Sunteți pe pagina 1din 15

Project management structure

Project
manager

Construction
Architect Engineer
manager
Conceptual design phase 1

Conceptual design

Design
3D model Material
developme Report Approval
design take off
nt
Phase 2nd Detailed design

Mechanical
Garden and Electrical
/piping Civil work Landscape General
plants design
design

soil Landscap
Design Design Structure e deign Project
specificat
criteria criteria design plan
ion

Tress, Piping
plant Cable Concrete Mobility Health
specificat specificat
specificat specificat specificat and
ion ion
ion ion ion security
Construct
Water ion and Paints
Switch Lighting
requirem assembly specificat Operatin
boards and
ents specificat ion g manual
water
ion

Material Construct Access


Materials Material Final
take off ion and requirem
take off take off report
assembly ents

Material
Line list take off
Construction design phase 3rd

construction

Exterior
Foundati Rough Exterior Exterior Electrical Wallboa Exterior Interior
Excavate Roof plumbin Flooring Painting
on wall siding painting work rd fixture fixture
g
Project time line
Conceptual phase -I Detailed Phase II Construction Phase-III
10 weeks
26 weeks 44 weeks

ID ACTIVITIES Weeks ESTIMATED COST


1 General 7
2 Landscape 13
3 Mechanical piping 14
design/WORKS
4 Electrical 6
design/WORKS
5 Civil work 13
6 Construction 2
schedule
7 Gardens and plants 9
ID Construction activities Weeks ESTIMATED COST

1 Excavate 2
2 Lay the foundation 4
3 Put up the rough wall 10
4 Put up the roof 6
5 Install the exterior plumbing 4
6 Install the interior plumbing 5
7 Put up the exterior siding 7
8 Do the exterior painting 9
9 Do the electrical work 7
10 Put up the wallboard 8
11 Install the flooring 4
12 Do the interior painting 5
13 Install the exterior fixtures 2
14 Install the interior fixtures 6
EXCAVATION
PERT ANALYSIS

FOUNDATION

ROUGH WALL

EX. PLUMBING

ROOF ELECTRICAL
WORK
INTR.PLUMBING

EXTERIOR
SIDING WALLBOARD

EXTERIOR INTER.
PAINTING FLOORING
PAINTING

EXTR. INTER.
FIXTURE FIXTURE
FINISH
EXCAVATION
CRITICAL PATH

FOUNDATION

ROUGH WALL

EX. PLUMBING

ROOF ELECTRICAL
WORK
INTR.PLUMBING

EXTERIOR
SIDING WALLBOARD

EXTERIOR INTER.
PAINTING FLOORING
PAINTING

EXTR. INTER.
FIXTURE FIXTURE
FINISH
ES 0
EXCAVATION
PERT ANALYSIS EF 0

ES 0
FOUNDATION
EF 2

ES 2
ROUGH WALL
EF 6

ES 16 ES 16 EX. PLUMBING ES 16
EF 22 EF 20 EF 23

ROOF ELECTRICAL
WORK
INTR.PLUMBING
ES 20
EF 25 ES 25
EXTERIOR ES 22
SIDING EF 33
EF 29 WALLBOARD

EXTERIOR ES 29 ES 33 INTER.
PAINTING FLOORING
EF 38 EF 77 PAINTING
ES 44
ES
EF 44
EXTR. ES 38 ES 38 INTER. EF
FIXTURE EF 40 EF 44 FIXTURE
FINISH
Path Length
1) START-A-B-C-D-G-H-M- FINISH 2 +4 +10 +6 +7 +9 +26 = 40 weeks
2) START-A-B-C-E-H-M- FINISH 2+4+ 10+ 4 +9 +2 +2+ 6 =31 weeks
3) START-A-B-C-E-FJ-K-N -FINISH 2 +4 +10+ 4 +5+ 8+ 4 +6 =43 weeks
4) START-A-B-C-E-F-J-L-N-FINISH 2 +4 +10+ 4 +5 +8 +5 +6 = 44 weeks
5) START-A-B-C-I-J-K-N-FINISH 2+ 4 +10 +7+ 8+ 4+ 6 +6 =41 weeks
6) START-A-B-C-I-J-L-N-FINISH 2 +4 +10+ 7 +8 +5+ 6 +6 =42 weeks
PERT ANALYSIS

ES
CIVIL
EF WORK

ES
ES ES
EF
EF EF
LANDSCAP ELECTRICA GARDEN
GENERAL CONSTRUC
E L WORK AND FINISH
TION
PLANTS
ES ES
ES
EF EF
EF

MECHINIC
AL WORK

ES
EF
PERT ANALYSIS

ES 35 Material
EF 5 take off
ES 0 ES 50
EF 0 EF 50
Conceptual
design COMMENT
3D model
developme S
nt
ES 15
EF 20 Design
Report

ES 35
EF 15
CRITICAL PATH

Material
take off

Conceptual
design COMMENT
3D model
developme S
nt

Design
Report
POPULATION
MALES FEMALES TEENAGERS KIDS

9%

10%

23% 58%
AVERAGE INCOME
POPULATION
MALES FEMALES TEENAGERS KIDS

9%
10%

23% 58%

S-ar putea să vă placă și