Documente Academic
Documente Profesional
Documente Cultură
As the wave hits the water passes inside thespace and turns
around inside. Thus the forceis largely dissipated
Various Stages of Construction
RESOURSES
Project Manager,
PROJECT HSE Engineer,
HSE ENGINEER HSE Technician,
HSE TECHNICIAN QA/QC
QA/QC Engineer, QA/QC Technician, Accounting
MANAGER &
ENGINEER
Admin Chief, Logistics & Storage, Accounting /
HUMAN Personnel, Camp Supervisor, Purchasing, Finishing
ACCOUNTING
Works&SiteLOGISTICS & Engineers,
Chief, Site ACCOUNTING CAMP
Site Architects,
RESOURCES ADMIN CHIEF STORAGE
Site Technicians, Foremen,AND PERSONAL
Structural WorksSUPERVISOR
Site
Chief, Technical Office Chief, Planning & Cost
Control, Quantity Surveying Engineer, Quantity
Surveying Technician, Design Office Chief, Design
FINISHING SITE ENGINEERS SITE SITE
Office
WORK SITE Architects, Design Office Technicians,
ARCHITECTS Site
TECHNICIANS
CHIEF Surveying Chief, Topographic Engineer,
Topographs, MEP Works Chief, Electrical
STRUCTURAL TECHNICAL
Engineers, PLANNINGMEP
Mechanical Engineers, AND Works
QUANTITY
WORK SITE OFFICE CHIEF COST CONTROL SURVEYING
Technicians
CHIEF ENGINEER
DESIGN OFFICE DESIGN OFFICE DESIGN OFFICE SITE SURVEYING
CHIEF ARCHITECTS TECHNICIANS CHIEF
HUMAN
RESOURCES TOPOGRAPHIC TOPOGRAPHS MEP WORK CHIEF ELECTRICAL
ENGINEER ENGINEERS
QA/QC QUANTITY
TECHNICIANS SURVEYING
TECHNICIANS
MATERIAL Construction material
equipments and
RESOURSES Construction
tools
MechanicaL materials
and equipment
electrical and plumbing supplies
Security systems
Sanitary appliances
Furniture supplies
Communication systems
special items
Financial
resourses Al Jumerah Group
Financial institutions
Investors
PROJECT 1.Project Charter Approval.
2.Budget estimation completed.
MILESTONES 3.Design Approval.
4.Equipment Installation.
5.Start Working in the site.
6.Finishing Foundation Works.
7.Complete Construction.
8.Completing Finishing works.
9.Equipment removed & Site Clean.
10.Closing Project.
11.Project Ended.
ESTIMATED DURATION
Cost Estimating is defined as
ESTIMATED developing an approximation of the
COST costs of the resources needed to
complete project activities. It will
allow the organisation to have a clear
view on their budget they would need
to provide the quality product or
service. The cost estimation is not
legal binding its just an over view for
the organisation of the initial project
budget
PROJECT
RISKS
Even the most carefully planned project can run into
trouble. No matter how well you plan, your project
can always encounter unexpected problems. Team
members get sick or quit, resources that you were
depending on turn out to be unavailable, even the
weather can throw you for a loop
Technical
risks
•Incomplete Design.
•Inadequate site investigation.
•Uncertainty over the source and
availability of materials.
•Appropriateness of specifications.
•Design faults and problems
4.Logistical Risks:
•Availability of resources –
particularly construction equipment ,
spare parts, fuel, and labor.
•Availability of sufficient
transportation facilities.
5.Construction Risks:
•Uncertain productivity of resources.
•Weather and seasonal implications.
•Industrial relations problems.
•Failure of structure.
6.Financial Risks:
•Inflation.
•Availability and fluctuation in foreign
exchange.
•Delay in payments.
•Repatriation of funds.
•Local taxes.
•Economic Crisis.
7.Political Risks:
12. Sub-contractors • Carry out parts of the project work contracted to them by
the main contractors
13. suppliers • Provide materials whenever required
14. Logistics company • Transportation of staff , material and equipments to
project site
15. Environment agencies • Ensure that environment laws are adhered to
• Approval of project environment impact assessment
16. Environment activists • Protection of the natural and sipiritual history of the
project environment