Cementacin de Liner

Definicin cualquier columna de Casing con su


tope debajo de la superficie.

2012 HALLIBURTON. ALL RIGHTS RESERVED. 1


Razones del uso de los Liners

Reduccin de costo
Menos restriccion ID
Permite
Permite mayor
mayor caudal
caudal durante
durante la
la perforacin
perforacin yy cementacion
cementacion
Cuando la tensin supera las especificaciones del casing.
Reduce el peso sobre la cabeza
Requerido para Well Construction
Sidetracks
Sidetracks
Multi-Laterals
Multi-Laterals
Liner
Liner ranurados
ranurados

2012 HALLIBURTON. ALL RIGHTS RESERVED. 2


Tipos de Liner

Drilling
Drilling Liner
Liner
Asentado a travs de una
seccin de pozo con plan de
continuar la perforacin.
Extender un casing intermedio.
Aislar zonas problemticas
Aislar zonas dbiles o
presurizadas

2012 HALLIBURTON. ALL RIGHTS RESERVED. 3


Tipos de Liner

Produccin Liner
Asentado a travs o
arriba del intervalo de
produccin.
Utilizado como casing
de completacion.
2012 HALLIBURTON. ALL RIGHTS RESERVED. 4
Tipos de Liner

Scab or Stub Liner


Extiende desde el tope
de un previo liner hasta
un punto debajo de la
cabeza de pozo. No
alcanza a llegar a la
cabeza.
2012 HALLIBURTON. ALL RIGHTS RESERVED.
Repara casing daado
5
Tipos de Liner

Tie-Back Liner
Se extiende desde el
tope de un previo liner
hasta la cabeza del
pozo.
Protege casing previos
Aislar topes de liner
2012 HALLIBURTON. ALL RIGHTS RESERVED.
previos
6
Consideraciones sobre la cementacin de liner

Pequeo anular
Alta
Alta presiones
presiones de
de friccin
friccin por
por consecuencia
consecuencia alta
alta ECD
ECD
Potencial
Potencial perdida
perdida de
de circulacin
circulacin
Incrementa
Incrementa elel potencial
potencial de
de flujo
flujo de
de Gas
Gas
Previsible
Previsible aprisionamiento
aprisionamiento diferencial
diferencial
Critica
Critica Centralizacin
Centralizacin
Limitado caudal de bombeo
Limitaciones
Limitaciones en
en el
el colgador
colgador del
del Liner
Liner
Altas
Altas ECD
ECD
Potencial
Potencial pobre
pobre desplazamiento
desplazamiento del
del lodo
lodo

2012 HALLIBURTON. ALL RIGHTS RESERVED. 7


Consideraciones sobre la cementacin de liner

Limitado Movimiento de los caos


Normalmente
Normalmente sese asienta
asienta el
el Liner
Liner antes
antes de
de la
la cementacion
cementacion
Por
Por aprisionamiento
aprisionamiento diferencial
diferencial

Altos pesos de lodo


Cementos
Cementos yy espaciadores
espaciadores Densificados
Densificados
Densidad
Densidad de
de la
la lechada
lechada aa lo
lo menos
menos 11 ppg
ppg >> lodo
lodo

2012 HALLIBURTON. ALL RIGHTS RESERVED. 8


Consideraciones sobre la cementacin de liner

Se necesita exactos datos del pozo


Gradiente
Gradiente de
de fractura
fractura
Presin
Presin poral
poral
Caliper
Caliper para
para el
el calculo
calculo de
de volumen
volumen yy uso
uso del
del simulador
simulador

Temperatura
BHCT
BHCT @ @ liner
liner bottom
bottom
BHST
BHST @ @ liner
liner bottom
bottom and
and top
top
Altas
Altas diferencias
diferencias puede
puede requerir
requerir largos
largos tiempos
tiempos de
de espera
espera (WOC)
(WOC) oo usar
usar el
el
SCR-100
SCR-100
Wellcat
Wellcat simulador
simulador dede temperatura
temperatura
2012 HALLIBURTON. ALL RIGHTS RESERVED. 9
Consideraciones sobre la cementacin de liner

Diseo de la lechada
Estable, sin agua libre o asentamiento de solidos
Baja reologa como para minimizar el ECD pero suficiente para
mantener en suspensin los slidos
Fluid loss 50-100 cc/30 min; menos de 50 cc si hay probabilidad
de migracin de gas o si el anular es extremadamente pequeo
Resistencia a la compresin de 500 psi en el tope del liner antes de
perforar
Adecuado tiempo de bombeabilidad para permitir el batch mixing,
la operacin de colgar el liner, circulacin del exceso de cemento.

2012 HALLIBURTON. ALL RIGHTS RESERVED. 10


Consideraciones sobre la cementacin de liner

Concerniente a la contaminacin
Siempre efectuar los test de contaminacin en el laboratorio
Lodos de altas densidades pueden estar altamente cargado de
qumicos
La Contaminacin resulta en alta viscosidad & alto ECD
Espaciador en el drillpipe a la altura del colgador si el lodo
del anular es OBM
Evitar los espaciadores SUPERFLUSH

2012 HALLIBURTON. ALL RIGHTS RESERVED. 11


Consideracin en la seleccin del tipo de colgador a usar

Asentamiento mecnico e hidrulico


Rotacin y/o reciprocacin durante la cementacin

2012 HALLIBURTON. ALL RIGHTS RESERVED. 12


VersaFlex Sistemas de Liner
Un Nuevo Reto
LINER HANGERS EVOLUTION VersaFlex

2012 HALLIBURTON. ALL RIGHTS RESERVED. 14


Liner Top Reliability
VersaFlex

Pe r c e n t o f A ll o f Co mp a n y X 's In c id e n ts
Liner-Incident Factors
60%
50% Company A
40% Company B
30% Company C
20%
10%
0%

2012 HALLIBURTON. ALL RIGHTS RESERVED. 15


Advantages Over Conventional Equipment

Single redundant sealing area


No slips
No tortuous fluid flow paths
Simplicity
Rotation and reciprocation
No pre-set risk
No need to dress the liner top
Immediate test

2012 HALLIBURTON. ALL RIGHTS RESERVED. 16


Installation Procedure VersaFlex

Drill hole
Run Liner, 2 min/std, circulate if is necessary until tag bottom
Circulate up to 10 BPM Max rpm 25
Cement and drop PDP set plug with 500 psi above final displace pressure
Deploy Setting Ball
Pressure up to expand Hanger 3300-5000 psi for 7 x 9 5/8; 6500-8000 psi
for 5 x 7
Pressure released, Check PU weight 100K
Disengage Setting Tool with 50K SO weight, POOH tool
Reverse out any cement on top of Liner
Pull out of hole
2012 HALLIBURTON. ALL RIGHTS RESERVED. 17
Installation Procedure Other Systems

Drill hole
Run Liner 3 min/std
Circulate Max 1,400 psi to prevent LH pre-settings
If stall out occurs work out the torque very slow this will prevent emergency release activation.
Tag bottom and circulate Liner & DP contents max 5 BPM
Deploy Setting Ball and set liner 2,300 psi if liner does not set increase pressure 200 psi at the
time.
Increase pressure to 2,800 psi to release setting tool. BOP, If not use left hand torque
mechanism 4,400 ft-lb
Pressure up to 3,400 psi to shear out the ball and re-establish circulation formation will be
expose to this pressure
Mix and pump cement, release PDP
POH 10 stand and circulate the long way round
2012 HALLIBURTON. ALL RIGHTS RESERVED. 19
Advantage VersaFlex

Easy to deploy into the hole


Fast operation RIH 1.5 min/stand others 3 min/stand
Hanging capacity 400K # per seal
There is no risks to liner top leak (no cement on the Over Lap) because
has seals on top.
Solid Drill Down. (It is possible rotate while RIH).
It is possible rotate and reciprocate while cement the hole.

2012 HALLIBURTON. ALL RIGHTS RESERVED. 20


Advantage VersaFlex

By pass area/Circulation area.


Eliminates tortuous paths through the liner
Less risk to have remedial cementing jobs due benefit of bigger by pass
area.
It is possible perform an hydraulic test on the liner top immediately after set
into the hole.
Versaflex does not have external mobile parts.

2012 HALLIBURTON. ALL RIGHTS RESERVED. 21


VersaFlex Consideraciones de Cementacin
Diseo de cementacin para un liner expandible

2012 HALLIBURTON. ALL RIGHTS RESERVED. 23


Consideraciones Especiales
Baja consistencia menor a 30 Bcs
Bajo desarrollo de esfuerzo de gel
Lechada de cabeza retardada 4 hrs sobre tiempo de operacin

Ventajas
Mayor tasa de circulacin
Reciprocacin/Rotacin durante la cementacin
En caso de empaquetamiento anular la
reciprocacin de Liner es vital para liberarse
La expansin del liner protege el sello del
anular despus de cementar
2012 HALLIBURTON. ALL RIGHTS RESERVED. 24
Consisten Grafica TT Lechada de Cabeza (15 Bcs)
cy (Bcs)
Bourdon

Tiempo (min)
2012 HALLIBURTON. ALL RIGHTS RESERVED. 25
Grafica Resistencia a la Compresin (psi)

2012 HALLIBURTON. ALL RIGHTS RESERVED. 26


Grafica trabajo de Cementacin
Slurry Density (ppg) B Slurry Volume for Stage (bbl) D
A B Slurry Rate (bpm) C Pressure (psi) A C D

Bombeando lechada de cemento


3500 9 90
18

8 80
3000
16
Espaciador
7 70
2500
14
6 60
2000
12 5 50
1500
4 40
10
1000
3 30
8
500
2 20

0 6
1 10
Desplazamiento

-500 4 0 0
08:20 08:40 09:00 09:20 09:40
2/3/2005 2/3/2005
Time
CemWin v1.7.0
04-Feb-05 18:00 H A L L IB U R T O N

2012 HALLIBURTON. ALL RIGHTS RESERVED. 27


Grafica Expansin de Liner
Slurry Density (ppg) B Slurry Volume for Stage (bbl) D
A B Slurry Rate (bpm) C Pressure (psi) A C D
1.0 5
3500 Expansion Colgador
18

3000
17 4

2500 16

2000 15 3

14 0.5
1500

13 2
1000
12
500
11 1

0
10
1
-500 9 0.0 0
10:46 10:48 10:50 10:52 10:54
2/3/2005 2/3/2005
Time
CemWin v1.7.0
04-Feb-05 18:02 H A L L IB U R T O N

2012 HALLIBURTON. ALL RIGHTS RESERVED. 28


POZO 1 POZO 2 POZO 3

2012 HALLIBURTON. ALL RIGHTS RESERVED. 29


POZO 4 POZO 5 POZO 6

2012 HALLIBURTON. ALL RIGHTS RESERVED. 30