Documente Academic
Documente Profesional
Documente Cultură
June 8, 2015
Agenda: What led to this point?
Project Background
Latest Findings
Risk Management
Alternate Routes
Next Steps
2
PROJECT BACKGROUND
Goals, design process, preliminary work
3
Project Goals: Trust & Transparency
Environmental stewardship
4
Project history to date
Relocate to former Luke Wood Park and Luke Wood Park and
high school parking lot inverted siphon under microtunnel under
Hudson Bayou Bridge Hudson Bayou Bridge
5
Project Status
U.S. 41
2011 2012
Construction Work stops due to
begins microtunnel issues
6
New Successor Engineer of Record
8
Hudson Bayou Crossing Phases
Phase II Scope of Work
Finalize microtunnel design (-16.5 feet)
Redesign Lift Station 87
9
Current Design Route
U.S. 41
Microtunnel Microtunnel
receiving pit jacking pit
Current Alternate
alignment alignment
Benefits
Maintenance of Traffic
Microtunnel Access to Businesses
jacking pit
Less US 41 Impacts
Hudson Bayou
Osprey Ave.
10
Hudson Bayou Crossing
12
Comprehensive Geotechnical Review
0 0 0 0
0 0 0
0 0
0 0
0 0 0 00 0
0 0 0
0 0
0 0
0 0 0 0
0
Original Original
8.75' 36" pipe 8.0' 36" pipe
Proposed Proposed
36" microtunnel 36" microtunnel
8'
Original pipe
Top of pipe
elevation: -8.5'
Proposed
microtunnel
Top of pipe
elevation: -16.5'
15
RISK MANAGEMENT
Designs, data and assessments
16
Risk Assessment of Designs
17
Risk Register and Criteria
IMPACT
Low Medium High Probability
1: 0 20%
2: 20 40%
High
3: 40 60%
4: 60 80%
PROBABILITY
5: 80 100%
Medium
Impact
1: < $100 K
2: $100 K $250 K
3: $250K $500K
Low
4: $500 K $1M
5: > $1M
18
What is a Risk Register?
19
Analysis of microtunneling
High jacking force i.e. stuck machine
Environmental impact to Hudson Bayou
Mixed face conditions hard soils on part of machine, soft on another
Unexpected geotechnical conditions
Line and grade deviations outside of tolerances
Pipe breaking
Differing Site Conditions claims
Damage to the bridge
20
Risk Example: High Jacking Force
Relative Risk
score (total)
22
Additional factors considered
Bathymetric Surveys
Nettles (2013) 6-8 feet
Forensic/Hyatt (2014) 7 feet
23
ALTERNATE ROUTES
Methods, plans and other considerations
24
Open Cut vs. Microtunneling
Evaluate options to re-use existing wetwell
Open Cut Microtunneling
25
Alternate Routes: Control Elevations
U.S. 41
Top of
Influent MH Wetwell
Foundation
Invert Invert
Material
(-13.08) (-13.52)
(-9.0)
Hudson Bayou
Osprey Ave.
26
Regulatory Considerations
Subaqueous
Crossing
Regulations
Florida
Department of
Environmental
Protection (FDEP)
3 Feet Cover
U.S. Army Corps
of Engineers
(USACE)
6 Feet Cover
Top of Pipe
El. -9.00
Open cut
27
Alternate Route 1
1903 Lincoln Drive
U.S. 41
36"
Disrupts condos
Permits needed
New easement
Osprey Ave.
Disrupts home
0 Manhole 30"
28
Alternate Route 2
1821 Lincoln Drive
U.S. 41
36"
Disrupts condos
Permits needed
New easement
29
Alternate Route 3
East of Bridge
Disrupts park
U.S. 41
36"
Permits needed
Disrupts home
Hudson Bayou
New easement
30
Open Cut Considerations
Easements and land acquisition required
Regulatory permits
- FDEP/Sarasota County
- Sovereign Submerged Lands
- Environmental Resource Permit
- FDEP/ACOE Variances
Environmental
Documented Lead Contamination (2001 Boyle Report)
Geotechnical Investigations
Borings/Bathymetric
Schedule
31
Operational Impacts
Period submergence of sewer system
- Reduced conveyance capacity
- More frequent pipeline cleaning
- Increased odor potential in neighborhood
32
Normal Operating Conditions
Odor
Open Cut Control
Odors
Elevation -13.5 ft.
Overflow hazard
Gravity Sewer
Wetwell
33
Surcharge Conditions
Existing Wetwell Design
-TBD ft.
Odors
Elevation -13.5 ft.
Overflow hazard
Gravity Sewer
Manhole
Existing Wetwell
34
Upgrades will still be required
Stand-by Pump
Reliability required
35
Planning level comparable costs
Microtunnel Open Cut
current est.
36 Inch (Phase 1) $11.0 M $6.5 M
Open Cut notes: Hudson Bayou crossing assumes variance from state and federal regulation requirements; Land 36
Acquisition & Legal estimated based on city input; Environmental from 2001 Hudson Bayou Stormwater Study
Analysis of project costs
Previous Bid Previous Bid Current Difference
January 2011 indexed to 2015 estimate
39
NEXT STEPS
Resolving design issues, communicating challenges
40
Sequencing of
Construction Additional
Advantages
U.S. 41
Risk Management
Minimize Disruption to
Existing Utilities
Cost Controls
Hudson Bayou
Maintenance of Traffic
41
Construction Plan
Three
Phases Phase 1
36 inch pipe
Phase 2
LS 87 construction
Phase 3
Demolition of
24 inch pipe
Lift Station 7
and park
restoration
Lift Station 7
42
Construction Challenges
Limited site access
Construction zone restrictions
Minimize impacts to Luke Wood Park
Maintenance of traffic
Minimize service disruptions
43
Jacking shaft
Microtunneling LS site
driveway
work zone
Work Zone
U.S. 41
Receiving shaft
Construction
work zone
support
work zone
Jacking shaft
work zone
Hudson Bayou
44
Microtunnel Work Zone (Osprey)
MICROTUNNEL
ALIGNMENT
MICROTUNNEL
HUDSON
BAYOU JACKING SHAFT
WORK ZONE
45
Microtunneling Work Zone (LS 87)
JACKING SHAFT
EQUIPMENT
PIPE
STORAGE
AREA
LS SITE
DRIVEWAY
OFFICE
TRAILER
MICROTUNNEL
ALIGNMENT
46
Building Work Zone
APPROXIMATE
EXCAVATION
LIMITS
APPROVED
SITE PLAN
47
Scheduling and Timeframes
Estimates subject to final engineering decisions
Q Q Q Q Q Q Q Q Q Q Q Q
1/2 3/4 1/2 3/4 1/2 3/4 1/2 3/4 1/2 3/4 1/2 3/4
Bid Phase Start Finish
48
Project Goals
Environmental stewardship
- Improve service and system reliability
- Storm protection (Category 3 hurricane)
- Offset potable water demands with reclaimed water
Utility City
Design Team Administrative
Department Commission
conclusion acceptance
support direction
50
City Commission Direction
Actions to move the project forward
51
Discussion
Lift Station 87 Funding Options
53
Option 1
Cash while maintaining CIP funding level
54
Option 2
Bond debt while maintaining CIP funding level
55
Option 3
Bond debt while maintaining CIP funding level
56
Staff Recommendation
Option 3
Bond debt while maintaining CIP funding level