Documente Academic
Documente Profesional
Documente Cultură
5
6
7
8
9
10
11
12
13
NORMAL CURVE
(TORNADO DIAGRAM)
TIME
C
O
S
T
NORMAL CURVE
TIME
C
MATERIALS
O
EQUIPMENT
S MANPOWER
T
NORMAL CURVE
Brief History of PERT/CPM networking
A B D F G
0 10 30
10 20 10 20 10
C E
20 10
Forward Pass
Drawing the PERT/CPM Network
Compute the longest time path through the network. This is
called the critical path.
A B D F G
0 10 30 40 60
20 70
10 20 10 20 10
30 Slack Time
“Float”
C E
20 20 10
Merge Point
Drawing the PERT/CPM Network
Compute the longest time path through the network. This is
called the critical path.
0 10 30 40 60
20 70
10 20 10 20 10
C E
20 20 10
Drawing the PERT/CPM Network
Compute the longest time path through the network. This is
called the critical path.
Late Finish
A B D F G
0 0 10 10 30 30 40 40 60 60
20 70 70
10 20 10 20 10
C E
30 20 20 50 10
A B D F G
0 0 10 10 30 30 40 40 60 60
20 70 70
10 20 10 20 10
C E
20 20 50 10
CRITICAL PATH
Drawing the PERT/CPM Network
Compute the longest time path through the network. This is
called the critical path.
A B D F G
0 0 10 10 30 30 40 40 60 60
20 70 70
10 20 10 20 10
C E
20 20 50 10 CRITICAL PATH
Drawing the PERT/CPM Network
PREPARE A DRAFT BY DRAWING A TIME-SCALED DIAGRAM
(using the CRITICAL PATH as reference)
A B D F G
10 20 10 20 10
OFFICE
20 10
C E
Drawing the PERT/CPM Network
A B D F G
0 0 10 10 30 30 40 40 60 60 70 70
10 20 10 20 10
C E
20 20 50 10 CRITICAL PATH
48
The Key Concept used by PERT/CPM is that a
small set of activities, which make up the longest
path through the activity network control the
entire project. If these "critical" activities could
be identified and assigned to responsible
persons, management resources could be
optimally used by concentrating on the few
activities which determine the fate of the entire
project.
59
60
61
62
Activity Relationships
• Conventional
• Start to Start
• Finish to Finish
• Start to Finish
• Finish to Start Positive
• Finish to Start Negative
63
FINISH TO FINISH in the PDM Diagram
64
Determine the Early Finish (EF) and LF in
the PDM Diagram
65
Determine the Early Finish (EF) and LF in
the PDM Diagram
66
Determine the Early Finish (EF) and LF in
the PDM Diagram
67
Determine the Early Finish (EF) and LF in
the PDM Diagram
68
START TO START
in the PDM Diagram with Lag
69
START TO START in the PDM Diagram
70
START TO FINISH
in the PDM Diagram with LAG
71
START TO FINISH in the PDM Diagram
72
START TO FINISH
in the PDM Diagram with LAG
73
START TO FINISH
in the PDM Diagram with LAG
74
75
76
Purchase Materials
CONSTRUCTING
Hire Workers
A
Excavate Foundation
SHED
Layout Foundation
Cure Cement Foundation
Purchase Lot
Select Design
Assemble/construct Shed
Purchase Paint
78
79
80
Total Float
Total float is the amount of time an
activity can be delayed without delaying
the project completion date. On a critical
path, the total float is zero
Total float is often known as the slack.
calculate the total float by subtracting
the Early Start date of an activity from its
Late Start date (LS – ES)
or Early Finish date from its Late Finish
date (LF – EF)
81
82
83
86
87
88
89
90
91
92
93
94
95
97
98
99
100
101
102
103
104
Pag
e
105
Pag
e
106
Pag
e
107
108
1 2 3 4 5 6 7
ACT COST
B C
A 200 20
B 150 4 3
C 300 A D F
D 200 10 30 40 50
3
E 100 3 1
F 150 E
35
2
1 2 3 4 5 6 7
B C
ACT COST 20
4 3
A 200 A D F
B 150 10 30 40 50
3
C 300 3 1
D 200 E
35
E 100 2
F 150
A + 3B
4
1 2 3 4 5 6 7
B C
ACT COST 20
4 3
A 200 A D F
B 150 10 30 40 50
3
C 300 3 1
D 200 E
35
E 100 2
F 150
A + B + D + 1E
312.50 2
1 2 3 4 5 6 7
B C
ACT COST 20
4 3
A 200 A D F
B 150 10 30 40 50
3
C 300 3 1
D 200 E
35
E 100 2
F 150
A + B + D + E + 1F +1G
3 3
312.50 600
1 2 3 4 5 6 7
B C
ACT COST 20
4 3
A 200 A D F
B 150 10 30 40 50
3
C 300 3 1
D 200 E
35
E 100 2
F 150
A D F
10 30 40 3 50
3 1
COST E
35
1200 - 2
1100
1000 -
800 - 800
600 - 600
400 -
312.50
200 - TIME
0-
1 2 3 4 5 6 7
B C
20
4 3
A D F
10 30 40 3 50
3 1
COST E
35
1200 - 2
1100
1000 -
800 - 800
600 - 600
400 -
312.50
200 - TIME
0-
1 2 3 4 5 6 7
B C
20
4 3
A D F
10 30 40 3 50
3 1
COST E
35
1200 - 2
1000 -
800 -
600 -
400 -
200 - TIME
0-
1 2 3 4 5 6 7
Pag
e
117
COST 312.50 600 800 1100
COST
1200 -
1000 -
800 -
600 -
400 -
200 - TIME
0-
1 2 3 4 5 6 7
312.50 600 800 1100
COST
%
100 -
80 -
60 -
40 -
20 - TIME
0-
1 2 3 4 5 6 7
1 2 3 4 5 6 7
B C
ACT COST 20
4 3
A 200 A D F
B 150 10 30 40 50
3
C 300 3 1
D 200 E
35
E 100 2
EVERY TWO MONTHS
F 150
By MILESTONES
4
20
3
1 2 3 4 5 6 7
312.50 600 800 1100
COST
%
100 -
80 -
60 -
40 -
20 - TIME
0-
1 2 3 4 5 6 7
B 150 C 300
4
20
3
1 2 3 4 5 6 7
312.50 600 800 1100
COST
1200 -
1000 -
800 -
600 -
400 -
200 - TIME
0-
1 2 3 4 5 6 7
312.50 600 800 1100
B F
A C E G H
D
2 3
Exercises 3
5
2 0.5
4 0.5
B F
A C E G H
D
2 3
Exercises 3
5
2 0.5
4 0.5
B F
A C E G H
D
B F
A C E G H
D
B F
A C E G H
A C E G H
A C E G H
2 3
5 3
2 0.5
Project Implementation Period
4Timeline in Months 0.5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
2
B F
A C E G H
2 3
5 3
2 0.5
Project Implementation Period
4Timeline in Months 0.5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
2 9.75 12.25
B F
A C E G H
2 3
5 3
2 0.5
Project Implementation Period
4Timeline in Months 0.5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
2 9.75 12.25 13 16 18 19.5 20
Project Implementation Period
Timeline in Months
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
16.
2.0 9.75 12.25 13.0 18.0 19.5 20.0
5
Project Implementation Period
Timeline in Months
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
16.
2.0 9.75 12.25 13.0 18.0 19.5 20.0
5
20 -
16 -
12 -
8-
4-
0-
COST Project Implementation Period
Timeline in Months TIME
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
16.
2.0 9.75 12.25 13.0 18.0 19.5 20.0
5
20 -
16 -
12 -
8-
4-
0-
COST Project Implementation Period
Timeline in Months TIME
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
16.
2.0 9.75 12.25 13.0 18.0 19.5 20.0
5
20 -
16 -
12 -
8-
4-
0-
COST Project Implementation Period
Timeline in Months TIME
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
16.
2.0 9.75 12.25 13.0 18.0 19.5 20.0
5
2 3
Exercises 3
5
2 0.5
4 0.5
B F
A C E G H
D
B 3 F
5
2 3
0.5 0.5
A 2 C E G H
4 D
2 3
5 3
2 0.5
4 0.5
B 3 F
5
2 3
0.5 0.5
A 2 C E G H
4 D
16.
2.0 9.75 12.25 13.0 18.0 19.5 20.0
5
B 3 F
5
2 3
0.5 0.5
A 2 C E G H
4 D
16.
2.0 9.75 12.25 13.0 18.0 19.5 20.0
5
B 3 F
5
2 3
0.5 0.5
A 2 C E G H
4 D
16.
2.0 9.75 12.25 13.0 18.0 19.5 20.0
5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
B 3 F
5
2 3
0.5 0.5
A 2 C E G H
4 D
16.
2.0 9.75 12.25 13.0 18.0 19.5 20.0
5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
B 3 F
5
2 3
0.5 0.5
A 2 C E G H
4 D
16.
2.0 9.75 12.25 13.0 18.0 19.5 20.0
5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
B 3 F
5
2 3
0.5 0.5
A 2 C E G H
4 D
16.
2.0 9.75 12.25 13.0 18.0 19.5 20.0
5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
B 3 F
5
2 3
0.5 0.5
A 2 C E G H
4 D
16.
2.0 9.75 12.25 13.0 18.0 19.5 20.0
5
16.
2.0 9.75 12.25 13.0 18.0 19.5 20.0
5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
B 3 F
5
2 3
0.5 0.5
A 2 C E G H
4 D
16.
2.0 18.0 19.5 20.0
5
16.
2.0 9.75 12.25 13.0 18.0 19.5 20.0
5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
B 3 F
5
2 3
0.5 0.5
A 2 C E G H
4 D
16.
2.0 9.75 12.25 13.0 18.0 19.5 20.0
5
B 3 F
5
2 3
0.5 0.5
A 2 C E G H
4 D
16.
2.0 18.0 19.5 20.0
5
16.
2.0 9.75 12.25 13.0 18.0 19.5 20.0
5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
B 3 F
5
2 3
0.5 0.5
A 2 C E G H
4 D
A + B 3/5 +
16.
2.0 18.0 19.5 20.0
5
16.
2.0 9.75 12.25 13.0 18.0 19.5 20.0
5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
B 3 F
5
2 3
0.5 0.5
A 2 C E G H
4 D
A + B 3/5 + C 3/8
16.
2.0 18.0 19.5 20.0
5
16.
2.0 9.75 12.25 13.0 18.0 19.5 20.0
5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
B 3 F
5
2 3
0.5 0.5
A 2 C E G H
4 D
A + B 3/5 + C 3/8
16.
2.0 5.75 5
18.0 19.5 20.0
16.
2.0 9.75 12.25 13.0 18.0 19.5 20.0
5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
B 3 F
5
2 3
0.5 0.5
A 2 C E G H
4 D
A + B 3/5 + C 3/8
16.
2.0 5.75 8.25 13.0 5
18.0 19.5 20.0
16.
2.0 9.75 12.25 13.0 18.0 19.5 20.0
5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
20 -
16 -
12 -
8-
4-
0-
COST Project Implementation Period
Timeline in Months TIME
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
16.
16.
2.0
2.0 9.75
5.75 12.25
8.25 13.0
13.0 18.0
18.0 19.5
19.5 20.0
20.0
55
20 -
16 -
12 -
8-
4-
0-
COST Project Implementation Period
Timeline in Months TIME
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
16.
16.
2.0
2.0 9.75
5.75 12.25
8.25 13.0
13.0 18.0
18.0 19.5
19.5 20.0
20.0
55
B 150 C 300
15 20
2 3
15 20
2 3
15 20
2 3
15 20
2 3