Sunteți pe pagina 1din 20

How megabolts installed as

primary support assist in


safely improving
development rates

ACARP Roadway Development Operators Workshops - October 2011


Introduction

Three types of megabolts installed from


continuous miner

● Post grouted megastrands – MW9


● Resin anchored, torque-tensioned megaflex bolts - TTX
● Resin anchored, post groutable fibreglass rib bolts

ACARP Roadway Development Operators Workshops - October 2011 2


MW9 Megabolt

● Most commonly
installed megabolt is
the barrel & wedge
version – MW9
● Fully bulbed using
spiral rib wire for max
load transfer
● Up to 11 m long cables
installed from miner in
LW installation roads

ACARP Roadway Development Operators Workshops - October 2011 3


MW9 – Nth Goonyella face road

ACARP Roadway Development Operators Workshops - October 2011 4


MW9 advantages

● 42 mm hole – no reaming
● Single 1,000 mm resin capsule
with resin retainer
● Resin pushed up hole with bolt
– no conduit
● Collar fittings attached after
bolt installed
● No bearing plate or bolt head to
catch on walkway

ACARP Roadway Development Operators Workshop 2011 5


MW9 advantages

● Tension within 5 mins of


installation
● Tension using system
hydraulics or intensifier
● 9 to 20 t pre-tension can be
achieved depending whether
system hydraulics or
intensifier used
● No air needed on miner
● Provides immediate point
anchor support of 57 t

ACARP Roadway Development Operators Workshop 2011 6


Important considerations

● Bolt is point anchored until


grouted
● Anchor length designed to
take capacity of bolt – depends
on rock type at anchor horizon
● Pull tests must be done to
determine if anchor can take
full capacity of bolt
● This ungrouted bolt is loaded
to 45-50 tonnes

ACARP Roadway Development Operators Workshop 2011 7


MW9 grouting

● Top down grouted using grout


lance – quickest grouting
method
● Grouting done within
designated time or distance
advanced – depends on
conditions
● Heavy conditions may require
grouting within 24 hrs
● Good conditions (intersections)
can be left for more than a week

ACARP Roadway Development Operators Workshop 2011 8


MW9 grouting

● Grout generally reaches


sufficient strength (30 to 40
MPa) within 24 hrs
● Readily & easily audited
● Regular auditing has greatly
improved quality of
installation
● Grouting non-compliance now
less than 5%
● Good installation reduces
likelihood of remedial roof
support
ACARP Roadway Development Operators Workshop 2011 9
MW9 developments

Mechanised insertion
● Lobster from Conway
Engineering
● Being used at Angus
Place
● Favourable reports so
far

ACARP Roadway Development Operators Workshop 2011 10


MW9 developments

Resin grouting using Minova


Carbothix
● Immediate roof support
● Remote pumping
● Quicker grouting

ACARP Roadway Development Operators Workshop 2011 11


Megaflex TTX

● Torque-tensioned
● TT bolt becoming more in
demand
● 56 t and 48 t versions
● 56 t generally requires 28
mm hole
● 48 t a 27 mm hole

ACARP Roadway Development Operators Workshop 2011 12


TTX – advantages

● No exposure to high
pressure tensioner
hydraulics
● Reduced injuries from
handling tensioners
● Quicker installation than
hydraulically tensioned
cables
● Combo dolly

ACARP Roadway Development Operators Workshops - October 2011 13


Combo dolly – no changing dollies

Mixing Tightening
Inner socket engages hex drive Outer socket engages nut

ACARP Roadway Development Operators Workshops - October 2011 14


TTX – advantages

● Roller race between nut &


washer reduces friction
● Race is shrouded to keep
bearing free of dirt or mud
● 7 t bolt tension from 320
Nm drill torque
● Minimal protrusion from
roof – important in low
seams
● Removing hex drive
reduces protrusion further
– as little as 115 mm
ACARP Roadway Development Operators Workshop 2011 15
TTX – advantages

● Wires are anchored in the bolt


head using button heads forged
on end of each wire – maintains
max collar strength
● B&W anchor typically reduces
cable collar capacity by approx
10%

ACARP Roadway Development Operators Workshop 2011 16


TTX – advantages

● Increased load transfer from


spiral wire
● Groutable version being
developed – will require 42
mm dia. hole

ACARP Roadway Development Operators Workshop 2011 17


Limitations of torque-tensioned cables

● Reduced bolt pre-tension compared to hydraulic


tensioning
● Possible use of torque multipliers
‐ Slows down installation
‐ Failure of torque multiplier can delay production
‐ Possible safety issues
● May need modifications to head-plate of drill mast to
accommodate bolt and/or dolly
● Full resin encapsulation difficult for cables > 4 m
● Load transfer lower than for bulbed cables
● If bulbed then larger hole dia. & bigger resin capsule

ACARP Roadway Development Operators Workshop 2011 18


Groutable FG rib bolt

● 42 t capacity
● Cuttable
● 42-45 mm drill hole
● Point anchored initially
● Breakout nut
● High torsion strength –
stalls rib bolting rigs
● 17 t collar capacity
● Shear strength of 14 t
● SG of 1.9 to 2.1 – separates
in washery

ACARP Roadway Development Operators Workshops - October 2011 19


Groutable FG rib dowel - advantages

● Immediate rib support


● Hollow centre - post groutable
with thixotropic grout
● Full encapsulation vital in
heavy rib conditions
● Easily audited
● No secondary rib support
required – maximises
development rates

ACARP Roadway Development Operators Workshops - October 2011 20

S-ar putea să vă placă și