Sunteți pe pagina 1din 51

Role of Electricity Regulatory

Commissions

By
S C Shrivastava
Joint Chief (Engg)

Central Electricity Regulatory


Commission
In this presentation…
• Overview
• Legal/Policy framework
• Regulatory framework
• Regulatory scope/activities
• Market Development - CERC
initiatives & impact

06/15/19 CERC 2
OVERVIEW
06/15/19 CERC 3
Sectoral Parameters
Unelectrified rural households (2001 77.8 million
Census) (57%)
Power Supply Position during July
2010
- Energy shortages 8.3%
- Peaking deficit 12.1%

Generating plants – PLF (2009-10) All 77.53%


India
Generation performance (2009-10) 771 BUs
(7.0 % growth over
corresponding period of
previous year)

Cumulative High Voltage Transmission 2,26,458 ckt km


links (220 KV and above) (upto April
2010)

06/15/19 CERC 4
Installed Generation Capacity in India
(as on 31.01.2011)

06/15/19 CERC 5
Installed Renewable Generation Capacity in India
(end December’10)

06/15/19 CERC 6
6
Power Infrastructure in India
(as on 31.01.2011)

06/15/19 CERC 7
Ownership Status of Transmission
and Distribution
• Almost 100% of Electricity Transmission
in India is owned by public sector.
• About 13 % of Electricity Distribution in
India is owned by private sector.

06/15/19 CERC 8
Electricity Requirement 2031 - 32

GDP Growth Rate


8% 9%
Total Energy Requirement 3880 4806
Billion kWh
Energy Requirement at Bus Bar 3628 4493
Projected Peak Demand (GW) 592 733
Installed Capacity Requirement (GW) 778 960
Source: Integrated Energy Policy

06/15/19 CERC 9
LEGAL/POLICY
FRAMEWORK
06/15/19 CERC 10
Basic Legal Framework
• Electricity – a concurrent subject as per

Constitution of India.

• Both Centre and States can legislate.

• In case of repugnancy, Central

legislation prevails.

06/15/19 CERC 11
Legal Framework under old laws
• Regulatory authorities under IE Act, 1910 and E(S)
Act, 1948
• Central Government
• State Government
• CEA
• SEB
• Central Government – Powers to fix capital ceiling
for TEC clearance etc.
• State Government – Powers to grant licence etc.
• CEA – TEC of generation projects, technical norms
etc.
• SEB – Several powers as main advisor of State
Govt.

06/15/19 CERC 12
Legal Framework Contd…

• Regulatory authorities under ERC Act,


1998
• CERC
• SERCs
• JERC

• Objective – distancing of Govt./Govt.


organization from regulation.

06/15/19 CERC 13
Legal Framework – Electricity Act, 2003
• Consolidates laws of electricity relating to generation,

transmission, distribution and trading of electricity.

• Creates environment conducive for development of

electricity industry.

• Introduction of competition.

• Constitution of Central and State Regulatory

Commissions to rationalize electricity tariffs.

06/15/19 CERC 14
Electricity Act 2003 -Key Features

• Open Access to Transmission /Distribution Systems

• De-licensing of power generation

• Trading in electricity permitted

• Liberal provisions for captive power generation

• Rural generation and distribution freed from licensing

• Expanded role for the Regulatory Commissions

• Envisages unbundling of transmission and distribution.

• Regulatory Commissions to develop electricity markets.

06/15/19 CERC 15
The Electricity Act, 2003……
• Clear demarcation of role and responsibility of

• Government (policy making)

• Independent Regulatory Commission (powers of

regulation)

• Other statutory bodies – like Central Electricity

Authority (as expert body on technical matters)

06/15/19 CERC 16
Government
• Formulation of

– National Electricity Policy

– Tariff Policy

– National Electricity Policies on rural electrification.

• Powers to issue directions to the Regulatory

Commissions on issues involving public

interest.

06/15/19 CERC 17
National Electricity Policy
• Total village electrification by year 2010

By year 2012 :

• Per capita availability 1000 units.

• Installed capacity over 200,000 MW.

• Spinning reserves 5% .

• Minimum lifeline consumption of 1 unit per household per


day.

• Inter-regional transmission capacity 37,000 MW.

• Energy efficiency/ conservation savings about 15%.

06/15/19 CERC 18
Tariff Policy
• Mandates competitive procurement of power and transmission
services – transitional window of 5 years period given to public
sector companies.

• Encourage efficiency in operations by sharing of gains between


licensees and consumers.

• Promote Multi-Year Tariff (MYT) framework.

• Encourage loss reduction Strategies.

• Tariff design : Linkage of tariffs to cost of service

• gradual reduction in cross subsidy (+/- 20% of average cost of


supply)

• Progressive reduction in Cross-subsidy surcharge for open access.

06/15/19 CERC 19
REGULATORY FRAMEWORK
06/15/19 CERC 20
Regulatory Commissions
• At the Center – CERC
• Powers to regulate centrally owned generating companies
and companies having composite scheme for generation and
sale of electricity in more than one State.

• To regulate inter-State transmission/Trading.

• In the States – SERCs


• Powers to regulate intra-State generation, transmission and
distribution.

– CERC vis a vis SERCs

• No hierarchical relationship. However, SERCs are to be


guided by the principles of tariff determination specified by
06/15/19 CERC. CERC 21
Functions of CERC
• to regulate the tariff of inter-state generating companies

• to regulate the inter-State transmission of electricity

• to determine tariff for inter-State transmission of electricity

• to issue licenses for inter state electricity transmission and


trading.

• to adjudicate upon inter-State disputes

• to specify Grid Code

• to specify and enforce the standards with respect to quality,


continuity and reliability of service

• to fix the trading margin

06/15/19 CERC 22
Functions of CERC…
• Advisory Functions:
– formulation of National electricity Policy and tariff policy;

– promotion of competition, efficiency and economy in the activities of


the electricity industry;

– promotion of investment in electricity industry;

– any other matter referred to the Central Commission by the Central


Government

06/15/19 CERC 23
Functions of SERCs
• determine the tariff for generation, supply, transmission and wheeling
of electricity, wholesale, bulk or retail within the State

• regulate electricity purchase and procurement process of distribution


licensees

• facilitate intra-State transmission and wheeling of electricity

• issue licences for intra state transmission, distribution and trading.

• promote co-generation and generation of electricity from renewable


sources of energy

• adjudicate upon the intra-state disputes

• specify or enforce standards with respect to quality, continuity and


reliability of service by licensees;

• fix the trading margin in the intra-State trading of electricity

06/15/19 CERC 24
06/15/19
Functions of SERCs…
• Advisory Functions:
– promotion of competition, efficiency and economy in
activities of the electricity industry;

– promotion of investment in electricity industry;

– reorganization and restructuring of electricity industry in


the State;

– matters concerning generation, transmission ,


distribution and trading of electricity or any other matter
referred to the State Commission by that Government.

06/15/19 CERC 25
06/15/19
Mission Statement-CERC
• The Commission promotes competition, efficiency and economy in

power markets, protects the interests of consumers and promotes

investments in power sector. In pursuit of these objectives the

Commission aims to –
• Formulate an efficient tariff setting mechanism which ensures economy and

efficiency in the pricing of bulk power and transmission services and leads to

least cost investments,

• Promote development of power market by creating a market structure, facilitating

open access in inter-State transmission, facilitating interstate trading,

• Improve the operations and management of the inter-State transmission systems

through Indian Electricity Grid Code (IEGC), Availability Based Tariff (ABT),

06/15/19 CERC 26
Regulatory Commission - a quasi judicial body

• Powers of Civil Court for the purposes of

inquiry or proceedings under the Act.

(Section 94)

• Powers to impose penalty for non-

compliance of direction of Regulatory

Commissions.

• Powers to adjudicate

06/15/19 CERC 27
Accountability of Regulators

• Annual Report to be laid before the Parliament.

• Accounts of Regulatory Commissions to be

audited by CAG.

• Appeal against the orders of Regulatory

Commissions to lie before the Appellate

Tribunal.

06/15/19 CERC 28
Procedure for Regulations

06/15/19 CERC 29
PROCEDURE FOR PETITIONS

PETITIONER RESPONDANTS

ARGUMENTS

Appeal in
REVIEW
ORDERS Appellate
PROCEEDINGS
Tribunal

06/15/19 CERC 30
Appellate Tribunal
• Constitution of Appellate Tribunal consisting of Chairman,
three Members (Technical and Judicial) and one Member with
specialization in Petroleum Sector.

• Appellate Tribunal to hear appeals against the orders of


CERC/SERC/PNGRB.

• The appeal to Appellate Tribunal should be filed within 45


days of order issued by CERC/SERC/PNGRB.

• Appeal against the orders of Appellate Tribunal to lie before


the Supreme Court within 65 days.

• Appellate Tribunal considered necessary to-

• Reduce litigation and delay in decisions through High Court.

• Provide technical expertise in decision on appeals.


06/15/19 CERC 31
REGULATORY
SCOPE/ACTIVITIES
06/15/19 CERC 32
Generation
• No requirement of licence.

• Full freedom to captive generation.

• For hydro-generation clearance of CEA is necessary


due to concern of dam safety and inter-State issues.

• Generation from Non-Conventional Sources / Co-


generation to be promoted. Minimum percentage of
purchase of power from renewables may be prescribed
by Regulatory Commissions.

06/15/19 CERC 33
Transmission
• Transmission Utility at the Center and in the States to
undertake planning/development of transmission
system.

• Regional Load Despatch Centers to ensure integrated


operation of the power system.

• Flexibility regarding keeping Transmission Utility and


load despatch together or separating them.

• The Load Despatch Centre/ Transmission


Utility/Transmission Licensee not to trade in power.

06/15/19 CERC 34
Trading/ Market development
• Trading distinct activity permitted with licensing.

• Regulatory Commission to specify technical

requirement, capital adequacy requirement and credit

worthiness for a trader.

• Regulatory Commission may fix ceiling on trading

margin to avoid artificial price volatility.

• The Regulatory Commission to promote development

of market including trading.

06/15/19 CERC 35
Tariff
• Regulatory Commissions to determine tariff for

– Supply by Generating Company to distribution licensee

through long term contract. For short term contracts only

minimum and maximum ceiling of tariff.

– Transmission of electricity.

– Wheeling of electricity

– Retail sale to consumers by Licensee.

06/15/19 CERC 36
MARKET DEVELOPMENT
- CERC INITIATIVES & IMPACT
06/15/19 CERC 37
Market Development - CERC initiatives
• Regulations on

• Short-term Open Access

• Grant of Connectivity, Long-term Access and Medium-

term Open Access in inter-State Transmission.

• Grant of Regulatory Approval for execution of Inter-State

Transmission Scheme to CTU

• Transmission Pricing

• Power Market

06/15/19 CERC 38
CERC initiatives…
• Special Features of CERC regulations on short-term open
access

• Timelines for concurrence of SLDC in case use of intra-


State system is involved

• Provision of deemed concurrence if SLDC does not


decide within above timelines.

• SLDC to look at only two aspects:

• existence of metering infrastructure, and

• availability of surplus transmission capacity in the


State network.

06/15/19 CERC 39
CERC initiatives…
• Features of CERC regulations on Grant of Connectivity,
Long-term Access and Medium-term Open Access in inter-
State Transmission
• Enabling transmission products of different varieties, standardization of
procedures, defining time lines and ensuring level playing field among
different categories of market players.

• Introduced medium-term Open Access to inter-State grid - for a period


ranging from 3 months to 3 years.

• New regulatory provisions for seeking connectivity to grid.

• Discrimination between public and private sector generators on


connectivity to grid, abolished.

06/15/19 CERC 40
CERC initiatives…
• Regulations on Grant of Regulatory Approval for execution
of Inter-State Transmission Scheme to Central
Transmission Utility

• This is to facilitate network expansion keeping in view


the anticipated transmission needs without the
requirement of prior agreement with the beneficiaries

• CERC has granted approval for investment (of about Rs.


58000 Cr. ) to CTU for nine high capacity transmission
corridors.

06/15/19 CERC 41
CERC initiatives…
• Regulations on Sharing of Inter State Transmission
Charges and Losses

• National transmission tariff framework – in line with


vision of tariff policy.

• Sensitive to direction, distance and quantum;

• Addresses short-comings of existing system – like


pan-caking of charges, sharing of charges not being
fully sensitive to distance and direction, pricing not
efficient enough to address emerging market
requirements.
06/15/19 CERC 42
CERC initiatives…
• Power Market Regulations

• Provide a road map for development of power


market

• Define roles of various players in the market


and phases of introduction of
products/contracts.

06/15/19 CERC 43
Market Development- Impact
Volume of Open Access transactions
(inter-State transmission)

Source: NLDC
06/15/19 CERC 44
Market Development- Impact…
Consumer Open Access through Power Exchange - A
Snapshot
Details Indian Energy Exchange Ltd
Total Clients 300
Open Access Consumers 160
Nature of Business of these Industrial Consumers- Textiles,
Consumers Spinning mills, Auto Ancillary
Geographical Location of Punjab, Rajasthan , Tamil Nadu,
these Consumers Andhra Pradesh

% of Daily Cleared Volume by 25-30 % ( 5-7 MU) of total daily


OA consumers during Oct cleared volume of Power Exchange
2009 – Feb 2010
Nature of purchase Peak , Off Peak

06/15/19 CERC 45
Market Development- Impact…
• Investment promotion:
– CTU has received 225 applications from private
developers for Long Term Open Access amounting to
1,62,898 MW
• Phase 1: 42,108 MW (LTOA granted to 43 applicants )
– Bank guarantee of 875 Cr given by developers and
BPTA signed
– Geographical locations
• Pit-head coal Orissa, Chhattisgarh, Jharkhand
• Coastal with port facilities - Andhra Pradesh, Tamil
Nadu
• Hydel sites – Sikkim

06/15/19 CERC 46
Grid discipline - IEGC
• IEGC and UI regulations amended to ensure greater grid
discipline .
• Operational frequency band tightened from ‘50.3 Hz
to 49.2 Hz’ to ‘50.2 to 49.5 Hz’.
• This is aimed at ensuring better performance of
generating stations and user appliances.
• All users of inter-State grid including distribution
utilities will also now be directly responsible for grid
discipline and load management, in addition to
SLDCs.

06/15/19 CERC 47
Grid Discipline - Restructured UI mechanism
• UI regulations amended to send a message that UI mechanism should not be
used as a trading tool

• Underdrawls and over injections beyond the permissible quantities,


disincentivised and priced at lower rates

• in order to push more electricity to organized electricity markets and

• to further discourage use of UI mechanism for sale of electricity,

• Additional UI charge of 40% on the normal UI rate (Rs. 8.73 per unit),
applicable at grid frequency below 49.5 Hz instead of 49.2 Hz
• to more effectively curb the tendency of some states to heavily
overdraw
• Additional UI rate has been made 100% on overdrawals when grid
frequency is below 49.2 Hz
• to put further exemplary deterrent on overdrawls
• Improvements in grid frequency profile subsequent to CERC regulation on IEGC
and UI

06/15/19 CERC 48
Improvement in Grid profile

06/15/19 CERC 49
Grid discipline - constraints

• Disconnection almost impossible in meshed system

• Centre-State issues
• J&K defaulting in UI payments, difficulties in
disconnection.

06/15/19 CERC 50
Thank You
www.cercind.gov.in

S-ar putea să vă placă și