SCHEDULING

PT. ARGHA KARYA PRIMA INDUSTRY, TBK


PT Argha Karya Prima Industry Tbk,
also known as Argha, was established
on 7 March 1980, and is the pioneer in
Indonesias flexible packaging industry.

The Companys main products are the


packing films BOPP (Biaxially Oriented
Polypropylene) and BOPET (Biaxially
Oriented Polyethylene Terepthalate) or
Polyester, each marketed under the
trademarks ARLENE and ARETA.
MEMBER OF THE GROUP

Dimas Cahya Anugrah 1201154212


Fauzan Rahmatullah 1201154168
Firjatullah Nastari 1201154425
Patricia Amalia 1201154322
Rakatama 1201154120
BACKGROUND

Most companies complete jobs simultaneously, therefore need to combine


several work schedules Merger
This merging process is called scheduling and the result is simply called the
schedule (schedule) or production schedule (production schedule) as a whole.
One of the keys to success in improving efficiency within an operating unit is the ability to
schedule effectively.
PRODUCTION PROCESS
STUDY CASE

PT Argha Karya Prima Industry, Tbk is a company that produces flexible packaging company. The company wants
to design an efficient and optimal machine scheduling for the production of flexible packaging. With the
following data :

Job Job 1 Job 2 Job 3 Job 4 Job 5


M1 15 20 15 15 20
M2 35 10 25 20 20
M3 10 30 20 25 25
METHOD USE

1. Production Scheduling
The purpose of the scheduling activity as follows:
1) Increase the use of resources, or reduce the time delay (delay)
2) Reduced inventory of intermediate goods
3) Reduced the delay on the job that has a time limit of completion
4) Assist decision-making regarding plant capacity planning

2. Flow Shop Scheduling

3. Johnson's algorithm
IMPLEMENTATION THEORY
The Data of Plastic Production
Job Job 1 Job 2 Job 3 Job 4 Job 5
M1 15 20 15 15 20
M2 35 10 25 20 20
M3 10 30 20 25 25

M1 = M1+M2, M2=M2+M3
Job Job 1 Job 2 Job 3 Job 4 Job 5
M1 50 30 40 45 40
M2 45 40 45 45 45

J2 J3 J5 J4 J5

20 30 35 55 70 85
110 145 155
M1 J2 J3 J5 J4 J1
M2 J2 J3 J5 J4 J1
M3 J2 J3 J5 J4 J1

Make Span = 155


Conclusion
Based on previous discussion, then the conclusion to be drawn as follows:

1) Scheduling production machines at pt argha method using cds, more precisely using the
johnson algorithm.Scheduling a production machine with cds in pt argha method generates a single
iteration. The first iteration yields value makespan of 155 hours of work with the sequence m1, m2,
m3.

2) Scheduling production machines using the CDS on PT Argha generate optimal schedules for
production.
Suggestion

Since the company are the type of company that tend to only produce according to demand
at that period, it would be better if they can calculated the production machine schedule to
know what time in each machines have, to make it more efficient in use.