Documente Academic
Documente Profesional
Documente Cultură
PAM form clause 23.8: 24 related events, which entitles the contractor to EOT;
E.g.;
Force Majeure
Bad Weather
Delay by Client in handing over site
Re-nomination of NSCs
Breach of Contract by the Client
War Damages
Etc.
Caused by Clients and Neutral Events
Delays by Contractor
Insufficient Manpower and Machineries
Not having materials when needed
Poor site management
Failing to pay Workers
Contractual Effects
No Entitlement to EOT
No Reimbursement for Loss and Expenses
Client may Levy/Impose Liquidated Damages
Client may terminate employment of Contractor
Delays by Client
Not Issuing AI on time
Delay in giving site possession
AI for Discrepancies, Variations, Suspension of Works
Re-nomination of NSCs
Delay by Clients direct Contractor
Delay/ Failure to supply materials
Opening for inspection and testing
Prevention or Breach by the Client
Delay in giving site entry & exit
Executing works with insufficient provisional quantities
Contractual Effects
Contractor can claim for;
EOT
Loss and Expense
Client unable to Levy/impose for Liquidated Damages
Contractor may Terminate his Employment
Delays by Neutral Events
Force Majeure (23.8a)
Harsh weather (23.8b)
Loss and Damages caused by Fire etc. (23.8c)
Civil commotion (23.8d)
War damages (23.8n)
Changes in laws (23.8p)
Delays/Failure to by statutory bodies to carry out duties (23.8q)
Suspension of work by Statutory bodies. (23.8w)
Contractual Effects
Contractors can claim for EOT
But not Loss/Damages
Client unable to Levy Liquidated Damages
Both parties are to share the burden of delay.
Procedure For Extension Of Time
According to PAM Form Contract, there are 2 steps of procedure:-
(1) In Clause 23.1(a):
Contractor are required to provide a written notice to the Architect of his
intention to claim for extension of time within 28 days from commencement of
relevant event. The written application is a condition precedent to any Extension Of
Time.
It is important to include the content above to ensure that Architect to make reasonable and fair
assessment of delays.
Whether To Claim For EOT?
- According to PAM Form Contract, Clause 23.1, contractor may apply
for EOT.
- Up to the decision of contractor.
- If the contractors opinion that:-
(i) The completion of works is actually delayed.
(ii) The completion will be delayed.
(iii) The cause of delay is caused by the relevant events which stated
in Clause 23.8.
Failure To Submit Claim Application
According to Clause 23.1(b), contractor are to submit the final claim within
28 days of the end of cause of delay.
However, if the contractor fails to submit within the time frame or within any
extended date, it is deemed that:-
(i) The contractor has assessed the cause and decide that the completion
date will not be delayed.
(ii) The contractor have waived his right to any EOT.
Application to;
Be in written form
State the Cause of Delays
State the effects on the work programs and progress
State the number of days delayed
State the steps taken to accelerate
Submit the rescheduled work programs
Include all supporting documents
State the number of EOT required.
Question 2:
Q2.
What are the purpose of an extension of time clause in most standard
contract and its implications? What is the implications of a Certificate of
Non-Completion? What is the difference between general damages and
liquidated damages?
Answer
(i)If there is a delay, the completion date can be extended; Employer can now set a new
completion date; It preserves the employers contractual rights should he cause works
Liquidated damages are agreed amount of damages that are likely to be suffered in the
event of a
breach of contract while general damages are to be assessed and could be for any amount.
Question 3:
The Contractor can claim EOT, as for Loss and Expense shall be the Loss
and Expense that can be claim which cause by the Employer.
Question 4:
In contrast to the delays in PAM form, what are the types of Delays
stated in the JKR form?
Answer
Force Majeure; JKR 43.1(a)
Exceptionally Inclement Weather JKR 43.1(b)
Suspension of Works by SO JKR 43.1(c)
Disputes with Neighboring owners JKR 43.1(d)
SOs instructions issued under clause 5 JKR 43.1(e)
Delay/Failure to Issue Instructions JKR 43.1(f)
Delay in giving site possession JKR 43.1(g)
Delays on part of artists, tradesmen JKR 43.1(h)
Inability to secure goods, materials & services JKR 43.1(i)
Delays on part of NSCs JKR 43.1(j)
Question 5:
Within how many days the contractor are required to submit his final
application claim for extension of time along with all supported
documents?
Answer
If the Contractor planned to finish its work before the completion date, but
events where the Employer was held responsible for prevented the early
completion of the project, may the contractor recover delay damages from
the owner even if it finishes the project by the date specified in the contract?
May the contractor recover delay damages from the
owner even if it finishes the project by the date
specified in the contract?
In Grow Construction Co. v. State, 391 N.Y.S.2d 726 (N.Y. A.D. 1977), the
contractor was delayed by state interference. The contractor sued the
state of New York for delay damages despite the fact that it was able to
finish the work by the date specified in the contract. The state of New
York argued that the contractor could not recover delay damages
because the job was completed on time. The court rejected the states
argument, reasoning that the contractor had a right to perform its work
free from interference from the state, and to finish early if possible.
May the contractor recover delay damages from the
owner even if it finishes the project by the date
specified in the contract?
Other courts have adopted similar reasoning. See Sun Shipbuilding &
Dry Dock Co. v. U. S. Lines, Inc., 439 F. Supp. 671 (E.D. Pa. 1977). Courts
that allow contractors to recover delay damages despite timely or early
completion, however, require the contractor to prove that early
completion would have occurred but for the owners delay.
Additionally, notice to the owner of the contractors intent to complete
the work ahead of scheduled is often required. Where a CPM schedule
is initially utilized to establish an early completion date and it is logically
consistent, the schedule is strong evidence of a reasonable intent to
complete early.
May the contractor recover delay damages from the
owner even if it finishes the project by the date
specified in the contract?
Yes, completing the project by the date specified in the contract does
not necessarily prevent the contractor from recovering delay damages
so long as the contractor could have reasonably finished by an earlier
date. (United State Law)
No, because no actual loss cause by Employer, so they could not claim
for delay damages. (UK Law)