1) STORING THE BLOCKS

 Do not stack the blocks in


 Stack the blocks on dry and
haphazard manner or leave
even surface to avoid contact
them exposed to rain or
with moisture.
moisture
 It is recommended that the
blocks be placed on planks or
other supports.
 The blocks must be covered in
rainy season
www.aacpune.com
2) CUTTING THE BLOCKS

 Do not use tools like hammer,


chisel etc. to cut the blocks  Use a carbide tipped saw to
cut the AAC blocks

www.aacpune.com
3) USING THIN BED MORTAR

 If using thin bed mortar, do not  If using thin bed mortar, the
use a thapi for spreading he thickness of the joint should
mortar. not be more than 3 mm.
 Only recommended tools
should be used. For laying the
mortar, use a notched trowel

www.aacpune.com
4) USING CEMENT-SAND MORTAR AND ITS COMPOSITION

 Do not use a rich mortar mix  If using sand-cement mortar,


as it tends to shrink and might the thickness should be 10-12
cause cracks mm.
 Use 1:6 cement-sand mortar.

www.aacpune.com
5) WETTING THE BLOCKS

 Do not flood the wall with  Moisten the blocks slightly


water using a brush before applying
mortar

www.aacpune.com
6) MAXIMUM WALL CONSTRUCTION IN A DAY

 Do not lay more than six layers  Lay only up to six layers of
of blocks in a day blocks everyday.

www.aacpune.com
7) PLASTER THICKNESS

 The thickness of the external  The thickness of the external


plaster should not be more plaster should be 15 mm and
than 15 mm and thickness of internal plaster should be 10
internal plaster should not be mm
more than 10 mm

www.aacpune.com
8) PLACING THE LINTEL

 The lintel should not be placed  The lintel should be placed on


on half blocks as this causes a complete block
stress concentration resulting
in cracks

www.aacpune.com
9) COPING BEAM

 Coping beam must be 2 nos, 8


 Do not construct a wall mm reinforcement after every
without a coping beam 1.4 mts.

www.aacpune.com
10) LAYING THE BRICKS

 Do not slide the blocks  While placing the blocks, care


horizontally into position after must be taken to slide the
applying mortar on the blocks vertically into position
surface. This causes the as this prevents the mortar
mortar to get displaced and from being displaced
accumulate at the corners

www.aacpune.com
11) CHASE AREA

 Do not apply plaster on chase  Fill the chase area with


area without wire mesh. compact mortar and apply
wire mesh on it.

www.aacpune.com
12) ELECTRICAL AND SANITARY CHASES

 Do not install electrical and  Install the electrical and


sanitary chases after sanitary chases before
plastering. plastering the wall.

www.aacpune.com
13) MAXIMUM WALL CONSTRUCTION IN A DAY

 Do not immerse the block  Dip only the surface of the


completely in water blocks in water.

www.aacpune.com
Thank you

Green Building Products


Gut no 437, Nashik road, near kanifnath mandir,
moshi, Pune 412105
Contact no: 9370066444
Website: www.aacpune.com
Facebook: www.facebook.com/greencubeblocks
Twitter: @GBPGreenCube