A-ST43 Submission

King post removal


(between roof-concourse and
concourse-base)
Under this submission
Under this submission
Under separate
submission
C

C
Construction Sequence for Section C-C
Construction Sequence for Section C-C

1. Cast all inner walls, columns and external


walls
Construction Sequence for Section C-C

1. Cast all inner walls, columns and external walls.


2. 2.1 Cut Kingpost between roof and concourse slab
2.2 Cut Kingpost between concourse and base slab
3. (above roof) Cast concrete footing for kingpost and
install steel bracing and cut kingpost above roof SSL
4. Backfill to 107.18 mRL

Sequence 2 and 3 are interchangeable. ONLY IF Sequence


3 is done first, sequence 2.1 and 2.2 are interchangeable.
Construction Sequence for Section C-C

1. Cast all inner walls, columns and external walls.


2. 2.1 Cut Kingpost between roof and concourse slab
A 2.2 Cut Kingpost between concourse and base slab
3. (above roof) Cast concrete footing for kingpost and
install steel bracing and cut kingpost above roof SSL
B 4. Backfill to 107.18 mRL

C Sequence 2 and 3 are interchangeable. ONLY IF Sequence


3 is done first, sequence 2.1 and 2.2 are interchangeable.

Possible Sequences:
1. B C A

2. A B C

3. A C B
Construction Sequence for Section C-C

5. Remove S1 Slab
6. Retrieve Kingpost
7. Backfill to Ground Level
8. Cut SBP wall 2.0m below final ground level and backfill

Sequence 6 and 7 are interchangeable


Construction Sequence for Section E-E

E
Construction Sequence for Section E-E

A
1. Cast inner walls, columns and external walls
2. Install steel bracing and cut kingpost above roof SSL
B 3. Cast 2.0m x 0.5m strengthening beam along GL 3-6
4. Cut kingpost between roof and concourse slab
5. Backfill 1.5m above roof level

Sequence:
A B
Construction Sequence for Section E-E

6. Remove S1 Slab
7. Retrieve Kingpost
8. Backfill to Ground Level
9. Cut SBP wall 2.0m below final ground level and backfill

Sequence 7 and 8 are interchangeable


King post Transfer
(Above Roof Slab)
Stage 1 Partial casting of footing and steel frame installation

1. Partially cast the concrete footing with


anchorage into roof slab
2. Place the pre-loading jacks on top of
footing
3. Install transfer beam, stiffeners and
bracings.

Plan View
Stage 2 Kingpost transfer and cutting

1. Preload jack
2. Cut bottom part of King post
3. Finish up the water proofing
Stage 3 Casting of remaining footing

1. Weld stiffeners to Kingpost


2. Cast remainder of concrete footing
Stage 4

1. Once concrete gained strength, remove


the steel frame and bracings
Waterproofing Details