Contractor
Prepare
Proposal
2.-Contractors proposal; issue within 14 days from receipt of RFP and shall include:
Contractor •Scope of work, Construction Methodology, Realistic level 3 schedule, Agree Operator
Submit proposal compensation method or propose different one .
to ISG
•Cost estimate; the Contractor shall generate and provide a realistic cost estimate.
14 DAYS Period
No
ISG
ISG not Agree with
ISG Issue
COO
Workflow
No
Work not completed
ISG
at satisfaction of ISG
Work completed at
Yes satisfaction of ISG
Contractor issue a final ISG approve payment of
ISG Issue completion commercial statement remaining 10% on acceptance
certificate for each COO of completion certificate.
Call Off Order (COO) Process
Type of COO :
1. For wellpads and access roads
2. For modifications
3. For misc ad hoc services
Initiation of work :
1- Request For Proposal RFP (
includes Scope, technical data,
compensation, target date )
OPERATOR CONTRACTOR
As lesson learn , the COO’s must be optimised (reduce numbers by grouping small scopes for
same MOC when possible) , and should be a comprehensive document package with all above
requirements to ensure successful execution of the work and compensation of contractor
Measurement of
each activity +
calculation
SITE
LEVEL 3 PLAN PLANNED % Vs ACTUAL % MEASUREMENT
(PROGRESS
ACHIEVED)
Activities to be
weighted
LESSONS LEARNS
CONTRACTOR to ensure the following data are correct on the invoice :
1- Description of COO and location of work .
2- COO No and relevant MOC No .
3- Type of COO : Lump Sum , Unit rates , Day Rates , Reimbursable .
4- Appropriate compensation method used .
5- Only One monthly invoice to present .
◙ VOWD for each COO : VALUE OF WORK DONE is the measure in term of cost of the
achieved progress / work to date for each COO .
VOWD = CUMULATIVE INVOICED COST + ESTIMATE OF
NON INVOICED WORK ACHIEVED TO DATE
◙ Final Forecast Cost FFC: Assessment by Contractor of Anticipated final cost for each COO
.
FFC = VOWD + TO GO FORECAST
Where TO GO is the measure of remaining work / progress to be
completed
◙ Items in red are mandatory and must be detailed , accurate , with more focus from
CONTRACTOR.
-Mobilisation
To be agreed
within first ten
-Amount to invoice for COO’s days of the month
between
-Demobilisation OPERATOR &
CONTRACOR
► Lump Sum Or Unit rate COO : to be invoiced based on approved achieved progress
up to 90% . The remaining 10% on acceptance of completion certificate .
► Reimbursable COO : Reimbursable mean that CONTRACTOR has paid for third party
services or materials procured for OPERATOR . Then OPERATOR need to compensate
CONTRACTOR based on paid invoices plus contractual mark-up . Supporting invoices
documentation is very important to ensure compensation .
REPORTING
● 3 Reports required from contractor :
► Daily Report :
- mainly on available resources and key issues .
Note :
For minor works , the RFP document could be just a short email .
RFP’s should be recorded properly in a system as they are the
only proofs for any initiated work by OPERATOR .
The COO revision should include the COO revision form with two attached documents : the RFP for change +
Change request for OPERATOR changes , or just COO revision and change request for CONTRACTOR changes .