Sunteți pe pagina 1din 38

Project Management

Learning Objectives
 Discuss the behavioral aspects of projects in
terms of project personnel and the project
manager.
 Discuss the nature and importance of a work
breakdown structure in project management.
 Give a general description of PERT/CPM
techniques.
 Construct simple network diagrams.

3/3/2018 2
Learning Objectives
 List the kinds of information that a PERT or
CPM analysis can provide.
 Analyze networks with deterministic times.
 Analyze networks with probabilistic times.
 Describe activity “crashing” and solve typical
problems.

3/3/2018 3
Project
 Unique, one-time operational activity or effort
 Examples
– constructing houses, factories, shopping malls, athletic
stadiums or arenas
– developing military weapons systems, aircrafts, new ships
– launching satellite systems
– constructing oil pipelines
– developing and implementing new computer systems
– planning concert, football games, or basketball
tournaments
– introducing new products into market

3/3/2018 4
Project Management
 Project management is the application of
knowledge, skills and techniques to execute
projects effectively and efficiently.
 Project management processes fall into five
groups:
– Initiating
– Planning
– Executing
– Monitoring and Controlling
– Closing

3/3/2018 5
Project Management
 How is it different?
– Limited time frame
– Narrow focus, specific objectives
– Less bureaucratic
 Why is it used?
– Special needs
– Pressures for new or improves products or
services

3/3/2018 6
Project Management
 What are the Key Metrics
– Time
– Cost
– Performance objectives
 What are the Key Success Factors?
– Top-down commitment
– Having a capable project manager
– Having time to plan
– Careful tracking and control
– Good communications

3/3/2018 7
Project Management
 What are the Major Administrative Issues?
– Executive responsibilities
• Project selection
• Project manager selection
• Organizational structure
– Organizational alternatives
• Manage within functional unit
• Assign a coordinator
• Use a matrix organization with a project leader

3/3/2018 8
Project Management
 What are the tools?
– Work breakdown structure
– Network diagram
– Gantt charts
– Risk management

3/3/2018 9
Key Decisions
 Deciding which projects to implement
 Selecting a project manager
 Selecting a project team
 Planning and designing the project
 Managing and controlling project resources
 Deciding if and when a project should be
terminated

3/3/2018 10
Project Life Cycle
 Definition
 Planning
 Execution
 Termination

3/3/2018 11
Work Breakdown Structure

Project X

Level 1

Level 2

Level 3

Level 4

3/3/2018 12
Gantt Chart
Gantt Chart MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

Locate new facilities

Interview staff

Hire and train staff

Select and order


furniture

Remodel and install


phones

Move in/startup

3/3/2018 13
PERT and CPM
 PERT: Program Evaluation and
Review Technique
 CPM: Critical Path Method

3/3/2018 14
PERT and CPM
 Graphically displays project activities
 Estimates how long the project will take
 Indicates most critical activities
 Show where delays will not affect project

3/3/2018 15
The Network Diagram
 Network (precedence) diagram – diagram of
project activities that shows sequential
relationships by the use of arrows and nodes.
 Activity-on-arrow (AOA) – a network diagram
convention in which arrows designate activities.
 Activity-on-node (AON) – a network diagram
convention in which nodes designate activities.
 Activities – steps in the project that consume
resources and/or time.
 Events – the starting and finishing of activities,
designated by nodes in the AOA convention
3/3/2018 16
The Network Diagram
 Path
– Sequence of activities that leads from the starting node to
the finishing node
 Critical path
– The longest path; determines expected project duration
 Critical activities
– Activities on the critical path
 Slack
– Allowable slippage for path; the difference the length of
path and the length of critical path

3/3/2018 17
Project Network – Activity on Arrow

Order
furniture 4
Furniture
Locate 2 setup
facilities
Remodel
1 5 6
Move in

Interview
Hire and
train
3

3/3/2018 18
Project Network – Activity on Node
Order
furniture
Locate Furniture
2 setup
facilities

1 6
Move in
Remodel

S 5 7

Hire and
Interview
train

3 4

3/3/2018 19
Network Conventions

a
b
c a

c
b

a c
a c

b Dummy
activity
b d

3/3/2018 20
Time Estimates
 Deterministic
– Time estimates that are fairly certain
 Probabilistic
– Estimates of times that allow for variation

3/3/2018 21
Example
6 weeks
4
3 weeks
8 weeks 2

11 weeks Move in
1 5 6
1 week

4 weeks
9 weeks

3/3/2018 22
Example - Solution

Critical Path

Path Length Slack


(weeks)
1-2-3-4-5-6 18 2
1-2-5-6 20 0
1-3-5-6 14 6

3/3/2018 23
Computing Algorithm
 Network activities
– ES: early start
– EF: early finish
– LS: late start
– LF: late finish
 Used to determine
– Expected project duration
– Slack time
– Critical path

3/3/2018 24
Probabilistic Time Estimates
 Optimistic time
– Time required under optimal conditions
 Pessimistic time
– Time required under worst conditions
 Most likely time
– Most probable length of time that will be required

3/3/2018 25
Probabilistic Estimates

to tm te tp

Activity Optimistic Most likely Pessimistic


start time time (mode) time

3/3/2018 26
Expected Time

te = t o + 4t m +t p
6
te = expected time
to = optimistic time
tm = most likely time
tp = pessimistic time

3/3/2018 27
Variance

2 (t
= p o– t ) 2

36

2 = variance
to = optimistic time
tp = pessimistic time

3/3/2018 28
Example
Optimistic Most likely Pessimistic
time time time

2-4-6
b

3-4-5 3-5-7 5-7-9


d e f

4-6-8
h
3/3/2018 29
Example – Time Estimates

Tabc = 10.0
Tdef = 16.0 4.00
Tghi = 13.50 b

4.00 5.0 7.0


d e f

6.0
h

3/3/2018 30
Time-cost Trade-offs: Crashing
 Crash – shortening activity duration
 Procedure for crashing
– Crash the project one period at a time
– Only an activity on the critical path
– Crash the least expensive activity
– Multiple critical paths: find the sum of crashing
the least expensive activity on each critical path

3/3/2018 31
Time-cost Trade-offs: Crashing

Total
cost

Expected indirect costs

Shorten

Cumulative CRASH
cost of crashing
Shorten

Optimum
3/3/2018 32
Advantages of PERT
 Forces managers to organize
 Provides graphic display of activities
 Identifies
– Critical activities
– Slack activities

3/3/2018 33
Limitations of PERT
 Important activities may be omitted
 Precedence relationships may not be correct
 Estimates may include a fudge factor
 May focus solely on critical path

3/3/2018 34
Project Management Software
 Computer aided design (CAD)
 Groupware (Lotus Notes)
 CA Super Project
 Harvard Total Manager
 MS Project
 Sure Track Project Manager
 Time Line

3/3/2018 35
Advantages of PM Software
 Imposes a methodology
 Provides logical planning structure
 Enhances team communication
 Flag constraint violations
 Automatic report formats
 Multiple levels of reports
 Enables what-if scenarios
 Generates various chart types

3/3/2018 36
Project Risk Management
 Risk: occurrence of events that have
undesirable consequences
– Delays
– Increased costs
– Inability to meet specifications
– Project termination

3/3/2018 37
Risk Management
 Identify potential risks
 Analyze and assess risks
 Work to minimize occurrence of risk
 Establish contingency plans

3/3/2018 38

S-ar putea să vă placă și