Documente Academic
Documente Profesional
Documente Cultură
SEWAGE DISPOSAL
AND TREATMENT
1
Lecture One
INTRODUCTION TO BASICS of
WASTEWATER, SANITATION and
DRAINAGE
Introduction
The standards for the removal of nitrogen and phosphorus (N,P) are not
included in this table because (N) and (P) need tertiary treatment.
The Network
Network
•Water collection
•collection •Collection
•Water treatment • treatment •Disposal
•Water distribution •Treatment
•Reuse
Types of collection systems
• Separate system
Used for domestic and industrial wastes in addition to inflow and infiltration. Storm
water is not considered.
It is preferred for the following:
• The size of pipes is much smaller than the combined system sewers. This gives the
advantage of good hydraulics in the pipe (the pipe is Designed to have a minimum
velocity to prevent sedimentation of sand)
Types of collection systems
Separate system
• Separation of wastewater from storm water minimize the total quantity of sewage
which has the following advantages :
1. Smaller pumping stations are needed.
2. Smaller and more efficient treatment plants are needed.
3. Overflow of combined sewers in the storm events produces pollution to
environment which is not the case in separate sewer.
• Only unavoidable Storm water inters the system which protects the system from the
accumulation of sand in the sewers in the non-paved areas.
Types of collection systems
Combined system Both sanitary & storm water
• It is used for both storm water and wastewater.
• It is preferred for the following cases:
• For areas of long rainy seasons.
• For areas where it is difficult to construct two pipelines in the streets crowded with other
services (electricity, telephone, gas, etc...).
• It’s not preferred for areas of short rainy season, and for areas poorly paved which leads to
the accumulation of sand in the system.
• Combined system is 40% lower in cost than separate system
Ways for transmission of sewage
• By gravity: Used always wherever possible
• By pressure: It's use is limited for areas
which can’t be served by gravity
• By vacuum
Preliminary studies for the design
of sewage collection systems
vi. Detailed cross section for the streets showing the underground service (water
pipes, electricity cables, gas pipes, telephone,…..).
vii. Water supply and consumption study.
viii. Identification of industrial, commercial institutional and domestic areas.
ix. Identification of collection points of sewage and possible locations of
pumping stations and point of final collection.
x. Population forecast studies.
xi. Expected Development of the area (Master planning).
QUANTITY OF WASTEWATER
• Water uses,
• Climate,
• Lifestyle,
• Economics, etc.
Surface and Subsurface drainage
• Surface drainage: canal, channel
Components
Storm water
Storm water
Storm water
Storm water
Storm water
Lecture Three
Design Layout
and Construction
of Sewers
Basic design concepts
What is Design?
• An engineering design process is a process used by engineers to help develop
products. the engineering design is defined as
• the process of devising a system, component or process to meet desired
needs. It is a decision-making process (often iterative), in which the basic
sciences, mathematics, and engineering sciences are applied to convert
resources optimally to meet a stated objective. Among the fundamental
elements of the design process are the establishment of objectives and
criteria, synthesis, analysis, construction, testing, and evaluation.
Wastewater
Wastewater Infrastructure
Unit Operations/Processes
• Suspended solids: Screening, grit removal, sedimentation
• Biodegradable organics: Anaerobic and anaerobic treatments, chemical
oxidation, membrane filtration
• Nitrogen: Biological nitrogen removal, air stripping, ion exchange
• Phosphorus: Biological nitrogen removal, chemical treatment
• Pathogens: Chlorination, ozonation, UV
• VOCs: Air stripping, carbon adsoption
Determination of design flow
Diurnal Variation in Flow
Daily Variation in Flow
Variation in Loadings
Estimating Waste Conc
Estimating Flow Rate
1. The existing base flow
2. Estimated future flows for residential, commercial, institutional, and
industrial sources
3. Non excessive infiltration/inflow
Selection for Design
Design criteria:
• The season (monthly variations)
• Weather conditions
• Week of the month , day of the week, time of the day.
• Average daily water consumption per capita for domestic areas (L/c/d),
(Qavg).Average daily water consumption per capita for institution ( school, offices,
….etc. ), (Qavg).Average daily water consumption for commercial and industrial
areas.
Design criteria
• Qinfil is taken as [24-95 m3/day/km] or [0.5 m3/day/diamwter (cm)],
• Qinflo is taken as 0.2-30 [m3/ha/day]. ( hectare = 10,000 m2)
• take the bigger value of two
• Qdes= Qmax+ QI/I( if found)
• QI/I= Qinfil+ Qinflo
• Qmax= [0.80* Qavg] * Pƒ
Design criteria
• The minimum domestic wastewater flow (Qmin) is necessary to check for
the minimum velocity in the sanitary sewers, it is estimated from the
following formula:
A typical value of
[Qavg]w = 0.8 Qavg
Collection Mains
Collection Mains
• Gravity Flow: The wastewater collection system shall be designed for gravity
(open) flow conditions, using a “Mannings” roughness coefficient of 0.013
to account for various pipe materials and joints, service connections, and
future interior pipe conditions.
Collection Mains
• Peak Flow Depth: Collection mains shall normally be designed to carry the
peak flow with a flow depth of one-half of the full pipe.
• Pressurized Flow Prohibited: Pressurized surcharged or depressed
(inverted siphon) wastewater mains are prohibited in the City's wastewater
collection system.
Collection Mains
• Minimum Diameter: Collection mains shall be a minimum eight (8) inches
in diameter. (200mm)
• Size Changes: All changes in pipe size shall require a manhole at the size
change.
• Easements: All wastewater mains shall be installed in public rights-of-way
or easements, as prescribed under urban regulation.
• Lot Frontage: All platted lots, whether existing or proposed as part of a
subdivision, shall front on a collection main.
Collection Mains
• Minimum and Maximum Cover:
• All collection mains shall have a minimum depth of cover of three (3) feet,
(90cm) and a maximum depth of cover of eighteen (18) feet (540cm) feet,
measured from the top of pipe to the final surface grade.
Collection Mains
• Shallow Cover Protection:
• Where collection main depths are less than four (4 feet) (120cm), and the
main is located under a right-of-way, street, driveway, parking lot, or other
areas where live loading is a concern, special pipe materials (such as ductile
iron pipe) or other structural measures (such as concrete encasement) shall
be provided.
Collection Mains
Provision for Basements:
• Proposed collection mains shall be designed with adequate depth to provide
wastewater service to basements, where possible and appropriate.
Slope
Slope Changes: All changes in slope shall require a manhole at the slope change
connection.
4.Delivery Pipe.
• Electricity supply companies wish to limit the number of times the relatively high
start-up power is required;
• The overheating of motors must be prevented.
• For these reasons the number of starts per hour must be limited to 3-4 times for large
pumps and 6-8 times for small pumps.
The sump capacity
Determination of the wet well active volume
• The active volume in the wet well is the volume enclosed between the LWL
and the HWL.
• This volume depends on many factors such as the number of pumps, the
capacity of each pump and the raw WW influent flow rate.
• The active volume (V ) when one pump is in operation is calculated from the
following equation:
Where:
T: minimum cycle time between pump starts, min.
q : the pumping rate of a single pump in operation, m3/min
V: active volume for one pump in operation, m3
Determination of the wet well active
volume
• Example:
• What is the active volume of a wet well that has 5 pumps working in parallel plus one
standby pump. The capacity of one pump when operating alone is 12m3/min. Take T
as 8 minutes. The area of the horizontal cross section of the wet well is 12 m2 .
Solution
• The cycle time T depends on the pump type and the manufacturer recommendations.
• Typical value of T 6 minutes. This will lead to 10 starts of the pump in 1 hour
• If more than a pump is used, an additional 15 cm is added to the height of the wet
well for each pump other than the first.
Solution
• V = (14.7*6)/4 = 22.05 m3
hm = minor losses, m
g = gravitational acceleration, m/s2
V = liquid velocity, m/s
K = minor losses coefficient
Values of “ K” are given in hydraulic references. For example:
K = 0.1 – 0.40 gate valve
= 0.30 for 45o bend
Power output of pumps
ηp = pump efficiency
Pp = pump output power, Watt
Pi = input power to the pump, Watt
Pump motor Efficiency
Where:
D = pipe diameter (variable) according to the # of pumps in operation, m
Q = discharge (variable) according to the # of pumps in operation, m3/d
V = flow velocity (variable) according to the # of pumps in operation, m/s
The velocity in the manifold is usually assumed in the range of 1 to 2 m/s.
Design of the main Pressure line
• The main pressure line is the pipe that connects the manifold with ponit of
disposal. Its diameter is determined using the Continuity equation:
The velocity at peak flow in the main pressure line is usually assumed in the range of 1 to 2 m/s.
However the velocity when one pump in operation should not be less than 0.60 m/s.
Design of the main Pressure line
• Selecting the most economical diameter for the main pressure line
Homework -1I-
Lecture Seven
Wastewater
treatment I
Outline
• Wastewater treatment methods
• Classification of wastewater treatment methods
• Design of wastewater treatment systems,
• Design of Sedimentation tank,
• Waste Stabilization Pond,
Wastewater treatment methods
Ac = Qd / Va
Qd = design flow, m3/s
Ac = bar screen cross section, m2
Va = Velocity in the approach channel, m/s
Usually, rectangular channels are used, and the ratio between depth and width is taken as 1.5 to
give the most efficient section.
Head-loss
• Hl = head loss
• Va = approach velocity, m/s
• Vb = Velocity through the openings, m/s
• g = acceleration due to gravity, m/s2
Example
• A manual bar screen is to be used in an approach channel with a maximum
velocity of 0.64 m/s, and a design flow of 300 L/s. the bars are 10 mm thick
and openings are 3 cm wide. Determine:
a) The cross section of the channel, and the dimension needed
b) The velocity between bars
c) The head loss in meters
d) The number of bars in the screen
Solution
a) Ac= Qd/Va= 0.3/0.64 = 0.47 m2
• Ac= W x1.5W =1.5 W x W
• W = 0.56 m, Depth (d) = 1.5 W = 0.84 m
b) From continuity equation: Va Ac= Vb Anet
• Anet= 0.84 x 0.56 (3/3+1) = 0.35 m2
• Anet=Ac(Sc/(Sc+tbar) = 84 x (56(3/(3+1))) = 0.35m2
• Vb= 0.64 x 0.56 x 0.84/0.35 = 0.86 m/s < 0.9 m/s ok
Solution
c) Head-loss
= 0.024m
d) n tbar + (n-1)Sc = W
= n x 1 + (n-1) x 3= 56 n= 14.75 = 15
Design of rectangular Grit removal channel
• Settling theory
Example
• A suspension contains particles of grit with a diameter of 0.2 mm and
specific gravity of 2.65. For particles of this size CD= 10, f= 0.03, and b=
0.06. The suspension also contains organic solids of same size for which the
specific gravity is 1.10 and band f are unchanged. Determine the settling
velocity of the grit and the scour velocity of grit and organic material.
Solution
• Settling velocity of particles
Wastewater treatment I
Biological Treatment
Ponds
Introduction
•Primary treatment
•Secondary treatment
•Advanced treatment (tertiary
treatment )
•Sludge treatment
•Physical treatment
•Biological treatment
•Chemical treatment
•Incineration
Waste Stabilization Ponds (WSP) system
• Primary Treatment
• Series of ponds
• Anaerobic pond
• Facultative pond
• Maturation pond ( one or more )
depend on the effluent quality
Stabilization Ponds
• Ponds are probably one of nature's most economical ways of treating sewage and
producing a highly purified effluent (end product.)
• The degree of treatment provided by ponds depends upon the type and number of
ponds used.
• Ponds can be used as the sole type of water treatment or can be used in conjunction
with other forms of wastewater treatment.
Stabilization Ponds
• Advantages and Disadvantages
• Ponds, oxygen is transferred directly into the water across the surface area without
the need for any equipment.
• The natural method of aeration used by a sewage pond takes much longer than an
aerator does to add oxygen to the water. As a result, ponds treat sewage much
more slowly than package plants do.
Stabilization Ponds
•Sewage ponds are very simple to construct.
•However, the pond and surrounding area must be planned in such a
way that the human and natural environments surrounding the pond
are not damaged.
Requirements
• Embankments
• The soil in which a pond is built must be impermeable
• A pond must be completely fenced to keep unwanted visitors out
• Tree growth must be restricted (root may damage the embankment)
• Sewage ponds must be encircled by a windbreak, which usually consists of a row of
pine trees.
• The windbreak will prevent the pond's odors from disturbing the nearby residents
and will also make the area aesthetically pleasing.
Requirements (Depth)
• The pond must be greater than 60cm deep at all parts to exclude
plant growth.
• Plants growing at the edge of a pond will create areas of still water in
which mosquitoes will lay their eggs.
• But at depths of over 1.8m, anaerobic conditions occur, so regulations
stipulate that the depth of a sewage pond can be no more than 1.5m.
Typical depths
• Typical pond depths are: ~3 m for
anaerobic ponds;
• ~1.5 m for facultative ponds; and
• ~1 m for maturation ponds.
Health of the Surrounding Environment
• One way of protecting the surrounding environment is by adding a finishing
pond.
• A finishing pond , also known as a polishing pond
• The finishing pond is installed between the sewage pond and the stream as shown
below.
Stabilization pond at Kaliti
Green Pond
• Facultative and maturation ponds are usually a deep
green colour (and, if they are not, then something s
likely to be wrong).
• The green colour is due to the profuse growth of
micro-algae in the pond.
Treatment Process
•Micro-algae as they are the work
horses of facultative and maturation
ponds.
•two broad groups:
•The motile and
•The non-motile algae.
Treatment Process
• Motile algae have one or more tails called flagella which enable them to
move. So, in the fairly turbid waters of facultative ponds this gives them an
advantage over non-motile forms and so they tend to predominate in these
ponds.
• But as you move down a series of maturation ponds, the water becomes less
and less turbid and you find more and more non-motile algae and fewer
motile ones.
Lecture Nine
Wastewater
treatment I
Pond Design
Anaerobic Pond
• These ponds have such a high organic loading,
or BOD loading, that they do not contain any
dissolved oxygen.
• They are usually quite deep, often 2- 4 m deep.
• And they contain no, or very few, algae,
although
Anaerobic Pond
Design Of Anaerobic Pond
Design Of Anaerobic Pond
Odour
• It’s mainly caused by H2S, and this comes from the reduction of sulphates
by the obligately anaerobic sulphate-reducing bacteria, such as Desulfovibrio
spp.
• These bacteria reduce sulphates to sulphides, and in aqueous solution
sulphides are present as a mixture of dissolved H2S gas molecules,
bisulphide ions HS , and sulphide ions S2 ; and the proportion of these three
forms depends on the pH
Odour
Odour
• WW do not have an odour problem if the sulphate concentration in the raw
wastewater was less than 500mg SO4/l.
• This is quite high, especially as the maximum concentration permitted in drinking
water is 250 mg SO4/l.
• Of course, the sulphate concentration in wastewater is higher than in drinking water
as detergents, for example, can contain up to 40% by weight of sodium sulphate.
• Control should not normally be necessary but, if it is required, you can add lime or
soda ash to keep the pH above 7.
Anaerobic pond lined with an impermeable
plastic membrane
Inlet structure for anaerobic and primary
facultative ponds
Inlet structure for secondary facultative and
maturation ponds
Outlet weir structure
Lecture Ten
Wastewater
treatment I
Pond Design
Facultative Ponds
• Primary facultative pond for fac. ponds that receive raw wastewater, after screen
and grit removal
• Secondary facultative pond for those receiving the effluent from an anaerobic
pond or other settling device such as septic tanks, or the solids interceptor tanks used
in settled sewerage.
Facultative Ponds
The McGarry and Pescod
equation
lS = 60(1.099)T
• where the units are now kg per ha per day and °C.
Maturation Ponds
We normally design
maturation ponds for
E. coli removal, although of
course we
might in any one case want
to design them
for something else nitrogen
removal, for
instance.