Documente Academic
Documente Profesional
Documente Cultură
C19PT
Lecture 11
Project Evaluation and Control
Session 11
Why do changes occur in projects?
What are the sources of changes?
What is Milestone monitoring
How do we perform Earned Value
Management on a project?
Project Changes
Projects incur numerous changes
Re-designing; Re-planning; Re-working
Impact on time and costs
Sources of Change
Scope Changes:
Scope Creep
Additional project elements
Improvements / quality changes
Baseline Changes
Client requests for improvement in schedule or reduction in costs
Risks
Implementation of contingency plans
Failure
Risks that were not identified
Contractor or Supplier failure
Improvements
Project team changes
Control
4. Taking Action
2. Measuring
Progress
and
performance
3. Comparing Actual
with Planned
Project S-Curve
Tracking schedule & time
Project Base-line
Project S-Curve
Negative variance
Milestone Analysis
Milestones are events or stages of the project that
represent a significant accomplishment
Clear and well defined (Concrete)
Milestone tracking
Simple & effective method
Milestones
Milestone Analysis
Milestone Tracking Chart
35
Cost/1000
30
E
25
20
15
10
10
Week No.
15
20
Performance
Schedule
Planned
Week
Cum Cost ()
PV
1000
2000
3000
4000
5000
6000
Planned
Percentage
Complete
Week
Cum Cost ()
PV
1000
100
2000
75
3000
66
4000
62
5000
6000
Planned
Percentage
Complete
Earned Value
()
EV
Week
Cum Cost ()
PV
1000
100
1000
2000
75
1500
3000
66
2000
4000
62
2500
5000
6000
SV = EV PV
= 2500 - 4000
= - 1500
At week 4, the project is behind schedule by
1500
Earned Value
SV
Planned
Week
Earned Value
()
Cum Cost ()
EV
PV
Actual Cum
Cost
()
AC
1000
1000
1000
2000
1500
2500
3000
2000
3500
4000
2500
5000
5000
6000
CV = EV AC
= 2500 - 5000
= -2500
Project has a cost overrun of 2500
Cost Variance
A
C
SV
CV
SPI =
EV
PV
2500
= 0.625
SPI =
4000
= 9.6 weeks
CPI =
EV
AC
2500
CPI =
= 0.50
5000
BAC
6000
EAC =
=
CPI
0.5
= 12000
Summary
Recognise the source of changes within a
project
Understand the nature of the control cycle and
four key steps in a general project control model.
Understand the benefits of milestone monitoring
Understand how to use Earned Value
Management to track and evaluate a project