LSS GENERAL PROCESS FLOW

1
LSS General Process Flow

Stage 1 Process Flow Description PIC

-Preliminary Power System Study to be -Pre-PSS by Developer


Stage 1
completed and presented at LSSAC -Approval LSSAC by TNB
RFP to ST
-After approval of Pre-PSS by LSSAC,
RFP to ST developer shall submit Request for -Developer
Site Verification Proposal (RFP) to ST

-GS to coordinate joint site visit for


Site Verification -GS
verification of proposal
ESC Approval
-GP unit, GS to present the paper
ESC Approval -Approval of proposal by ESC
in ESC to seek for Approval
Stage 2
-Final PSS Study to be verified and
Stage 2 -GP unit, GS
endorsed by GP
NTP
-Issuance of NTP and Appointment of -GS
NTP
Project Manager -GD to be coordinator

GD Review -To review Soil Investigation, Detail -GD (Design)


GD Review Survey, Drawing etc. -GD (LM)
NO -Land Acquisition (if any) to be assisted
YES
-Civil and M&E physical construction -GD / PM as Project Supervisor
Construction
Construction stage from TNB
-Testing include PQA etc. -GD
Testing &
-Commissioning/Taking Over
Commissioning
Testing & Commissioning Certificate

- To clear TOC defects (if any) -GD / PM as Project Supervisor


Defect Liability Period
- End-of-warranty from TNB
Defect Liability Period

-Project is considered fully completed


Project Closing upon issuance of Completion -GD and relevant parties.
Project Closing Certificate,
2
Disclaimer

All information contained herein are solely for the purpose of this presentation
only and cannot be used or referred to by any party for other purposes without
prior written consent from TNB. Information contained herein is the property of
TNB and it is protected and confidential information. TNB has exclusive copyright
over the information and you are prohibited from disseminating, distributing,
copying, reproducing, using and /or disclosing this information.

S-ar putea să vă placă și