PROJECT EXECUTION PLAN

BT3 2X5 MW MHPP PROJECT


Basic Idea

• To start commencing this project, access road


development is a must
• The 1st: access road to weir
• The 2nd: Inspection Road to weir parallelly
with waterway, sandtrap and flushing way
• The 3rd: Cofferdam #1 Construction
• The 4th: Intake & Spill way of weir and some
parts of weir body
• When this construction finish, It can be
functioned for diversion channel
• Water is directed to flow through intake and
flush out back to river through flushing way
Execution Schenario
Intake
Inspection Cofferdam
Access
Road & @intake Gate
Road to
Waterway weir & Installation
Weir
to Weir Dewatering
Gate
Fabrication

Syphon
Foundation
Inspection
Road & Syphon
Waterway Installation
to Syphon
Syphon
Fabrication

Inspection Road
Access Road
& Waterway
To Power
from Syphon to
House
PH

River Diversion
through intake
Cofferdam
& Flush out
@weir body &
through
Dewatering
flushing of
sandtrap

Penstock Penstock Penstock


Fabrication Delivery Installation

Penstock
Foundation

Power House Building

Turbine & Turbine & Testing &


Generator Generator Tie In Commissio
Foundation Installation ning
Cofferdam

Cofferdam Stage #1

Cofferdam Stage #2
Cofferdam Stage #1

Construction at lowest
discharge time Cofferdam Stage #2
Dewatering

Cofferdam
Stage #1

Cofferdam
Stage #2

upstream Construction area downstream

Item of Concern: Item of Concern: Item of Concern:


Q, Compaction, GWL, Pump GWL,
Impervious Material capacity, Number of
for filler, Mechanical Pump, Electric
Properties of soil Power for Pump,
Keep area dry for
construction
THANK YOU