Documente Academic
Documente Profesional
Documente Cultură
Faculty of engineering
Concrete project
Main unit
(Unit 1 & 2)
Calculations
sheet
1- Right part
The Right part consists of :
1- Deflection :
*Long term deflection equation :
As`
Equation = (2 – 0.2 *
As )*D.L + L.L = 1.8 D.L + L.L Where As` = As
LMax 847
Allow = = = 3.39 cm .
250 250
Max = 2.65 cm For flat slab .
1- Right part 5
2- Middle part
The Middle part consists of :
1- Deflection :
*Long term deflection equation :
As`
Equation = (2 – 0.2 *
As )*D.L + L.L = 1.8 D.L + L.L Where As` = As
LMax 820
Allow = = = 3.28 cm .
250 250
Max = 2.52 cm For flat slab .
2- Middle part 8
1- Deflection :
*Long term deflection equation :
As`
Equation = (2 – 0.2 *
As )*D.L + L.L = 1.8 D.L + L.L Where As` = As
LMax 925
Allow = = = 3.7 cm
250 250
Max = 3.6 cm For flat slab , Max = 3.45 cm For Ribs system.
3- Upper left part 11
∴ As = 2 16 / rib ∴ As = 2 25 / rib
** For Office floors in the Upper left part : 14
2
∵ Area = 7.5 * 12 m
∴ Use One way Hollow blocks system .
Take Blocks = ( 200*400*250) & slab 7 cm
∴ S = e + b = 0.4 + 0.1 = 0.5m
0.695 T/m`
7.30 ((m))
4.63 T.m
∴ As = 2 20 / rib
Ground ceiling
15
1- Deflection :
*Long term deflection equation :
As`
Equation = (2 – 0.2 *
As )*D.L + L.L = 1.8 D.L + L.L Where As` = As
Max = 2.15 cm For flat slab , Max = 1.60 cm For Girders system.
4- Lower left part 16
∴ As = 392.7 mm 2 L ((m))
6
MU.L* 10
∴ As = =392.7mm 2
360 * 100 * 0.826
∴ From 1 & 2
2
∴ As = 331.4 mm 2 ∴ As = 886.72 mm
∴` As = 5 10 ∴ As = 5 16
For internal beams :
∴ As = 588.5 mm 2 ∴ As = 1716.61 mm 2
∴ As = 6 12 ∴ As = 6 20
Design of girders : 20
∵ O.W of beams = 1.4*0.25*0.60*2.5 = 0.525 t/m2 = 5.25 KN/m2
For External beams : For internal beams :
∴We = 5.25 + 12.2 * 2.65 2 = 21.4 KN/m` ∴We = 5.25 + 2*12.2 *
2.65
2
= 37.6 KN/m`
∴ Rext. =21.4 * 6.5 = 139.1 KN ∴ Rint. =37.6 * 6.5 = 244.3 KN
2 2
∵ O.W of Girder = 1.4*0.4*0.9*2.5 = 1.26 t/m = 12.6 KN/m
3
834.94 KN.m 1
834.94 KN.m
2
Sec 1-1 Sec 2-2
Take d= 900-50 = 850 mm Take d= 900-50 = 850 mm
∴ As = 10 25 ∴ As = 8 25
Sec 3-3
∴ As = 5 20
First floor ceiling
21
1- Right part
The Right part consists of :
1- Deflection :
*Long term deflection equation :
As`
Equation = (2 – 0.2 *
As )*D.L + L.L = 1.8 D.L + L.L Where As` = As
LMax 847
Allow = = = 3.39 cm .
250 250
Max = 3.31 cm For flat slab .
1- Right part 22
2- Middle part
The Middle part consists of :
1- Deflection :
*Long term deflection equation :
As`
Equation = (2 – 0.2 *
As )*D.L + L.L = 1.8 D.L + L.L Where As` = As
∴ As = 392.7 mm 2 L ((m))
6
MU.L* 10
∴ As = =392.7mm 2
360 * 100 * 0.826
∴ From 1 & 2
2
∴ As = 331.4 mm 2 ∴ As = 886.72 mm
∴` As = 5 10 ∴ As = 5 16
For internal beams :
3
∴We = 4.40 + 2*11.1* 2 = 37.7 KN/m`
3.77 T/m` 3.77 T/m`
∴ As = 588.5 mm 2 ∴ As = 1716.61 mm 2
∴ As = 6 12 ∴ As = 6 20
Design of Two fixed frame :
1405.5 + 793
∴ Dist. Load on frame = 1.4*0.4*1.7*25 + 282.75
24
*7
+ = 197.9KN/m
2
1405.5 24
779
157.9 282.75 282.75 282.75 282.75 282.75 282.75 282.75 157.9
23.8 KN/m`
7.50 ((m))
8.70 ((m))
15.00 ((m)) 8.70 ((m))
24.00 ((m))
157.9 157.9
197.9 KN/m`
8.70 ((m))
8.70 ((m))
24.00 ((m))
30
1 2
3 3
1 2
4 4
Sec 1-1 31
Check
PU.L =
1832.7 *1000
= 0.0535 > 0.004 (Don`t neglect N)
FCU * b * t 30*600*1900
MU.L e 4.76
e = PU.L = 4.76 m ∴ = 1.90 = 2.51 > 0.5 ∴Use es
t
∴ es = e + t/2 - c = 2.51 + 0.95 – 0.1 = 3.26 m
Sec 2-2
Check
PU.L =
1832.7 *1000
= 0.0535 > 0.004 (Don`t neglect N)
FCU * b * t 30*600*1900
MU.L e 3.25
e = PU.L = 3.25 m ∴ = 1.90 = 1.71 > 0.5 ∴Use es
t
∴ es = e + t/2 - c = 1.71 + 0.95 – 0.1 = 2.56 m
Check
PU.L =
2568.9 *1000
= 0.07515 < 0.004 (Don`t neglect N)
FCU * b * t 30*600*1900
MU.L e 3.39
e = PU.L = 3.39 m ∴ = 1.90 = 1.784 > 0.5 ∴Use es
t
∴ es = e + t/2 - c = 1.784 + 0.95 – 0.1 = 2.634 m
Sec 4-4
Check
PU.L =
2568.9 *1000
= 0.0751 > 0.004 (Don`t neglect N)
FCU * b * t 30*600*1900
MU.L e 2.10
e = PU.L = 2.10 m ∴ = 1.90 = 1.11 > 0.5 ∴Use es
t
∴ es = e + t/2 - c = 1.11 + 0.95 – 0.1 = 1.96 m
1- Deflection :
*Long term deflection equation :
As`
Equation = (2 – 0.2 *
As )*D.L + L.L = 1.8 D.L + L.L Where As` = As
LMax 925
Allow = = = 3.7 cm
250 250
Max = 3.6 cm For flat slab , Max = 3.45 cm For Ribs system.
3- Upper left part 34
∴ As = 2 16 / rib ∴ As = 2 25 / rib
** For President Office & secretary floors in the Upper
left part :
37
2
∵ Area = 7.5 * 12 m
∴ Use One way Hollow blocks system .
Take Blocks = ( 200*400*250) & slab 7 cm
∴ S = e + b = 0.4 + 0.1 = 0.5m
0.695 T/m`
7.30 ((m))
4.63 T.m
∴ As = 2 20 / rib
First floor ceiling
38
1- Deflection :
*Long term deflection equation :
As`
Equation = (2 – 0.2 *
As )*D.L + L.L = 1.8 D.L + L.L Where As` = As
Max = 2.15 cm For flat slab , Max = 1.60 cm For Girders system.
4- Lower left part 39
∴ As = 392.7 mm 2 L ((m))
6
MU.L* 10
∴ As = =392.7mm 2
360 * 100 * 0.826
∴ From 1 & 2
2
∴ As = 331.4 mm 2 ∴ As = 886.72 mm
∴` As = 5 10 ∴ As = 5 16
For internal beams :
∴ As = 588.5 mm 2 ∴ As = 1716.61 mm 2
∴ As = 6 12 ∴ As = 6 20
Design of girders : 43
∵ O.W of beams = 1.4*0.25*0.60*2.5 = 0.525 t/m2 = 5.25 KN/m2
For External beams : For internal beams :
∴We = 5.25 + 12.2 * 2.65 2 = 21.4 KN/m` ∴We = 5.25 + 2*12.2 *
2.65
2
= 37.6 KN/m`
∴ Rext. =21.4 * 6.5 = 139.1 KN ∴ Rint. =37.6 * 6.5 = 244.3 KN
2 2
∵ O.W of Girder = 1.4*0.4*0.9*2.5 = 1.26 t/m = 12.6 KN/m
12.6 KN/m`
3
834.94 KN.m 1
834.94 KN.m
2
Sec 1-1 Sec 2-2
Take d= 900-50 = 850 mm Take d= 900-50 = 850 mm
∴ As = 10 25 ∴ As = 8 25
Sec 3-3
∴ As = 5 20
Second floor ceiling
44
1- Right part
The Right part consists of :
1- Deflection :
*Long term deflection equation :
As`
Equation = (2 – 0.2 *
As )*D.L + L.L = 1.8 D.L + L.L Where As` = As
LMax 847
Allow = = = 3.39 cm .
250 250
Max = 2.65 cm For flat slab .
1- Right part 45
2- Middle part
The Middle part consists of :
1- Deflection :
*Long term deflection equation :
As`
Equation = (2 – 0.2 *
As )*D.L + L.L = 1.8 D.L + L.L Where As` = As
LMax 820
Allow = = = 3.28 cm .
250 250
Max = 3.25 cm For flat slab ,.
2- Middle part 48
1- Deflection :
*Long term deflection equation :
As`
Equation = (2 – 0.2 *
As )*D.L + L.L = 1.8 D.L + L.L Where As` = As
LMax 925
Allow = = = 3.7 cm
250 250
Max = 3.6 cm For flat slab , Max = 3.45 cm For Ribs system.
3- Upper left part 51
∴ As = 2 16 / rib ∴ As = 2 25 / rib
** For Office floors in the Upper left part : 54
2
∵ Area = 7.5 * 12 m
∴ Use One way Hollow blocks system .
Take Blocks = ( 200*400*250) & slab 7 cm
∴ S = e + b = 0.4 + 0.1 = 0.5m
0.695 T/m`
7.30 ((m))
4.63 T.m
∴ As = 2 20 / rib
Second floor ceiling
55
1- Deflection :
*Long term deflection equation :
As`
Equation = (2 – 0.2 *
As )*D.L + L.L = 1.8 D.L + L.L Where As` = As
Max = 2.15 cm For flat slab , Max = 1.60 cm For Girders system.
4- Lower left part 56
∴ As = 392.7 mm 2 L ((m))
6
MU.L* 10
∴ As = =392.7mm 2
360 * 100 * 0.826
∴ From 1 & 2
2
∴ As = 331.4 mm 2 ∴ As = 886.72 mm
∴` As = 5 10 ∴ As = 5 16
For internal beams :
∴ As = 588.5 mm 2 ∴ As = 1716.61 mm 2
∴ As = 6 12 ∴ As = 6 20
Design of girders : 60
∵ O.W of beams = 1.4*0.25*0.60*2.5 = 0.525 t/m2 = 5.25 KN/m2
For External beams : For internal beams :
∴We = 5.25 + 12.2 * 2.65 2 = 21.4 KN/m` ∴We = 5.25 + 2*12.2 *
2.65
2
= 37.6 KN/m`
∴ Rext. =21.4 * 6.5 = 139.1 KN ∴ Rint. =37.6 * 6.5 = 244.3 KN
2 2
∵ O.W of Girder = 1.4*0.4*0.9*2.5 = 1.26 t/m = 12.6 KN/m
12.6 KN/m`
3
834.94 KN.m 1
834.94 KN.m
2
Sec 1-1 Sec 2-2
Take d= 900-50 = 850 mm Take d= 900-50 = 850 mm
∴ As = 10 25 ∴ As = 8 25
Sec 3-3
∴ As = 5 20
Roof ceiling
61
Right part
Left part
Roof ceiling
62
1- Right part
The Right part consists of :
1- Deflection :
*Long term deflection equation :
As`
Equation = (2 – 0.2 *
As )*D.L + L.L = 1.8 D.L + L.L Where As` = As
Using MACRUS :
α = 0.54 & β = 0.26 2
β = 0.26
α = 0.54
1 1
2
66
Strip 1 Strip 2
0.54*0.737 = 0.4 T/m` 0.26*0.737 = 0.19 T/m`
∴ As = 2 16 / rib ∴ As = 2 12 / rib
Roof ceiling
67
2- Left part
The Left part consists of :
1- Deflection :
*Long term deflection equation :
As`
Equation = (2 – 0.2 *
As )*D.L + L.L = 1.8 D.L + L.L Where As` = As
LMax 525
Allow = = = 2.10 cm .
250 250
Max = 1.74 cm For flat slab .
2- Left part 68
Manual Beam 1 :
Ws U.L Flat slab = 1.4(0.26*2.5 + 0.15) + 1.6*0.3 = 1.6 t/m
WS U.L Flat slab = 1.4(0.16*2.5 + 0.15) + 1.6*0.3 = 1.25 t/m
∴ C1 = 5.08 6.20 m
J = .826
6
588.61*10 2
∴ As = 360 * 650 * 0.826
=3045 mm
As =9 22 B8 (30*80) 588.61 KN.m
Beams
71
Manual calculation for some beams:
Manual Beam 2 :
Ws U.L Flat slab = 1.4(0.22*2.5 + 0.15) + 1.6*0.3 = 1.46 t/m
∴ C1 = 3.59 6.60 m
J = 0.794
6
223.74*10 2
∴ As = 360 * 650 * 0.794
=1204 mm
As =6 16 B2 (30*70) 588.61 KN.m
Beams
Manual calculation for some beams: 72
Cantilever beam :
Assume that the RFT Of cantilever will extend into the beam as
stirrups , then check the stirrups for shear and torsion .
q cu = 0.24 2.50
= 0.98 N/mm
2
1.50
q = 0.06
2.50
= 0.245 N/mm
2
700
t min 1.50
q = 0.70
2.50
= 2.85 N/mm
2
U Max 1.50 9 12 From
design of slab
WsU.L cant. slab= 1.4(0.28*2.5 + 1.5) + 1.6*2
= 15.10 KN/m` 300
2
15.1 * 2.8
MU.L = mt = = 59.19KN.m/m` 15.10 KN/m`
2
59.19 KN/m`
MT = 201.25 KN.m 2.80 m
59.19KN.m/m`
6.80 m
201.25
T.M.D
201.25 R = 42.28 kn
73
W due to shear = R + O.W of beam
= 42. 28 + 1.4*0.3*0.7*25 = 49.63 KN/m`
49.19 KN/m`
6.80 m
168.74
S.F.D
168.74
2
A o h = 220 * 620 = 136400 mm
2
A o = 0.85 * 220 * 620 = 115940 mm
620
3
qu = Q
=
168.74 * 10
= 0.865 N/mm
2
b*d 300*650
q tu = Mtu 201.75 * 10
6
2
2 Ao te = 2 * 115940 *81.19 = 10.71 N/mm
920
Ao h
te = 2
= 144.18 N/mm
Ph
3
qu = Q
=
168.74 * 10
= 0.375 N/mm
2
b*d 500*950
420
q tu = Mtu 6
= 2 *201.25 * 10 2
2 Ao te 309120 *144.18
= 2.257 N/mm
q cu = > qu
2
0.98 N/mm
q
t min
= 0.245 N/mm
2
< q tu ∴ Use RFT to resist q tu
6
Astr = Mtu * S 201.25 * 10 * St
= = 0.979 * St mm 2
1.7*Ao* Fy 1.7 * 309120 * 360 1.15
Ys
1- Right part :
Moment values of beams in Hz direction :
2- Middle part :
Moment values of beams in Hz direction :
1- Right part :
Moment values of beams in Hz direction :
2- Middle part :
Moment values of beams in Hz direction :
1- Right part :
Moment values of beams in Hz direction :
2- Middle part :
Moment values of beams in Hz direction :
1- Right part :
Moment values of beams in Hz direction :
2- Left part :
Moment values of beams in Hz direction :
Stair 1
Design of stair 1:
ts = Ltotal/25 = 6.57/25
1.67 t/m` o
= 0.28m = 28cm
26.56
ts avg.= ts + 7cm = 35cm
∴ As = 7 16/m` 7 m.t
Design of stair 1:
102
Strip 2 : 1.67 t/m`
6
20.0*10 ∴c1 = 9.2
∴ 260 = c1 25*1000 1.55 m
j = 0.826
6
20.00 *10 2 2 t.m/m`
∴ As = 260 * 360 * 0.826
= 258.7 mm/m`
∴ As = 5 10/m`
2.59 t
Loads on Vertical beam :
6.55 t/m` 6.55 t/m`
3.325 t/m`
B.M.D
6.28 mt
2.00 m.t/m`
0.265 mt
T.M.D
0.265 mt
6.55 t/m` 6.55 t/m`
3.325 t/m`
9.12 ton
S.F.D
9.12 ton
103
Cantilever beam :
Assume that the RFT Of cantilever will extend into the beam as
stirrups , then check the stirrups for shear and torsion .
q cu = 0.24 2.50
= 0.98 N/mm
2
1.50
q = 0.06
2.50
= 0.245 N/mm
2
700
t min 1.50
q = 0.70
2.50
= 2.85 N/mm
2
U Max 1.50 5 12 From
design of slab
2 300
A o h = 220 * 620 = 136400 mm
2
A o = 0.85 * 220 * 620 = 115940 mm
P h = 220 * 2 + 620 * 2 = 1680 mm
Ao h
te = = 81.19 mm
Ph
3
qu = Q
=
91.2 * 10
= 0.467 N/mm
2
620
b*d 300*650
q tu = Mtu 2.65 * 10
6
2
2 Ao te = 2 * 115940 *81.19 = 0.141 N/mm
220
Strip 2
700
5 10/m` From
design of slab
300
Stairs
Manual calculation for RFT of stairs 105
1 2
Design of stair 2: 1
Stair 2
ts = Ltotal/25 = 4.76/25
1.39 t/m` o
= 0.20m = 20cm
26.56
ts avg.= ts + 7cm = 27cm
∴ As = 5 10/m`
1.84 t
B.M.D
6.39 mt
1.22 m.t/m`
0.564 mt
T.M.D
0.564 mt
4.24 t/m` 4.24 t/m`
2.575 t/m`
7.70 ton
S.F.D
7.70 ton
107
Cantilever beam :
Assume that the RFT Of cantilever will extend into the beam as
stirrups , then check the stirrups for shear and torsion .
q cu = 0.24 2.50
= 0.98 N/mm
2
1.50
q = 0.06
2.50
= 0.245 N/mm
2
700
t min 1.50
q = 0.70
2.50
= 2.85 N/mm
2
U Max 1.50 5 10/m` From
design of slab
2 300
A o h = 220 * 620 = 136400 mm
2
A o = 0.85 * 220 * 620 = 115940 mm
P h = 220 * 2 + 620 * 2 = 1680 mm
Ao h
te = = 81.19 mm
Ph
3
qu = Q
=
77.00* 10
= 0.395 N/mm
2
620
b*d 300*650
q tu = Mtu 5.64 * 10
6
2
2 Ao te = 2 * 115940 *81.19 = 0.299 N/mm
220
700
5 10/m` From
design of slab
300
Strip 2
6
Astr = Mtu * S 5.60 * 10 * St
Fy= 1.7 * 136400 * 360 = 0.0771 * St mm2
1.7*Ao* 1.15
Ys
Strip 2
700
5 10/m` From
design of slab
300
Stairs
Manual calculation for RFT of stairs 110
1 2 1
Design of stair 3: 1 1
Stair 3
Strip 1 : 1.60 t/m`
ts = Ltotal/25 = 6.13/25
1.60 t/m` o
= 0.26m = 26cm
26.56
ts avg.= ts + 7cm = 33cm
∴ As = 5 10/m`
2.40 t
B.M.D
7.39 mt
1.80 m.t/m`
0.135 mt
T.M.D
0.135 mt
6.025 t/m` 6.025 t/m`
3.135 t/m`
8.37 ton
S.F.D
8.37 ton
112
Cantilever beam :
Assume that the RFT Of cantilever will extend into the beam as
stirrups , then check the stirrups for shear and torsion .
q cu = 0.24 2.50
= 0.98 N/mm
2
1.50
q = 0.06
2.50
= 0.245 N/mm
2
700
t min 1.50
q = 0.70
2.50
= 2.85 N/mm
2
U Max 1.50 5 10/m` From
design of slab
2 300
A o h = 220 * 620 = 136400 mm
2
A o = 0.85 * 220 * 620 = 115940 mm
P h = 220 * 2 + 620 * 2 = 1680 mm
Ao h
te = = 81.19 mm
Ph
3
qu = Q
=
83.70* 10
= 0.429 N/mm
2
620
b*d 300*650
q tu = Mtu 1.35 * 10
6
2
2 Ao te = 2 * 115940 *81.19 = 0.072 N/mm
220
Strip 2
700
5 10/m` From
design of slab
300
Stairs
Manual calculation for RFT of stairs 114
2
1
1
Strip 1 Strip 2
1.35 m 1.50 m
1.69 t 1.875 t
115
6 6
11.39*10 18.0*10
∴ 140 = c1 25*1000 ∴ 140 = c1 25*1000
∴c1 = 6.56 ∴c1 = 5.22
6 j = 0.826 6
j = 0.826
11.39 *10 14.1 *10
∴ As = 240 * 360 * 0.826
∴ As = 240 * 360 * 0.826
∴ As = 5 10/m` ∴ As = 5 10/m`
1.41 m.t/m` 1.41 m.t/m`
2.56 mt 0.186 mt
0.186 mt
2.56 mt
q tu = Mtu 25.6 * 10
6
q tu = Mtu 1.86 * 10
6
6
Astr = Mtu * S 25.6 * 10 * St
=
1.7*Ao* Fy 1.7 * 136400 * 360
1.15
Ys
= 0.352 * St mm
700
5 10/m` From
design of slab
300
Strip 2
700
5 10/m` From
design of slab
300
Check buckling of columns :
1- Lower left part columns : 117
External column :
70
In plane 70
Out of plane 70 70
Internal column :
In plane 70
Out of plane 70
C1 (Corner column) :
3.35
q Pcu = 0.316 25
= 1.29 N/mm
2
0.51
1.5
C1 (30*40)
q Pu = Qpu
*β
0.41
Ap 1.25
1.22
7.25
q Pcu = 0.316 25
= 1.29 N/mm
2
C12 (40*100)
1.5
q Pu = Qpu
*β
Ap 0.62
7.20
C8 (Edge column) :
0.72
5.30
q Pcu = 0.316 25
= 1.29 N/mm
2
C8
1.5 (30*50)
q Pu = Qpu
*β
Ap 0.41
3.90
∴ q Pu =
29.75 2
93.16 t/m = 0.932 N/mm < q Pcu
2
* 1.30= (Safe)
0.39
121
C17 (Interior column) :
1.22
4.00
q Pcu = 0.316 25
= 1.29 N/mm
2
C17 (30*100)
1.5
q Pu = Qpu
*β
Ap 0.52
14.00
q Pcu = 0.316 25
= 1.29 N/mm
2
C21 (30*80)
1.5
q Pu = Qpu
*β
Ap 0.52
7.70
0.92
3.50
q Pcu = 0.316 25
= 1.29 N/mm
2
C26 (30*70)
1.5
q Pu = Qpu
*β
Ap 0.52
15.50
q Pcu = 0.316 25
= 1.29 N/mm
2
C30 (30*40)
1.5
q Pu = Qpu
*β
Ap 0.52
4.20
1.02
6.40
q Pcu = 0.316 25
= 1.29 N/mm
2
C31 (30*80)
1.5
q Pu = Qpu
*β
Ap 0.52
6.25
q Pcu = 0.316 25
= 1.29 N/mm
2
C32 (30*100)
1.5
q Pu = Qpu
*β
Ap 0.52
7.30
1.22
4.75
q Pcu = 0.316 25 2
= 1.29 N/mm C33 (30*100)
1.5
q Pu = Qpu
*β
Ap 0.52
17.00
Take t d = t s / 2 = 0.12 m
3.00
C33 (40*120)
0.71
d = 0.22+0.12-.03= 0.31 m
Qpu = 1.915* (17.00*4.75 – 0.71*1.51) = 152.58 ton
Ap = (2*0.71 + 2*1.51)*0.31 = 1.377 m 2
∴ q Pu = 1.377 * 1.15= 127.43 t/m = 1.27 N/mm 2 < q Pcu
152.58 2
(Safe)
Check punching :
2- Middle part : 125
q Pcu = 0.316 25
= 1.29 N/mm
2
C41,42 (30*40)
1.5
q Pu = Qpu
*β
Ap 0.64
5.95
1.24
3.40
q Pcu = 0.316 25
= 1.29 N/mm
2
C43,44 (40*100)
1.5
q Pu = Qpu
*β
Ap 0.64
7.70
q Pcu = 0.316 25
= 1.29 N/mm
2
C47,48 (30*40)
1.5
q Pu = Qpu
*β
Ap 0.54
7.50
0.74
3.30
q Pcu = 0.316 25
= 1.29 N/mm
2
C51,52 (30*50)
1.5
q Pu = Qpu
*β
Ap 0.54
7.50
q Pcu = 0.316 25
= 1.29 N/mm
2
C53,54 (30*40)
1.5
q Pu = Qpu
*β
Ap 0.54
7.50
0.64
4.40
q Pcu = 0.316 25
= 1.29 N/mm
2
C57,58 (30*40)
1.5
q Pu = Qpu
*β
Ap 0.54
7.40
q Pcu = 0.316 25
= 1.29 N/mm
2
C61,62 (40*120)
1.5
q Pu = Qpu
*β
Ap 0.54
11.70
q Pcu = 0.316 25 2
= 1.29 N/mm
0.42
1.5
C67 (30*40)
q Pu = Qpu
*β
0.52
Ap 2.40
q Pcu = 0.316 25
= 1.29 N/mm
2
0.64
1.5
C107 (30*40)
q Pu = Qpu
*β
0.54
Ap 1.90
0.74
5.50
q Pcu = 0.316 25
= 1.29 N/mm
2
C114
1.5 (30*50)
q Pu = Qpu
*β
Ap 0.54
3.90
∴ q Pu =
41.048 2
122.1 t/m = 1.221 N/mm < q Pcu
2
* 1.30= (Safe)
0.437
q Pcu = 0.316 25
= 1.29 N/mm
2
C113
1.5 (30*40)
q Pu = Qpu
*β
Ap 0.54
3.80
∴ q Pu =
39.34 2
123.8 t/m = 1.238 N/mm < q Pcu
2
* 1.30= (Safe)
0.413
132
C110 (Interior column) :
1.24
5.45
q Pcu = 0.316 25
= 1.29 N/mm
2
C110 (40*100)
1.5
q Pu = Qpu
*β
Ap 0.64
11.00
q Pcu = 0.316 25
= 1.29 N/mm
2
C118 (30*100)
1.5
q Pu = Qpu
*β
Ap 0.54
8.40
1.04
3.90
q Pcu = 0.316 25
= 1.29 N/mm
2
C119 (30*80)
1.5
q Pu = Qpu
*β
Ap 0.54
7.40
q Pcu = 0.316 25
= 1.29 N/mm
2
C122 (30*120)
1.5
q Pu = Qpu
*β
Ap 1.24
10.50
1.44
5.30
q Pcu = 0.316 25
= 1.29 N/mm
2
C127 (40*120)
1.5
q Pu = Qpu
*β
Ap 0.64
11.80
Take t d = t s / 2 = 0.12 m
3.00
C33 (40*120)
0.71
d = 0.26+0.12-.03= 0.35 m
Qpu = 2.020* (11.80*5.30 – 0.75*1.55) = 123.98 ton
Ap = (2*0.75 + 2*1.55)*0.35 = 1.61 m 2
∴ q Pu =
123.98 2
88.557 t/m = 0.89 N/mm < qPcu
2
* 1.15= (Safe)
1.61
135
C135 (Interior column) :
1.44
6.70
q Pcu = 0.316 25
= 1.29 N/mm
2
C135 (30*120)
1.5
q Pu = Qpu
*β
Ap 0.54
7.20
q Pcu = 0.316 25
= 1.29 N/mm
2
C136 (30*70)
1.5
q Pu = Qpu
*β
Ap 0.54
4.60
0.74
2.50
q Pcu = 0.316 25
= 1.29 N/mm
2
C137 (30*50)
1.5
q Pu = Qpu
*β
Ap 0.54
3.60
Data :
1- Area of footing :
Pw = 88 ton = 880 KN
AP.C = PW = 880 2 tp.c = 40 cm
= 4.4 m
qall 200 qall= 200 KN/m2
2
= Lp.c * Bp.c Fcu = 30 N/mm
2
C- Check shear :
q Scu = 0. 16 30
= 0.7155 N/mm
2
1.5
0.38
Z = 0.475 - = 0.285 m
2
Q SU = 782.22 * 0.285 = 222.93 KN
∴q u =
3
= 0.586 N/mm < q Scu (Safe)
222.93 * 10 2
380*1000
D- Check Punching :
q Pcu = 0. 316 30
= 1.414 N/mm
2
1.5
0.38
Z = 0.475 - = 0.285 m
2
Q SU = 1320 – 782.22 * (0.68 * 0.78 = 905.11 KN
∴qPu=
3
= 0.816 N/mm < q Pcu (Safe)
905.11 * 10 2
380*2*(680+780)
E- Check Punching :
A = 1.5 * 380 = 570 mm /m`
2
S Min
6
Use 7 12/m`
A = 88.240 * 10 2
= 780.91 mm / m` In both directions
S Req 360 * 0.826 * 380
140
B- Excel sheet for Design isolated footing C7 (30*40) :
F1 141
F2 142
F3 143
F4 144
F5 145
F6 146
Footings models :
F7 147
Footings models :
F8 148
Footings models :
F9 149
Footings models :
F 10 150
Design of footings at expansion joints :
151
Pw = 118.8 t Pw = 307.93 t
= 135.9 t F15
= 179.5 t
F12
Footings models :
F 11 153
Footings models :
F 12 154
Footings models :
F 13 155
Footings models :
F 14 156
Footings models :
F 15 157
Footings models :
F 16 158
159
7.50 m
7.50 m
7.50 m
B3 B3
B2 B1 & & B1 B2
B2 B2 7.50 m
30.00 m
161
Design of slabs :
34.31 KN.m
34.31 KN.m
1 1 2 28.59 KN.m
∴ As = 2 20 / rib ∴ As = 2 18 / rib
162
Slab at Upper level
2
∵ Area = 7.5 * 4.00 m ∴ Use One way Hollow blocks system . 1
Take Blocks = ( 200*400*250) & slab 7 cm
∴ S = e + b = 0.4 + 0.1 = 0.5m
6.10 KN/m`
4.00 ((m))
12.2 KN.m
∴ As = 2 12 / rib
Design of internal arch girder
163
Design of beams :
B1 : B2 :
6.10 6.1
∴W = 5.00 + 6.50 * 0.5 = 84.3 KN/m` ∴W = 5.00 + 3.25 * 0.5 = 44.65 KN/m`
∴Rint = 1.1 * 7.5 * 84.3 = 695.48 KN ∴Rext. = 1.1 * 7.5 * 44.65 = 368.36 KN
B3 :
1926.74 1926.74
Design of Arch girder :
164
4.00 m
2.73 m
14318.72 KN.m
∴ Mo = 14318.72 KN.m
P = T = 0.95 * 14318.72
4.00
= 3400.7 KN
M = 0.05 Mo = 715.94 KN.m
Take t = L/20-25 = 1.20 m
715.94 KN.m
-
3400.7 KN
1
+
3400.7 KN
2
Sec 1-1 (Design of Arch girder) : 165
Check
PU.L =
3400.7 *1000
= 0.2834 > 0.004 (Don`t neglect N)
FCU * b * t 25*400*1200
MU.L e 0.21
e = PU.L = 0.21 m ∴ = 1.20 = 0.175 < 0.5 ∴Use I.D
t
∴ =1.20 - 0.2
1.20 = 0.80 ∴Use I.D Eccs design Page (4-5)
3 3
PU.L* 10 3400.7 * 10
∴ Fcu = = 0.283
*b*t 25 * 400 * 1200 ∴ρ <1 ∴ Take ρ=1
6 6
3400.7 * 10
∴ FM U.L* 10
cu * b * t
2=
25 * 400 * 1200
2 = 0.0497
-4 -3
∴ μ = ρ * Fcu * 10 = 2.5 * 10
As = As` = μ * b * t = 1200 mm2 ∴ As Total = 2400 mm 2
As Min = 0.008 * b * t = 3840 mm 2 ∴ As = As` = 1920 mm2 = 6 22
∴ As = 22 25
P = 1926.74 KN
3.25 m
4.00 m
∴k = 2.20 ∴k = 1.20
∴ =1.00 – 0.1
1.00 = 0.90 ∴Use I.D Eccs design Page (4-4)
3 3
PU.L* 10 1926.74 * 10
∴ Fcu = = 0.1926
*b*t 25 * 400 * 1000 ∴ρ <1 ∴ Take ρ=1
6 6
3400.7 * 10
∴ FM U.L* 10
cu * b * t
2=
25 * 400 * 1000
2 = 0.0317
-4 -3
∴ μ = ρ * Fcu * 10 = 2.5 * 10
As = As` = μ * b * t = 1000 mm2 ∴ As Total = 2000 mm 2
As Min = (0.0025+ 0.00052*18.15) * b * t = 4775 mm2
∴ As = As` = 2387 mm2 =5 22
Design of footing :
167
Finternal
Design of External arch girder
168
Design of beams :
B1 : B2 :
6.10 6.1
∴W = 5.00 + 6.50 * 0.5 = 84.3 KN/m` ∴W = 5.00 + 3.25 * 0.5 = 44.65 KN/m`
∴Rint = 0.45 * 7.5 * 84.3 = 284.50 KN ∴Rext. = 0.45 * 7.5 * 44.65 = 150.70 KN
B3 :
937.13 937.13
Design of Arch girder :
169
4.00 m
2.73 m
6954.74 KN.m
∴ Mo = 6954.74 KN.m
P = T = 0.95 * 6954.74
4.00
= 1651.75 KN
M = 0.05 Mo = 347.74 KN.m
Take t = L/20-25 = 1.20 m
347.74 KN.m
-
1651.75 KN
1
+
1651.75 KN
2
Sec 1-1 (Design of Arch girder) : 170
Check
PU.L =
1651.75 *1000
= 0.1376 > 0.004 (Don`t neglect N)
FCU * b * t 25*400*1200
MU.L e 0.21
e = PU.L = 0.21 m ∴ = 1.20 = 0.175 < 0.5 ∴Use I.D
t
∴ =1.20 - 0.2
1.20 = 0.80 ∴Use I.D Eccs design Page (4-5)
3 3
PU.L* 10 1651.75 * 10
∴ Fcu = = 0.1376
*b*t 25 * 400 * 1200 ∴ρ <1 ∴ Take ρ=1
6 6
347.74 * 10
∴ FM U.L* 10
cu * b * t
2= = 0.02415
25 * 400 * 1200 2
-4 -3
∴ μ = ρ * Fcu * 10 = 2.5 * 10
As = As` = μ * b * t = 1200 mm2 ∴ As Total = 2400 mm 2
As Min = 0.008 * b * t = 3840 mm 2 ∴ As = As` = 1920 mm2 = 6 22
∴ As = 12 25
P = 937.13 KN
3.25 m
4.00 m
∴k = 2.20 ∴k = 1.20
∴ =1.00 – 0.1
1.00 = 0.90 ∴Use I.D Eccs design Page (4-4)
3 3
PU.L* 10 937.13 * 10
∴ Fcu = = 0.0937
*b*t 25 * 400 * 1000 ∴ρ <1 ∴ Take ρ=1
6 6
154.34 * 10
∴ FM U.L* 10
cu * b * t
2=
25 * 400 * 1000
2 = 0.0154
-4 -3
∴ μ = ρ * Fcu * 10 = 2.5 * 10
As = As` = μ * b * t = 1000 mm2 ∴ As Total = 2000 mm 2
As Min = (0.0025+ 0.00052*18.15) * b * t = 4775 mm2
∴ As = As` = 2387 mm2 =5 22
Design of footing :
172
FExternal