Documente Academic
Documente Profesional
Documente Cultură
• Definition:
any change in
quantities of any item of work included in the contract
quality of work
levels , positions, or dimensions of any part of the work
Omissions of any work
Any additional work, plant, material or services necessary for permanent work
the sequence or timing of the execution of the works.
Which the engineers /employer or contractor finds it necessary to complete the permanent work
Disagree gives notice to the engineer stating that contractor could not obtain the required goods or the variation trigger the substantial change in
progress of the work. Upon receiving the notice, engineer shall cancel , confirm or vary the instruction.
Clause 13:Variations
Sub clause 3.1:
if the engineer is required to obtain the approval of the employer before executing a specified authority, the
requirement shall be stated in particular conditions.
The engineer should obtain specific approval of the employer before taking actions on the following sub clauses :
Sub clause 4.12: agreeing or determining an extension of time /additional cost
Sub clause 13.1: instructing a variation , except:
In an emergency situation as determined by the engineer
If such a variation would increase the accepted contract amount by less then the percentage specified in the
contract data
Sub clause 13.1: approving a proposal for variation submitted by the contractor in accordance with sub clause 13.1
( right to vary ) or 13.2 ( value engineering)
• The engineer shall not adjust rates for the change in quantities if the intitial contract price exceeds 2% ,
except of the prior approval of the employer
• The contractor should provide the engineer the quotation for carrying out the variation when requested
to do so by the project manager. It should include the contractor's direct costs, overheads and profit is
necessary.
• the project manager should asses the quotation within 7 days of submission and agree or comment .
• If not agreed , then make a fair determination in accordance with the Contract, taking due regard of all
relevant circumstances.
The Claims Procedure
(1) If the Contractor considers himself to be entitled to an extension of the
Time for Completion and/or additional payment
the Contractor must give notice to the Engineer as soon as practicable and “not later than 28 days after the Contractor became
aware, or should have become aware, of the event or circumstance” giving rise to the claim.
The Contractor has merely to give a bare notice of claim within 28 days. A one- or two-sentence letter will do. The Contractor
does not need to state the amount or time claimed nor the contractual basis of the claim nor provide any supporting
documents.
If the Contractor fails to give such notice of claim within 28 days: “the Time for Completion shall not be extended, the
Contractor shall not be entitled to additional payment, and the Employer shall be discharged from all liability in connection
with the claim”
The Claims Procedure
(2) When the Contractor gives such a notice under the new Sub-Clause, he is
required
and the Engineer is authorized to monitor the Contractor’s record-keeping and/or instruct the Contractor to keep additional contemporary records
(3) Within 42 days after the Contractor became aware, or should have become
aware, of the event or circumstance giving rise to the claim:
the Contractor is required to send to the Engineer (or Employer) “a fully detailed claim” which includes “full supporting particulars of the basis of the
claim and of the extension of time and/or additional payment claimed”.
The Claims Procedure
(4) Within 42 days after receiving a claim or any further particulars supporting a
previous claim,
the Engineer (or Employer) must respond “with approval, or with disapproval and
detailed comments”.
He may also request any necessary further particulars “but shall nevertheless give his
response on the principles of the claim within such time”.
Variations
Flow Chart
Variations
Flow Chart
Variations
Flow Chart
Variations
Flow Chart