrical in plan as far as possible.
Masonry Bond
Good interlocking of masonry courses at the junction should be ensured as the walls transfer loads to
each other at their junctions. To obtain full bond between perpendicular walls, it is necessary to make
stepped joints by making the corners first to a height of 600mm and then building the wall in between
them, otherwise, a toothed joints can be made in both the walls, in lifts of about 450mm.
Opening in walls:
Opening to be located away from the inside corner by a clear distance equal to at least of the height
of opening but not less than 60cm.
the total length of opening not to exceed 50% by the length of the wall between consecutive cross
walls in single story construction, 42% in two story construction and 33% in three story construction
The horizontal distance between two openings to be not less than half the height of the shorter
opening, but not less than 60cm.
The vertical distance from an opening to opening directly above it not to be less than 60cm nor less
than of the width of the smaller opening.
Different Horizontal band
Types of band
Plinth band:
Provided at plinth level on top of the foundation, it serves as damp proof
Horizontal reinforcement
Dowel bars:
Analysis of damaged
structure:
Following methods can be use for determine strength of damaged
structure.
Conventional methods:
Rebound hammer test.
Ultrasonic pulse velocity method
Advanced methods:
Infrared thermography.
Image processing.
Acoustic emission.
Radar.
Electromagnetic methods.
Impact echo.
In-situ permiability of concrete.