Documente Academic
Documente Profesional
Documente Cultură
Mega Projects by their very nature consist of smaller individual projects that integrate
together to form a whole.
In a similar fashion the estimate for such a project also comes from a multitude of diverse
disciplines with differing sources and work practices.
This paper will use a case study to show how a risk model for the Cost Estimate was built
in Palisade @Risk to identify appropriate levels of Contingency and Management
Reserve.
Control Estimate
Systemic risk models
Quantitative schedule risk models
Risk ranging workshops
Various risk registers
2
Contingency & Management Reserve
Contingency
Contingency is the amount of money used in the estimate to deal with the uncertainties
inherent in the estimating process. Contingency is required because estimating is not
an exact science.
The amount of infill and concrete to cover an underground pipe, the number of man-
hours to complete the task, and the actual all in labour rate, are all best estimates until
the work is complete
Management Reserve
An amount added to the estimate to allow for specific risks that may or may not occur
that are within the projects control or influence. Risk is defined as an undesirable
potential outcome and its probability of occurrence
Does not include force majeure, currency risk, political risk etc
Scope
Both amounts are based on a defined scope. Should scope change , the estimate must
be revised to reflect such changes in scope.
Neither Contingency nor Management Reserve are a source of funds to cover scope
changes
3
4
Mega Project vs Project Portfolio
Key Differences
So why is a Mega Project so different to a Portfolio of Projects being executed by a
Company.
Key differences are:
Same key personnel
Mega project is a number of inter related projects with numerous key interfaces. Any
delay or changes to one can have a significant effect on one or the others
Site Wide Services common to all sub projects
Same geographical location
Effect
Must not underplay the significance of these differences. Sub projects must not be
modeled in isolation
Liberal use of correlation between sub projects to avoid nodal bias
Schedule must be modeled at the mega project level ensuring all interfaces are
included.
5
Identifying the Risks
Likelihood of Occurrence
Consequence Very Low Low Medium High Very High
Very High 5A 5B 5C 5D 5E
High 4A 4B 4C 4D 4E
Medium 3A 3B 3C 3D 3E
Low 2A 2B 2C 2D 2E
Very Low 1A 1B 1C 1D 1E
6
Typical Risk Register
7
Typical Boston Square
8
The Cost Model
Main input to the Cost Model was the Control Estimate. However elements of the
estimate were modelled using a variety of techniques and then brought into an
overall Cost Risk model
9
Traditional Probability Distribution Functions
Risk Uniform
Used when we have no idea what the
value is between two limits
Risk Triangle
Most Popular distribution to show
Most Likely value tapering to a Min
and Max Fundamental
Flaw of Triangle
and Trigen is
when the
Risk Trigen
distribution is
Modification of Triangle
skewed
Allows for a finite probability of
achieving Min & Max Values
11
Most Likely =5, Min =4, Max =15
Most Likely = 5
Mean = 8
P50= 7.58
Most Likely = 5
Mean = 6.5
P50= 6.16
12
AACE International Recommended Practice No. 41R-08
Monte Carlo software for risk analysis requires identification of a probability density
function (PDF) for each critical item. In rare instances the behavior of a critical item is
known to conform to a specific type of PDF such as a lognormal or beta distribution,
which reflects items that may skew heavily to one side of a distribution. However in
most instances it is unlikely that the actual type of PDF that truly represents the item is
known. Thus a reasonable approximation is to use either
- Triangular Distribution
In most cases, the double triangular distribution is a better approximation since it can be
made to conform to the implicit skew of the project teams probability assessment. The
double triangle allows the risk analyst to use the probabilities which the project team
believes are reasonable rather than letting the triangular distribution dictate a probability
which, more often than not, is invalid.
13
Double Triangle Method
Probability Density
Area = Underrun Probability
a c Random Variable x b
Most Likely = 5
Mean = 6.5
P50= 5.0
14
Double Triangle Method
F1
Probability Density
F2
Urun 1-Urun
Min ML Max
0% 25-Feb-13 -122
5% 07-May-13 -51
10% 23-May-13 -35
15% 04-Jun-13 -23
20% 13-Jun-13 -14
25% 21-Jun-13 -6
30% 28-Jun-13 1
35% 05-Jul-13 8
40% 11-Jul-13 14
45% 17-Jul-13 20
50% 22-Jul-13 25
55% 28-Jul-13 31
60% 02-Aug-13 36
65% 09-Aug-13 43
70% 16-Aug-13 50
75% 23-Aug-13 57
80% 01-Sep-13 66
85% 11-Sep-13 76
90% 24-Sep-13 89
95% 12-Oct-13 107
100% 24-Dec-13 180
=RiskLoglogistic(-1063,1088.2,38.361, RiskFit("Schedule","RMSErr"),
RiskName("Schedule"), RiskStatic(0))
17
Use of a Systemic Risk tool
Systemic Risk
Systemic risk drivers such as the level of project scope definition affect
individual, disaggregated estimate line items in a way that is hard to see and
predict.
Best practice is to address systemic risk drivers using empirical knowledge
(from historical data) to produce stochastic models that link known risk
drivers (e.g. scope definition) to bottom line project cost growth.
It was decided that this approach would be best suited for the Process Plant,
which formed the major part of the cost estimate.
Conquest Consulting Group , who have wide experience in the use of such
tools, were engaged to construct a parametric model which used a series of
questionnaires to the project team based on :
- Contractor Organisation
- Contractor Experience
- Project Planning
- Execution Strategy
- Scope Definition
Fit Manager was again used to integrate the results from the parametric
model into the overall model
18
Systemic Risk Questionnaire
Case Description: SNAM
Date: 9/30/2010 & 10/22/2010
2 Enter Contractor Bid Value 1,079,000 ($ thousands) Currency Canadian$
Enter Execution Schedule Bid Duration 39.8 (months)
added note:
Contractor Organizational Structure 3
Meets expectations with regard to the proposed organization structure to support the project.
added note:
Alignment of JV Partners 3
Meets expectations with regard to clear and documented alignment of JV Partners.
added note:
Key Project Personnel Proposed 4
Does not meet expectations with regard to the key personnel proposed for the project (years of experience, applicable experience, guarantee of
staying with the project, etc.)
added note:
Contractor Ramp-up Strategy and Capability 3
Meets expectations with regard to the proposed ramp-up strategy and capability to adequately resource the project in a timely fashion.
added note:
Contractor Resource Capability and Availability 4
Does not meet expectations with regard to resource capabilities and availability (such as number of in-house resources and capability to contract
resources).
added note:
Alignment with Subcontractors and Suppliers 3
Meets expectations with regard to alignment of the contractor with sub-contractors and suppliers.
added note:
Contractor Organization Evaluation 3.3 19
Specific Risk Input
Problems
Prior to release of @Risk 5.0 there were inherent problems using this method in that
Tornado Diagram showed both Probability and Impact as two separate risk inputs
RiskMakeInput
@Risk5.0 onwards allowed for use of RiskMakeInput to combine the two together.
Use extract from Risk Register to directly map risks into the model
RiskID Description Score Prob Min $ Max $ Risk amount $
FFH-013 Construction in advance of sufficient engineering A3 5% 2,000,000 3,500,000 0
20
Risk Results
Summary Results
Individual Risk models were established on separate MSExcel sheets and outputs
summarised on tabular results sheet
Extensive use made of the @Risk function RiskPercentile to provide tabular output that
could be copied and pasted direct into reports
$MM Estimate Risked Value 50% 70% 90% P50 P70 P90
Process Plant $918.3 $918.3 $1,038.2 $1,107.7 $1,209.4 13.1% 20.6% 31.7%
SubSurface Development $1.6 $1.6 $1.8 $2.0 $2.3 16.4% 27.2% 42.9%
Drilling & Completions $193.8 $193.8 $208.4 $217.0 $229.3 7.6% 12.0% 18.3%
Infrastructure $124.4 $124.4 $133.4 $137.4 $143.3 7.2% 10.4% 15.2%
Midstream $30.2 $30.2 $33.2 $34.6 $36.6 9.9% 14.6% 21.2%
Business & System Management $11.3 $11.3 $12.8 $13.2 $13.9 13.2% 16.8% 22.7%
Ow ners Costs $156.6 $156.6 $171.7 $176.4 $183.2 9.6% 12.6% 17.0%
Additional Specific Risk $.0 $.0 $22.3 $28.2 $38.1
TOTAL PROGRAM $1,436.2 $1,436.2 $1,623.6 $1,693.4 $1,798.6 13.0% 17.9% 25.2%
Management Reserve $.0 $.0 $17.9 $30.7 $59.6
Overall Total $1,436.2 $1,436.2 $1,648.2 $1,717.8 $1,825.1 14.8% 19.6% 27.1%
Note the values in the above table are for a fictitious project
21
Summary
The cost risk model built in @Risk used a variety of techniques to both represent
uncertainty from ranging workshops and from other studies. Highlights include:
Use of the Fit Manager to replicate output from other models as input to the overall risk
model, in particular:
- Results from a quantitative schedule risk analysis
- Results from systemic parametric risk analysis
- Automatic recalculation of the curve fit on change of input data
Use of RiskPercentile and other output functions to provide templated report formats
that can be copied and pasted direct into presentational materials
22
Any Questions
23