ISSUE OF PTWC

(FOR NONOPERATIONAL WORKS IN MARAFIQ)

1
ISSUE OF PTWC

Sr Non operational Works API & APC APR Overall


# Responsibility
for Safety

1 Maintenance works of existing facility plant systems / Maintenance Department/


equipment Assigned Contractor

CAPEX jobs inside Marafiq facility - for up-gradation


2 or modification or tie–in jobs of existing system
Operations Marafiq Operation
CAPEX jobs (inside facility - expansion or up- Departments Dept
3 gradation of existing plant systems - Entry through Assigned Contractor
common gate )

CAPEX jobs inside (isolated by a fence) or outside


4 Marafiq facility for construction of new system /
building / infrastructure

CAPEX jobs (isolated area / outside Marafiq facility Safety section Main and sub contractors Marafiq Project
5a – separate gate ) Department
Case 1: No tie-in activity

5b CAPEX jobs (isolated area / outside Marafiq facility Operations Main and sub contractors Marafiq Operation
– separate gate ) Departments Dept
Case 2: For Tie-in job, the Project coordinating
Engineer shall guide the contractor to obtain
PTWC from operations department

2
RISK ASSESSMENT
Sr Non Operational Works Preparation Review Approval

Marafiq Maintenance Marafiq


1 Maintenance works of existing Department / Maintenance Marafiq Safety Marafiq Operations
facility plant systems / Contractor Engineer
equipment

CAPEX jobs inside Marafiq


2 facility - for up-gradation or Contractor Marafiq Projects Marafiq Safety Marafiq Operations
modification or tie–in jobs of
existing system

CAPEX jobs (inside facility -


3 expansion or up-gradation of Contractor Marafiq Projects Marafiq Safety Marafiq Operations
existing plant systems - Entry
through common gate )

CAPEX jobs inside (isolated by Marafiq Safety


4 a fence) or outside Marafiq
facility for construction of new Contractor PMC Marafiq Projects
system / building /
infrastructure

CAPEX jobs (isolated area / Marafiq Safety


5 outside Marafiq facility – Contractor PMC Marafiq Projects
separate gate )
PTW AUTHORIZATION COMMITTEE
(For Jubail)
Present Chairman - Mr. Fahad A. Shammari- Maintenance Manager
Committee Members – 1) Mr. Eleuterio Lulo - Operation Engineer
2) Mr. S. P. Kamat - Safety Engineer

Required 1. PTW Chairman - Change


Development 2. More members in Committee –preferably from
I ) Maintenance
ii ) Technical Services Department
iii) Projects – Engineering
iv) Operations