Documente Academic
Documente Profesional
Documente Cultură
Brief history
Interesting facts
Background
Ownership Structure
The Concession
Contractual Structure and Contracts
Estimated costs
Terms and conditions of loan facility
Problems
Financial Restructuring.
Conclusion
Eurotunnel-Background
Eurotunnel-Background
Eurotunnel-Background
100%
Eurotunnel
PLC (UK)
100%
79%
Eurotunnel
Finance
S.A
21% Eurotunnel
Finance
Limited
France
Manche
S.A.
(France)
Eurotunnel
General
Partnershi
p
100%
Eurotunnel
Developme
nts
Limited
100%
The
Channel
Tunnel
Group Ltd.
(UK)
Eurotunnel-Background
April 1985- The British & French governments issued
an Invitation for Promoters for Financing ,
Construction, and Operation of a fixed link across
the Channel, without recourse to government
funds or guarantees.
10 proposals received in Oct. 1985. 4 shortlisted:
1. EuroRoute:4.8 Bn. Part bridge/tunnel road/ rail.
2. CTG-FM Eurotunnel System:2.6 Bn. twin-bore rail
tunnel.
3. Eurobridge:5 Bn. 23 mile composite fiber
suspension bridge.
4. Channel Expressway: 2.5 Bn. Twin-bore road
tunnel with separate rail tunnel.
Eurotunnel-Background
January 1986-CTG-FM Eurotunnel
System was selected as the winning
project.
February 1986-British and French
governments signed a treaty by
which they authorized construction of
the Eurotunnel system and granted the
Concession to the winning bidders CTG
(UK) and FM (France).
The Concession
Gave CTG-FM the right to build and operate
the Eurotunnel System for a period of 55
years. Later extended to 65 years, expires in
2052.
On expiry it has to hand back the system to
British and French governments in good
working order.
CTG-FM have the freedom to establish tariffs
and determine operating policies.
British and French governments committed
that no competing fixed link could be before
the end of 2020 without CTG-FMs approval.
Main Contracts
Construction Contract
Railway Usage Contract.
MdO contract
Financing Agreements
Insurance contracts.
Partnership and Corporate Structure
Agreements.
MdO Contract
Number of Banks
Events of default
Eurotunnel would be in default under the
Project Loan Facility, if any of the following
events occurred:
1. One of the default cover ratio tests is not
met.
2. Eurotunnel System opening is delayed for
more than one year.
3. An unremedied breach of Eurotunnels
obligations occurs.
4. Once repayment starts, amounts
outstanding under the Project Loan Facility
exceed certain specified amounts.
Problems-Design changes
1. No cooling system envisaged in the
original proposal.
2. Friction caused by trains and heat
generated by electrical equipment could
raise temperature to 50 degrees celcius.
3. An elaborate cooling system was installed
carrying chilled water through several 100
kms of pipng.
4. Due to air pressure created by trains
travelling at 160 kph, tunnel components
needed to be re-designed to new
aerodynamic standards.
1.
2.
3.
4.
Financial Problems
1995 Apart from increase in construction
cost,it was clear actual revenues were well
below target
Sept. 95 interest payments on junior debt were
suspended. Junior debt was the bulk of total
debt
Breathing space-banks agreed not to pursue
unpaid interest through legal channels while
Eurotunnel tried to resolve its debt problems.
Cash flow problem were due to
1. Fierce price competition by ferry companies.
2. Failure of railways to develop traffic
3. Increase in operating costs
Current Position
On a more stable footing, paying its
first dividend in 2009 and begun to
pay down net debt that stands at
4.1 billion.
Conclusion