Documente Academic
Documente Profesional
Documente Cultură
2
The coal plant getting coal from mines is inferior than
for what it is designed for.
The inferior coal means it may have lower carbon
contents, higher percentage of ash, higher moisture and
volatile matters. In other words the Gross calorific value
and net calorific value may be lower than what is desired.
Incomplete burning of coal inside the furnace.
The quantity of unburnt coal going waste into the bottom
and fly ash is high.
Mills not performing as they should.
Quantity of Excess air is either high or low than the
theoretical one.
Fan not performing as expected. In other words a proper
furnace draught is not established.
High air ingress inside the furnace. 3
Condition of boiler tube is bad. i.e High Scale
deposits inside Super heater tubes, Ash deposits on
the outside of the tubes, reducing heat transfer,
Boiler tubes leakages, Clogging of economiser fins,
Distortion in alignments in the various tube banks,
Poor weld joints.
Soot Blower not operating as expected.
Higher rate of Boiler blow down.
Improper operation.
Lack of training.
Still many more obviously will reduce the boiler
efficiency meaning less heat being transferred to the
boiler feed water and Steam.
4
What are the things which are in our control and if we care
about them certainly plant performance / availability /
capacity factor and as a result more generation and higher
efficiency can be achieved.
6
Now a days you will see that a new technology called
"SUPER CRITICAL" is being employed by many new plants.
In case of super critical power plants the efficiency of the
turbine is increased as the super critical boilers work at a
very high pressure, which ultimately increases the work
done by the turbine.
There are 3 TPS technologies available at present
1) Sub-critical technology (design efficiency 3637%)
2) Super critical technology (design efficiency 4445%)
3) Ultra Super critical technology (design efficiency more
than 45%).
So, Ultra Super critical technology power plant shall be
the best from efficiency point of view.
7
Some general methods to improve the efficiency
are
1. Operate the power plant near to design main steam
pressure & temperature.
2. Use of VFDs
3. Replace conventional 6.6 KV HT motors with energy
efficient motors.
4. Proper maintenance of LP & HP heaters, Economiser,
Super heaters & Air-preheaters.
5. Attending passing of high energy drain valves.
6. Maintaining proper vacuum in condenser.
7. Using LED lights for lighting purpose
8
8. Optimizing and attending leakages of instrument &
service air.
9. Checking of conditions of pumps
10.Optimizing the running of air conditioning system
11.Operating equipment close to design efficiency
12.Optimizing the number of coal mills running
13.Optimizing the running of conveyor belts for
transporting coal from coal handling plant to main
power house site.
14.Optimizing total air flow
15.Ensuring proper working of SADC dampers, soot
blowers & burner tilt mechanism.
16. Maintain thermal insulation in right condition
17. Plant operation, follow procedures
18. Operate the Pump and fans near to it,s BEP 9
18. Training, peer review, honest audit
19. Proper maintenance, Testing and calibration
20. On line instrumentation and their calibration
21. Efficient online repairing or maintenance facility
22. Root Cause analysis and implementation of the finding
23. Research and material failure analysis
24. Market/venders support
25. Welders qualification
26. ISI program and still many more
27. House Keeping
28. Labelling, sign boards and paintings of pipe lines
29. Implementation of safety culture
30. Workers (Operation and Maintenance qualifications) with
incentive
10
What is not in our hand:
1. Quality of coal supplied
2. Quality of water supplied
3. Quality of ambient air
11
With my limited knowledge, few things which I
can think of to improve thermal plant efficiency
are as follows-
Using good quality coal
Thermal plants have very low efficiency mainly due to burning
of coal which requires a lot of energy.
In India, we generally mix very small amount of high quality
coal which is imported from foreign countries with coal
obtained from Indian mines which is of generally low
efficiency.
By increasing the amount of high quality coal concentration,
efficiency can be improved but then it will also lead to increase
in power production cost which ultimately is to be paid by
consumers. Hence , there must be balance between efficiency
and cost.
12
By reducing the leakage of steam, flue gases etc:
The leaked out steam does not contribute to the power
generation and is wasted thus decreasing the overall efficiency.
Hence, leakage must be reduced which can be done by
continuous real time monitoring of boiler, pipes, heat exchanger
etc using advanced software and computation technologies.
Also, the seals of boiler, pipes etc must be examined regular and ,
if required, must be replaced.
Continuous monitoring of coal and air input to boiler
The amount of coal and air being fed to boiler must be
continuously monitored in real time and must be regulated as
required.
13
Higher plant availability or higher availability factor will
also lead to higher plant efficiency.
Online data or operating parameters monitoring by data
acquisition or the distributed digital control system will
also help in achieving exacting information helping to
take corrective measure timely , which is a key to
achieving higher plant efficiencies.
ShB - hf
B = ----------------------- x 100
L x C.V Where:
ShB= Enthalpy of S.H Steam ( Kcal/Kg) at Boiler
hf = Enthalpy of feed water (kcal /kg)at F
TS = Total Steam supplied in kg
L = Fuel Burnt
CV = Calorific Value of fuel 15
Turbine efficiency:
16
The heat rejected in condenser is about 45 to 55% of the total
available heat energy available at turbine inlet. Thus cycle
efficiency:
17
G = Electrical energy sent out (kWhr x 860)
----------------------------------------------------- x 100
Mechanical Work
os = B x T x C x G
OTA = T x C x G
OS = B x OTA
18
Heat Rate: Heat rate is defined as heat supplied to
steam to produce I KWh of electrical energy:
19
Typical Losses
Typical Losses
Pressure Temp. Boiler Turbine & Generator Total To bus bar
cycle
Bar 0C % loss % loss % loss % age %age
output
41.4 455 14 50.25 1.75 72 28
62 480 13 55 2 70 30
93 510 12.5 53.75 2.25 68.50 31.5
103 536 11 52.5 2.5 66 34
162 565 10 49 3 62 38
241 593 9 48.25 3.75 61 39
310 650 9 46.5 4.0 50.5 49.5
20
Typical Boiler Losses:
1. Dry Flue Gas loss
2. Wet flue gas loss (loss due to moisture in fuel and due
to moisture formed by combustion of H2 in fuel
3. Moisture in combustion Air Loss
4. Unburnt carbon loss carbon in Ash Loss
5. Unburnt gas loss -- Due to incomplete combustion of
carbon
6. Radiation and unaccounted losses
21
Dry Flue Gas Loss depends upon two factors
Excess Air
Air Preheater gas outlet temperature high
Excess Air: Excess air is the quantity of air over and above
theoretical air being fed into the furnace by FD fans for
complete combustion of pulverised coal. This hoovers
around 20%. Too little excess air fuel is not completely
burnt and too much lead to greater amount of heat carried
to stack by flue gas by N2 contained in the excess. This
heat loss amount to significant loss and this can be
measured by measuring the O2 in flue gas.
22
Air heater gas outlet temperature:
The air heater outlet gas temperature should be lowest
from the point of overall efficiency. On the other hand
this temperature should be higher than the dew point of
sulphur which otherwise will cause condensation and
then corrosion of the ducting. For Indian coal with
sulphur around 0.5% air preheater gas outlet temp be
around 1300C. Lower leads to corrosion and higher
decrease in Boiler eff. A typical 220C rise in gas outlet
temp. reduces the boiler eff. By 1%.
Causes for higher gas outlet temp.
Lack of shoot blowing
Deposits on Boiler heat transfer surface
High excess air
23
Low final feed water temperature
Higher ele. Burner in service at low loads.
Defective baffles and bypass dampers, causing gas
short circuiting some heater transfer surface.
Improper combustion
Poor milling plant performance An incorrect PA / Sa
ratio causing delayed combustion
Air re-circulation reduces the heat removed from flue
gas.
Air in leakage before the combustion chamber.
24
Low air heater gas outlet temperature: Though in the
short run, low APH gas outlet temperature improves
eff. In the long run it can result in lower boiler eff.
Because of deposition of sulphur on its elements and
corrosion. The deposited material may also cause loss
of availability and reduction in heat transfer in the air
heater.
Wet Flue Gas loss: Moisture that enters the
combustion chamber as part of the fuel causes a heat
loss, because it must be heated to its boiling point first,
then evaporation and then superheating before it
leaves the boiler along with flue gas. So lot of heat is
wasted in doing so.
25
Carbon in Ash Loss: This loss depends upon the
fineness of pulverised coal, excess air and combustion
condition. If the conditions are not monitored properly
the loss which should be around 1% may be as high as
4 to 5%.
Causes of high carbon in ash are:
Coarse grinding
Mal adjustment of flame
Unequal loading of different mills
Incorrect PA fan temperature.
Causes of Coarse grinding:
Mill in need of adjustment
Exhauster speed too high in relation relative to feed rate.
Weak fuel / air mixture i.e high PA
Separator (Classifier) speed too high 26
Radiation and Unaccounted Heat Losses: These are the heat losses as follows
1) Heat carried away in ash
2) Loss from boiler casing to the surrounding
3) Heat loss in bottom water seal
4) Loss of heat due to unburnt volatile matter
5) These loss account for around 1%.
Radiation loss depends upon effectiveness of the insulation all around the boiler casing
and feed water piping.
Problem associated with high ash contents in coal:
Effect of varying boiler load on efficiency:
Control of Boiler Blow Down:
Usually it is for a period of around 2 minutes in every shift and
increase in boiler blow down will reduce the Boiler eff.
Auxiliary Power Consumption: Running additional auxiliary only
when it is essential and that only when it is going to yield fruitful
result.
Using efficient type of control for regulation of fans and pumps
Optimization of air, fuel and water consumption
Better maintenance and house keeping.
27
Optimization of oil consumption:
PF boiler consumes oil under different operating
conditions. It makes little difference in heat consumption.
Too much dependence on oil for flame stabilization and lt
low loads should be only as necessary and not an easy
remedy. Cost of oil is far more than cost of coal so the
generation cost will also be high. Oil should be used
judiciously.
28
Performance monitoring of Pumps and Fans
The objective of observing the Performance of Fan and
Pumps is very vital. Both Fans and Pumps are similar
machines. Both have same like components. Even the
operating principle of two is also similar. We understand
the Bernoulli's theorem and also know that sum total of
energies of the fluid flowing through a confined passage
is constant. Usually there are three components of Total
pressure that is Pressure energy, kinetic energy and
potential energy. While the fluid is flowing through a pipe
line or the duct one is altered at the cost of other until
and unless energy is not added.
29
30
Pumps and Fans add energy to fluid with the help of a
motor and the rotating component that is impeller.
Which increases the kinetic energy which if then
converted to pressure at its own cost. These are known
as Centrifugal machines. There is another which is called
axial flow machines which only displaces the fluid at high
rate axially without converting to pressure energy.
We must understand the internals or the type to monitor
its behaviour and gauge the performance. We must
understand whether the energy input, after all it is
costing to us, how much of it is doing it job. So come
efficiency into picture. Every fan or a pump has a specific
point of operation where its efficiency is maximum. Do
we know that.
31
At this point the fan or the pump will deliver a known flow against a
specified head. How much energy the pump or the fan is drawing
from the motor should be know. If it is more than the specified one
that means pumps is not performing well or where I am operating the
pump is not correct.
One more point depending upon the demand or the load on the unit
the flow by the pump or the fan has to alter that is less or more than
the operating point at which the efficiency was maximum, by
throttling the discharge valve or the speed or the inlet damper or
varying the pitch of the vanes what ever we do the flow should in
the most efficient manner, one thing you must understand it is
always at the cost efficiency and so it is uneconomical. That is what
comes into picture. If I am operating the plant at less load than
rated load it is always inefficient and performance of the fan or the
pump will e considered to be poor. As said how do we do this is also
important. It is therefore very essential that before we proceed into
the job of calculating the performance and efficiency we must
understand the following. 32
In figure of pumping layout the pump
takes water from below its centre line
and deliver to some higher elevation.
Various pumping terminologies or the
terms have been mentioned. Let us
study them.
Suction Lift marked is known as Static
Suction lift. When Velocity head and
Suction friction head is added to static
Suction lift it is called Suction lift or the
total suction lift.
Suction Lift = Static Suction Lift +
Velocity Head + Frictional Head + Entry
loss etc.
hL = hSSL + hv2/2g + hf + hi
Or
hSSL = hL ( hv2/2g + hf + hi)
33
Here the water source is above the pump
centre line. This is known as Suction Head.
And Static Suction head S = Suction Head +
Velocity head + Frictional Head + other losses
it can be written like this:
S = hs + Hv2/2g + Hf + He
In both suction lift and suction head velocity of
flow is almost decided as around 4 to 5 m/s what
can be altered is the frictional head loss and entry
losses.
2L/2gd
hf is given by = 4fv
34
Hf can be reduced by
F is a constant and depends upon the type of flow and internal
condition od the suction piping. It should be as smooth as
possible.
Velocity of flow is almost fixed
Length of the suction pipe should be as short as possible
Diameter of the suction pipe should be as large as possible
35
Similarly Static Discharge head hd = hD (hV2/2g + H f d + h exit)
36
37
38
39
40
41
42
43
44
45
46
47
Affinity laws
The affinity laws for pumps/fans are used in hydraulics
and/or HVAC to express the relationship between variables
involved in pump or fan performance (such as head,
volumetric flow rate, shaft speed) and power. They apply to
pumps and fans in common. In these rotary implements,
the affinity laws apply both to centrifugal and axial flows.
P1 N1
------ = { ---- } 3
P2 N2
49
Law 2. With shaft speed (N) held constant:
Law 2a. Flow is proportional to the impeller diameter:
D1 N1
------ = -------
D2 N2
Law 2b. Pressure or Head is proportional to the square of the
impeller diameter:
D1 N1
------ = { ---- } 2
D2 N2
Law 2c. Power is proportional to the cube of impeller diameter:
D1 N1
------ = { ---- } 3
D2 N2
50
where
51
Three Phase
KW E I PF = 173
1000
52
COAL -COKE.
53
COAL GARDES.CIL
54
55
PERFROMANCE TESTING ..A TYPICAL SCHEDULE
56
PERFROMANCE TESTING ..A TYPICAL REPORT
57
BOILER PERFORMANCE. DIRECT METHOD
Basically Boiler efficiency can be tested by the following methods:
1) The Direct Method: Where the energy gain of the working fluid (water and steam)
is compared with the energy content of the boiler fuel.
2) The Indirect Method: Where the efficiency is the difference between the losses and
the energy input.
58
BOILER PERFORMANCE. DIRECT METHOD
59
BOILER PERFORMANCE. INDIRECT METHOD
60
BOILER PERFORMANCE. INDIRECT MATHOD
61
BOILER PERFORMANCE. INDIRECT MATHOD
62
BOILER PERFORMANCE. INDIRECT MATHOD
63
BOILER PERFORMANCE. INDIRECT MATHOD
64
BOILER PERFORMANCE. INDIRECT MATHOD
65
BOILER PERFORMANCE. INDIRECT MATHOD
66
BOILER PERFORMANCE. INDIRECT MATHOD
67
BOILER PERFORMANCE. INDIRECT MATHOD
68
BOILER PERFORMANCE. INDIRECT METHOD
69
BOILER PERFORMANCE. INDIRECT METHOD
70
BOILER PERFORMANCE. INDIRECT METHOD
71
BOILER PERFORMANCE. INDIRECT METHOD
72
BOILER PERFORMANCE. INDIRECT METHOD
73
BOILER PERFORMANCE. INDIRECT METHOD
74
BOILER PERFORMANCE. INDIRECT METHOD
75
BOILER PERFORMANCE. INDIRECT METHOD
76
BOILER PERFORMANCE. INDIRECT METHOD
77
BOILER PERFORMANCE. INDIRECT METHOD
78
BOILER PERFORMANCE. INDIRECT METHOD
79
BOILER PERFORMANCE. INDIRECT METHOD
80
BOILER PERFORMANCE. INDIRECT METHOD
81
BOILER PERFORMANCE. INDIRECT METHOD
82
BOILER PERFORMANCE. INDIRECT METHOD
83
Step 4: Estimate all heat losses
Step-1: Calculate the theoretical air requirement i. Percentage heat loss due to dry flue gas
= [(11.43 x C) + [{34.5 x (H2 O2/8)} + (4.32 x S)]/100 = m x Cp x (Tf Ta ) x 100
kg/kg of oil ----------------------------
GCV of fuel
= [(11.43 x 84) + [{34.5 x (12 1/8)} + (4.32 x 3)]/100 m = mass of CO2 + mass of SO2 + mass of N2 + mass of O2
kg/kg of oil 0.84 x 44 0.03x64 20.74x77
= 13.82 kg of air/kg of oil m = ----------- + ---------- + ----------- (0.07 x 32)
12 32 100
Step-2: Calculate the % excess air supplied (EA) m = 21.35 kg / kg of oil
21.35 x 0.23 x (220 27)
Excess air supplied (EA)
= ------------------------------- x 100
= (O2 x 100)/(21-O2) 10200
= (7 x 100)/(21-7) = 9.29%
= 50%
Step 3: Calculate actual mass of air supplied/ kg of A simpler method can also be used:Percentage heat loss due to dry flu
fuel (AAS) gas
m x Cp x (Tf Ta ) x 100
AAS/kg fuel = [1 + EA/100] x Theo. Air (AAS)
= ------------------------------
= [1 + 50/100] x 13.82 GCV of fuel
= 1.5 x 13.82 m (total mass of flue gas)
= 20.74 kg of air/kg of oil = mass of actual air supplied + mass of fuel supplied
ii. Heat loss due to evaporation of water formed due to H2 in =fuel
20.19 + 1 = 21.19
9 x H2 {584+0.45 (Tf Ta )} = 21.19 x 0.23 x (220-27)
------------------------------- x 100
= --------------------------------- 10200
GCV of fuel = 9.22%
where H2 = percentage of H2 in fuel
9 x 12 {584+0.45(220-27)}
= --------------------------------
10200
= 7.10%
iii. Heat loss due to moisture present in air
AAS x humidity x 0.45 x ((Tf Ta ) x 100
= ------------------------------------------------- 84
GCV of fuel
BOILER PERFORMANCE. BLOW DOWN
Boiler Blow Down
When water is boiled and steam is generated, any dissolved solids contained in the water
remain in the boiler. If more solids are put in with the feed water, they will concentrate and
may eventually reach a level where their solubility in the water is exceeded and they
deposit from the solution. Above a certain level of concentration, these solids encourage
foaming and cause carryover of water into the steam. The deposits also lead to scale
formation inside the boiler, resulting in localized overheating and finally causing boiler tube
failure.
It is therefore necessary to control the level of concentration of the solids. This is achieved
by the process of 'blowing down', where a certain volume of water is blown off and is
automatically replaced by feed water - thus maintaining the optimum level of total
dissolved solids (TDS) in the boiler water. Blow down is necessary to protect the surfaces of
the heat exchanger in the boiler. However, blow down can be a significant source of heat
loss, if improperly carried out.
85
BOILER PERFORMANCE. BLOW DOWN
Conductivity as indicator of boiler water quality
Since it is tedious and time consuming to measure total dissolved solids (TDS) in
boiler water system, conductivity measurement is used for monitoring the overall
TDS present in the boiler. A rise in conductivity indicates a rise in the
"contamination" of the boiler water.
Conventional methods for blowing down the boiler depend on two kinds of blow
down: intermittent and continuous
86
BOILER PERFORMANCE. BLOW DOWN
Intermittent blow down
The intermittent blown down is given by manually operating a valve fitted to discharge
pipe at the lowest point of boiler shell to reduce parameters (TDS or conductivity, pH,
Silica and Phosphates concentration) within prescribed limits so that steam quality is not
likely to be affected. In intermittent blow down, a large diameter line is opened for a
short period of time, the time being based on a thumb rule such as once in a shift for 2
minutes.
There is a steady and constant dispatch of small stream of concentrated boiler water,
and replacement by steady and constant inflow of feed water. This ensures constant TDS
and steam purity at given steam load. Once blow down valve is set for a given
conditions, there is no need for regular operator intervention.
Even though large quantities of heat are wasted, opportunity exists for recovering this
heat by blowing into a flash tank and generating flash steam. This flash steam can be
used for pre-heating boiler feed water or for any other. This type of blow down is
common in high-pressure boilers.
87
BOILER PERFORMANCE. BLOW DOWN
Blow down calculations
The quantity of blow down required to control boiler water solids concentration is calculated by
using the following formula:
If maximum permissible limit of TDS as in a package boiler is 3000 ppm, percentage make up water
is 10% and TDS in feed water is 300 ppm, then the percentage blow down is given as:
= 300 x 10 / 3000
=1%
If boiler evaporation rate is 3000 kg/hr then required blow down rate is:
= 3000 x 1 / 100
= 30 kg/hr
Benefits of blow down control
Good boiler blow down control can significantly reduce treatment and operational costs that include:
Lower pretreatment costs
Less make-up water consumption
Reduced maintenance downtime
Increased boiler life
Lower consumption of treatment chemicals
88
BOILER PERFORMANCE. a TYPICAL TEST FOR 500 MW
90
BOILER PERFORMANCE.
Effect of Operating Parameters on Boiler Losses
91
BOILER PERFORMANCE.INSTRUMENTS
Drum Penthouse
SH
Div. SH
Panel
. .
Nose
. Arch
.
Locations for HVT & HVS Sampling
93
BOILER PERFORMANCE.
Instruments Used
Dirty Pitot
Rotary Sampler
FG Sampling SystemProbes
Bubble Jar
Condenser
Desiccant jar
Vacuum Pump
Gas Analyzers
Datascan boxes
High Velocity Thermocouple
High Volume Sampler
94
BOILER PERFORMANCE.
FG
Expansion
Bellow
Test Ports
Economizer
HVS
APH
Sampling
Locations
APH
FG
95
BOILER PERFORMANCE.
FG Samples
from probes
Desiccant
Jar
Bubble Jar
Condenser
Datascan Gas
Boxes Analyser
s Vacuum Pump
98
Sampling Locations
99
Air Ingress Points Furnace Roof , Expansion joints, Air
heaters, Ducts, ESP Hoppers, Peep Holes, Manholes,
Furnace Bottom
Air-in-
leakage
Furnace
Outlet
Zirconia
O2 Probe
Expansion Joints
AH ESP
Seal
Lkg
100
Oxygen % at various locations in boiler
10
6
O2 %
0
Furn Outlet AH Inlet AH Outlet ID outlet
210 MW 210 MW 500 MW 210 MW
101
BOILER PERFORMANCE.
Air ingress from the nose arch, penthouse and boiler second pass
and quantification thereof
Difference between on line zirconia reading and the actual oxygen
in the flue gas duct as measured by the sampling grid
Difference between actual and 'on line' temperature
measurement of air heater air / gas outlet temperatures
Fouling and Slagging
High unburnt Carbon in flyash or bottomash
High air heater leakage - reduced by ALCS operation
Boiler operation at high excess air
103
FAN PERFORMANCE
104
FAN PERFORMANCE
105
FAN PERFORMANCE
Fan Curves
Manufacturer will provide a fan curve for each fan
The fan curves predict the pressure-flow rate performance of
each fan.
Choose a fan that gives you the volumetric flow rate you need
for your system pressure drop.
Choose a fan that has its peak efficiency at or near your
operating point.
Sometimes will provide data in a table rather than in a graph.
106
FAN PERFORMANCE
107
FAN PERFORMANCE
108
FAN PERFORMANCE
Fan Laws
Flow ? Speed Pressure ? (Speed)2 Power ? (Speed)3
Q1 N 1 2 3
SP1 N 1 kW 1 N 1
Q2 N 2
SP 2 N 2 kW 2 N 2
Varying the RPM by 10% Varying the RPM by 10% Varying the RPM by 10%
decreases or increases air decreases or increases the decreases or increases the
delivery by 10%. static pressure by 19%. power requirement by
27%.
Where Q flow, SP Static Pressure, kW Power and N speed (RPM)
109
FAN PERFORMANCE
Fan Laws
Law 1 relates to effect of changing size, speed, or density on volume
flow, pressure, and power level
Law 2 relates to effect of changing size, pressure, or density on volume
flow rate, speed, and power
Law 3 shows effect of changing size, volume flow, or density on speed,
pressure, and power
The laws only apply to aerodynamically similar fans at the same point of
rating on the performance curve.
110
FAN PERFORMANCE
111
FAN PERFORMANCE
Draught System Pressure Variation
Pressure drop calculation in air & gas path and its comparison
with design value.
Assessment of ID and FD fan power as a function of furnace
pressure.
Assessment of effective kinetic rate coefficient as a function of
furnace pressure.
Duct
FD Back ID
Duct
Duct APH Duct Furnace Duct APH ESP Chimney
Fan pass Fan
112
FAN PERFORMANCE
Pressure Variation
9 LTSH Inlet
-100
10 Economiser Inlet
-150
Airheater Inlet
11
-200
E.P. Inlet
12
-250 I.D. Fan Inlet
13
113
FAN PERFORMANCE
Static Pressure: The absolute pressure at a point minus the reference atmospheric
pressure.
Dynamic Pressure: The rise in static pressure which occurs when air moving with
specified velocity at a point is bought to rest without loss of mechanical energy. It is also
known as velocity pressure.
Total Pressure: The sum of static pressures and dynamic pressures at a point.
Fan Shaft Power: The mechanical power supplied to the fan shaft
Motor Input Power: The electrical power supplied to the terminals of an electric motor
drive.
114
FAN PERFORMANCE
General: The flow measurement plane shall be located in any suitable straight length,
(preferably on the inlet side of the fan) where the airflow conditions are substantially
axial, symmetrical and free from turbulence. Leakage of air from or into the air duct shall
be negligible between the flow measuring plane and the fan. Bends and obstructions in
an air duct can disturb the airflow for a considerable distance downstream, and should
be avoided for the purposes of the test.
115
FAN PERFORMANCE
Test length: That part of the duct in which the flow measurement plane is located,
is termed the test length and shall be straight, of uniform cross section.
It shall have a length equal to not less than twice the equivalent diameter of the
air duct (i.e. 2De).
For rectangular duct, equivalent diameter, De is given by 2 LW/(L+W) where L, W
is the length and width of the duct.
For circular ducts De is the same as diameter of the duct.
Inlet side of the fan: Where the test length is on the inlet side of the fan, its
downstream end shall be at a distance from the fan inlet equal to atleast 0.75De.
.
Outlet side of the fan: Where the test length is on the outlet side of the fan, the
upstream end of the test length shall be at a distance from the fan outlet of at
least 3De.
116
FAN PERFORMANCE
117
FAN PERFORMANCE
118
FAN PERFORMANCE
119
FAN PERFORMANCE
Measurement of Air Velocity on Site
Velocity shall be measured by either pitot tube or a rotating vane anemometer.
When in use, the pitot tube shall be connected by means of airtight tubes to a
pressure measuring instrument. The anemometer shall be calibrated before
the test.
120
FAN PERFORMANCE
121
FAN PERFORMANCE
122
FAN PERFORMANCE
123
FAN PERFORMANCE
124
FAN PERFORMANCE
125
FAN PERFORMANCE
126
FAN PERFORMANCE
127
AIRPRE HEATER PERFORMANCE
Operational Problem
High Gas Leaving Temperatures
129
AIRPRE HEATER PERFORMANCE
Higher Pressure Drop Across APH
1. Choking of heating elements
2. Higher flows
3. Eroded/damaged heating elements - obstructs flow path.
4. Improper Soot Blowing steam parameters and eroded
nozzles and steam pipes.
5. Low cold end average temperature
131
AIRPRE HEATER PERFORMANCE
1. Air-in-Leakage
2. Gas Side Efficiency
3. APH Effectiveness.
4. X - ratio
5. Flue gas temperature drop
6. Gas & Air side pressure drops.
132
AIRPRE HEATER PERFORMANCE
Air Heater Leakage (%)
Weight of air passing from air side to gas side to the Wt of Flue gas
passing.
Direct - Hot End / Cold End
(60% through radial seals + 30% through Circumferential bypass)
Air leakage occurring at hot end of the air heater affects its thermal
and hydraulic performance while cold end leakage increases fans
loading.
Leakage% = 17.1 %
134
CO2 measurement is preferred due to high absolute values
AIRPRE HEATER PERFORMANCE
135
AIRPRE HEATER PERFORMANCE
Tgas out (no leakage) = Temp at which the gas would have left the air
heater if there were no leakage
136
AIRPRE HEATER PERFORMANCE
Low Gas side efficiency- APH problems like Basket wear, Ash
plugging, High Lkg
Low gas side efficiency results in high Exit gas temp and Low Air
outlet temp
137
AIRPRE HEATER PERFORMANCE
X Ratio
Ratio of heat capacity of air passing through the air heater to the heat
capacity of flue gas passing through the air heater.
138
AIRPRE HEATER PERFORMANCE
X-Ratio - factors
moisture in coal, air infiltration, air & gas mass flow rates
leakage from the setting
specific heats of air & flue gas
LOW X-ratio leads to a higher than design gas outlet temperature &
can be used as an indication of excessive tempering air to the mills or
excessive boiler setting infiltration.
139
AIRPRE HEATER PERFORMANCE
Pressure drops across air heater
140
AIRPRE HEATER PERFORMANCE
AH Performance Monitoring
141
AIRPRE HEATER PERFORMANCE
PA Header Pressure
High pressure results in increased AH leakage,
higher ID fan loading, higher PA fan power
consumption, deteriorates PF fineness & can
increase mechanical erosion
Upstream ash evacuation
No. Of Mills In Service
Air ingress levels
Maintenance practices
Condition of heating elements, seals / seal setting,
sector plates / axial seal plates, diaphragm plates,
casing / enclosure, insulation.
142
MILL
PERFORMANCE
143
MILL PERFORMANCE
The Purpose of a Pulverizer:
.
145
MILL PERFORMANCE
146
MILL PERFORMANCE-HGI
147
MILL PERFORMANCE
NO LOAD RUN
CLEAN AIR FLOW TEST
DIRTY PITOT TUBE TEST
MILL FINENESS SAMPLING
TRENDING OF COAL PIPE METAL
TEMPERATURE
148
MILL PERFORMANCE
OBJECTIVE OF TESTING
150
MILL PERFORMANCE
151
MILL PERFORMNANCE S TYPE PITOT .
152
MILL PERFORMANCE
153
MILL PERFORMANCE
Acceptance range
154
MILL PERFORMANCE
155
MILL PERFORMANCE
156
MILL PERFORMANCE
Accurate weighing and sieving of the samples through 4 sieves is also important. Why
four sieves? Because, with the desired near zero on 50 mesh sieve, at least three points
are needed on the
Rosin-Rammler Chart to plot the fineness Results. Four sieves of 50, 100, 150 and 200
mesh are recommended for fineness sampling. 157
MILL PERFORMANCE
U.S. MESH INCHES MICRONS MILLIMETERS
What does mesh size mean? Figuring out mesh sizes is simple. All you do is count the
number of openings in one inch of screen .The number of openings is the mesh size. So a
4-mesh screen means there are four little squares across one linear inch of screen. A 100-
mesh screen has 100 openings, and so on. As the number describing the mesh size
increases, the size of the particles decreases.
158
MILL PERFORMANCE
160
MILL PERFORMANCE
Pulverizer Troubleshooting-Matrix
LACK OF CAPACITY OR HIGH MOISTURE
HIGH POWER LOW GCV
CONSUMPTION INCREASED RAW COAL
SIZE.
GRINDING TOO FINE
EXCESSIVE BED DEPTH
INSTRUMENT ERROR
161
MILL PERFORMANCE
Pulverizer Troubleshooting-Matrix
162
MILL PERFORMANCE
Pulverizer Troubleshooting-Matrix
COARSE GRIND CHANGE IN COAL
GRINDABILITY
HIGH MOISTURE
INCREASED THROUGH PUT.
CLASSIFIER SETTING
MILL WEAR.
163
MILL PERFORMANCE
Pulverizer Troubleshooting-Matrix
LOW COAL \AIR HIGH MOISTURE
TEMPERATURE LOW PA INLET TEMPERATURE
PASSING OF COLD AIR.
LOW A.H INLET
TEMPERATURE
NON AVAILABILITY OF SCAPH
164
MILL PERFORMANCE
Pulverizer Troubleshooting-Matrix
165
MILL PERFORMANCE
Pulverizer Troubleshooting-Matrix
166
Optimization of
Boiler total air
167
BOILER PERFORMANCE. AIR OPTIMISATION
Concept
Efficient operation of boiler depends on
optimisation of CO2 and O2
This involved elimination of source of air
ingress.
As different losses of boiler is affected by
variation of air, the optimum value is
determined by plotting the total loss and
thereby determining CO2 and O2.
168
BOILER PERFORMANCE. AIR OPTIMISATION
169
BOILER PERFORMANCE. AIR OPTIMISATION
Oxygen % at various locations in boiler
10
6
O2 %
0
Furn Outlet AH Inlet AH Outlet ID outlet
210 MW 210 MW 500 MW 210 MW
170
BOILER PERFORMANCE. AIR OPTIMISATION
Air Ingress Points Furnace Roof , Expansion
joints, Air heaters, Ducts, ESP Hoppers, Peep
Holes, Manholes, Furnace Bottom
Air-in-
leakage
Furnace
Outlet
Zirconia
O2 Probe
Expansion Joints
AH ESP
Seal
Lkg
171
BOILER PERFORMANCE. AIR OPTIMISATION
The basis of O2 or CO2 calculation should be the same either wet or dry.
172
BOILER PERFORMANCE. AIR OPTIMISATION
173
BOILER PERFORMANCE. AIR OPTIMISATION
174
BOILER PERFORMANCE. AIR OPTIMISATION
175
BOILER PERFORMANCE. AIR OPTIMISATION
176
MILL PERFORMANCE.FEILD TEST
Specific energy Consumption (Kwh./T of Coal)
SEC Comparision
Acceptable SEC
11.00
10.00
9.00
SEC
8.00
7.00
6.00
5.00
Mill A Mill B Mill C Mill D Mill E Mill F Mill G Mill H Mill J Mill K
Unit-3 7.91 7.63 8.82 7.93 8.05 7.44 7.34 7.52 6.90 7.05
Unit-4 6.29 7.79 6.45 7.54 7.59 7.32 6.21 7.06 7.07 7.25
Unit-5 10.53 7.43 6.48 7.90 7.81 7.78 7.33 7.28 8.15 7.20
Unit-6 10.3 8.8 7.1 6.6 7.0 6.8 7.7 7.6 9.0 10.0177
MILL PERFORMANCE.FEILD TEST
SEC(PG Test).
PG Test SEC
Unit-3 Unit-4 Unit-5 Unit-6
Mill A 7.8 7.5 7.7 7.8
Mill B 7.7 7.4 7.5 7.5
Mill C 8.0 7.6 7.5 7.6
Mill D 7.6 7.6 7.9 7.8
Mill E 7.9 7.5 7.8 7.8
Mill F 7.9 7.6 7.5 7.9
Mill G 7.7 7.7 7.8 7.6
Mill H 7.6 7.6 7.7 7.8
Mill J 7.9 7.8 7.6 7.5
Mill K 7.8 7.6 7.6 7.6
Standard Deviation 0.148 0.110 0.143 0.15
SD of Audit 0.532 0.560 1.071 1.348
178
MILL PERFORMANCE.FEILD TEST
Current (Amps)
Acceptable Amp
Current(Amps) Comparision.
140
135
130
125
SEC
120
115
110
105
100
Mill A Mill B Mill C Mill D Mill E Mill F Mill G Mill H Mill J Mill K
Unit-3 130 130.4 113 131 121 122.9 120 120 132.8 120
Unit-4 113 130.4 113 129 121 124 120 120 124 123.2
Unit-5 134 115 112 129 127 123.4 119 118.4 130.1 115.7
Unit-6 134.0 138.0 117.0 117.0 113.0 118.0 130.0 124.0 131.4 125.1
179
MILL PERFORMANCE.FEILD TEST
Classifier O/L temp
Clssifier O/L Temp.
85
83
81
79
Temp Degree C
77
75
73
71
69
67
65
Mill A Mill B Mill C Mill D Mill E Mill F Mill G Mill H Mill J Mill K
Unit-3 78 79 82.2 80.9 79.9 75.6 83.3 82.3 82.5 75.6
Unit-4 74.9 83 74.4 75 78.1 82 82 72 72.5 76.4
Unit-5 81.5 74 74 78.9 76.9 77.9 84 79 82.5 83
Unit-6 73.5 76 75 80 74.9 72.6 73.5 75.2 75.4 76.2
180
MILL PERFORMANCE.FEILD TEST
Coal Flow (T/hr)
Coal Flow T/hr
70
65
Coal Flow T/hr
60
55
50
45
40
Mill A Mill B Mill C Mill D Mill E Mill F Mill G Mill H Mill J Mill K
Unit-3 65 65 55 64.2 65 64.5 65.4 59.6 64.9 64
Unit-4 65 60.2 64 62.6 62.59 64.5 62.8 59.6 62.4 60.3
Unit-5 50.8 63.13 64.5 63.4 64.3 63.39 62.5 63.2 62.8 63.5
181
Unit-6 50 61.7 63 65.3 63.4 64.3 62.9 64 60 45.74
MILL PERFORMANCE.FEILD TEST
Mill Loading
Mill Loading (Percent)
105.00
100.00
95.00
90.00
Percent
85.00
80.00
75.00
70.00
65.00
60.00
Mill A Mill B Mill C Mill D Mill E Mill F Mill G Mill H Mill J Mill K
Unit-3 97.90 94.48 92.38 96.95 99.62 91.43 91.43 85.33 85.33 85.90
Unit-4 77.90 89.33 78.67 89.90 90.48 89.90 74.29 80.19 84.00 83.24
Unit-5 101.90 89.33 79.62 95.43 95.62 93.90 87.24 87.62 97.52 87.05
182
Unit-6 98.04 103.24 85.14 81.52 84.57 82.86 92.76 92.76 102.48 87.05
MILL PERFORMANCE.FEILD TEST
P-Air/Coal ratio
183
MILL PERFORMANCE.FEILD TEST
Mill Fineness.
Mill Finness
77
% Coal through -200
76
75
74
73
72
71
70
A B C D E F G H J K
Unit-3 70 74 73 75 75 71 74 74 74 71
Unit-4 73 71 72 74 73 74 72 71 75 72
Unit-5 74 75 73 71 72 74 74 74 72 74
Unit-6 74 76 74 74 74 72 74 74 71 71
69
67
65
Temp Degree C
63
61
59
57
55
MILL A MILL B MILL C MILL D MILL E MILL F MILL G MILL H MILL J MILL K
Cr-1 63.5 65.2 62.3 63.5 66 66 62 59.8 62.5 64
Cr-2 64 66.5 63 63.5 65.2 65 65 59.8 63 64
Cr-3 65 64.9 63.2 64.5 63.5 65 65 60.2 63.2 65
Cr-4 65 65 63 62.9 64.8 65.3 64 60.2 64.2 65
185
MILL PERFORMANCE.FEILD TEST
Unit-4 Coal pipe Temp (Degree C)
65
Temp Degree C
60
55
50
69
67
65
Temp Degree C
63
61
59
57
55
MILL A MILL B MILL C MILL D MILL E MILL F MILL G MILL H MILL J MILL K
Cr-1 65 67.2 63 60.2 62 62 63 64 63.2 64
Cr-2 66 66.2 63 65.2 62.4 64 64 64 63 64
Cr-3 66 68 65 64.2 63 66 63 60 62.5 64
Cr-4 68 67.4 66 61.7 62.2 63.4 64 64 64.2 65
187
MILL PERFORMANCE.FEILD TEST
Unit-6 Coal pipe Temp (Degree C)
65
60
Temp Degree C
55
50
45
100
98
% of Cpacity
96
94
92
90
88
Mill A Mill B Mill C Mill D Mill E Mill F Mill G Mill H Mill J Mill K
Unit-3 100 94.8 96.1 93.5 93.5 98.7 94.8 94.8 94.8 98.7
Unit-4 96.1 98.7 97.4 94.8 96.1 94.8 97.4 98.7 93.5 97.4
Unit-5 94.8 93.5 96.1 98.7 97.4 94.8 94.8 94.8 93.5 97.4
Unit-6 94.8 92.2 94.8 94.8 94.8 97.4 94.8 94.8 98.7 98.7
189
MILL PERFORMANCE.FEILD TEST
Corrected Mill Capacity.
U-3
Moisture HGI FINENESS C1 C2 C3 CF CAP
Design 15 55 70
PG TEST 0.973 1.05 0.95 0.971 63.57
Mill A 19 52 70 0.953 0.97 1 0.924 60.55
Mill B 19 52 74 0.953 0.97 0.948 0.876 57.40
Mill C 19 52 73 0.953 0.97 0.961 0.888 58.19
Mill D 17 52 75 0.976 0.97 0.935 0.885 57.98
Mill E 17 52 75 0.976 0.97 0.935 0.885 57.98
Mill F 17 52 71 0.976 0.97 0.987 0.934 61.20
Mill G 16 52 74 0.984 0.97 0.948 0.905 59.27
Mill H 16 52 74 0.984 0.97 0.948 0.905 59.27
Mill J 16 52 74 0.984 0.97 0.948 0.905 59.27
Mill K 17 52 71 0.976 0.97 0.987 0.934 61.20
Where Correction factor
190
For moisture-C1, For HGI-C2, For fineness-C3, C=C1*C2*C3
MILL PERFORMANCE.FEILD TEST
Corrected Mill Capacity.
U-6
Moisture HGI FINENESS C1 C2 C3 CF CAP
Design 15 55 70
PG TEST 0.973 1.05 0.95 0.971 63.57
Mill A 17 52 74 0.976 0.97 0.948 0.897 58.79
Mill B 17 52 76 0.976 0.97 0.922 0.873 57.17
Mill C 15 52 74 1 0.97 0.948 0.920 60.23
Mill D 17 52 74 0.976 0.97 0.948 0.897 58.79
Mill E 17 52 74 0.976 0.97 0.948 0.897 58.79
Mill F 17 52 72 0.976 0.97 0.974 0.922 60.40
Mill G 17 52 74 0.976 0.97 0.948 0.897 58.79
Mill H 17 52 74 0.976 0.97 0.948 0.897 58.79
Mill J 17 52 71 0.976 0.97 0.987 0.934 61.20
Mill K 17 52 71 0.976 0.97 0.987 0.934 61.20
191
MILL PERFORMANCE.FEILD TEST
Velocity Profile Mill-3A
24.0 MILL 3A
22.0
20.0 Cr-1
Velocity of Pulv. Coal in Pipes
Cr-2
18.0 Cr-3
Cr-4
16.0
m/Sec.
Poly. (Cr-1)
Poly. (Cr-2)
14.0
Poly. (Cr-3)
Poly. (Cr-4)
12.0
10.0
0 4 8 12
22.0 MILL 3K
Cr-1
20.0
Cr-2
Velocity of Pulv. Coal in Pipes
18.0
Cr-3
16.0 Cr-4
m/Sec.
Poly. (Cr-1)
14.0
Poly. (Cr-2)
12.0
Poly. (Cr-3)
Cr-3
18.0
Cr-4
16.0
m/Sec.
Poly. (Cr-1)
14.0
Poly. (Cr-2)
Cr-4 DP and Velocity Zero
12.0
& Coal Pipe Temp 41.6 Degree C Poly. (Cr-3)
against Other Pipes 69 Degree C
10.0
Poly. (Cr-4)
0 4 8 12
PAF-MW
1.6
1.4
1.2
Power(MW)
1
0.8
0.6
0.4
0.2
0
Unit-3 Unit-4 Unit-5 Unit-6
PAF-A 1.263 1.155 1.223 1.37
PAF-B 1.209 1.167 1.204 1.137
PAF-A(PAB) 1.08 1.07 1.09 1.1
PAF-B(PAB) 1.09 1.09 1.1 1.08
195
MILL PERFORMANCE.FEILD TEST
196
MIL OPTIMIZATION
MILL PERFORMANCE.FEILD TEST
197
Mill Capacity Correction Curve
Mill Capacity Vs Grindability Index
HGI limit
198
Mill Capacity Correction Curve
Mill Capacity Vs Fineness
Fineness limit
199
MILL OPTIMIZATION
Mill Capacity Correction Curve
Mill Capacity Vs Moisture
200
Pragayan MILL OPTIMIZATION
Power consumption per unit coal transported
Actual for 2009-10 vs PG test St-II
MILL Coal Flow Current Coal Flow CURRENT Current/T/H Current/T/H KW/T/H KW/T/H
10.00
9.00
KW/hr/Ton coal
8.00
actual
7.00
desired
6.00
5.00
4.00
1 3 5 7 9 11 13 15 17 19 201
THANK YOU
202