Sunteți pe pagina 1din 11

[CCN-0718A]

Advanced Network: Final Presentation


By: [Muhammad Salihin bin Senin
Contents

1. Project Definition
2. Deliverables
3. Milestones & Tasks
4. Project Environment
5. Project Tasks
6. Milestone Feedback & Results
7. Learning & Challenges
1. Project Definition
 Project Objective
 Assemble and mount switch a rack for physical security.
 Connect Switch and peripherals in accordance with manufacturer requirements.
 Configure switch according to technical requirements and manufacturer’s guidelines.
 Test the switch with other network devices in accordance with technical requirements and
organizational guidelines.
 Determine switch network topology to be installed, with reference to network architecture and network
protocol types
 Install switches according to vendor guidelines, network architecture and client requirements
 Test the switches to assess impact of the changes on the network
 Troubleshoot the network to track and resolve errors
2. Project Deliverables
 Project Deliverables
 Assemble and mount switch a rack for physical security.
 Connect Switch and peripherals in accordance with manufacturer requirements.
 Configure switch according to technical requirements and manufacturer’s guidelines.
 Test the switch with other network devices in accordance with technical requirements and organizational
guidelines.
 Determine switch network topology to be installed, with reference to network architecture and network protocol
types
 Install switches according to vendor guidelines, network architecture and client requirements
 Test the switches to assess impact of the changes on the network
 Troubleshoot the network to track and resolve errors
3. Project Milestones & Tasks

Project
Project Project Task Description Milestone
Task ID ID
1 Task 1: List the Switch capabilities and identify if these capabilities will be used in the network. 1
1 Task 2: Ensure the switch has the ability to support all the technologies identified in the requirements. 1
Task 3: Draw a rack elevation drawing showing the switches mounted in racks located in the main or
1 1
intermediate distribution frames (closets)
4. Project Environment
 Technical Environment and Tools Used
 Cisco Packet Tracer 7.2.1
5. Tasks – 1

Milestone 1 –
List the Switch capabilities and identify if these capabilities will be used in the network.
Milestone Statement:
5. Tasks – 2

Ensure the switch has the ability to support all the technologies identified in the requirements.
5. Tasks – 3

Draw a rack elevation drawing showing the switches mounted in racks


located in the main or intermediate distribution frames (closets)
6. Milestone Feedback & Action Taken

Project Milestone Milestone Feedback received from Mentor / Learning Action Taken
ID Facilitator (Yes / No)

3
7. Learning & Challenges

• Describe any key learning or observations


• Describe challenges, if any, which you faced during the project execution

S-ar putea să vă placă și