Documente Academic
Documente Profesional
Documente Cultură
Finish fast
Quantify progress
Communicate effectively
Activity on branch
Activity on node
C D
2 3 2 4 3 End
A B E F G
Start
1 1
C D
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
Forward pass calculates early start and finish
2 3 2 4 3 End
A B E F G
Start
1 1
C D
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
Backward pass calculates latest start and end times
2 3 2 4 3 End
A B E F G
Start
1 1
C D
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
Start
1 1
C D
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
Activities not on the critical path have “slack.”
The latest start time
3 andEthe2earliest 4startGdate
3 are
A 2 B F End
different
Start
1 1
C D
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
Start Finish
Early 0
Late
2 3 2 4 3 End
A B E F G
Start
1 1
C D
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
Start Finish
Early 0 2
Late
2 3 2 4 3 End
A B E F G
Start
1 1
C D
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F Start Finish
E 0 2 Early 2 5
L Late
2 3 2 4 3 End
A B E F G
Start
1 1
C D
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F S F
E 0 2 E 2 5
L L
2 3 2 4 3 End
A B E F G
Start
1 1
C D
Start Finish
Early 2 5
Activity Description
Late A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F S F
E 0 2 E 2 5
L L
2 3 2 4 3 End
A B E F G
Start
1 1
C D
S F Start Finish
E 0 1 Early 1
Activity
2
Description
L Late A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F S F Start Finish
E 0 2 E 2 5 Early 5 7
L L Late
2 3 2 4 3 End
A B E F G
Start
1 1
C D
S F S F
E 0 1 E 1 2 Activity Description
L L A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F S F S F S F S F
E 0 2 E 2 5 E 5 7 E 7 11 E 11 14
L L L L L
2 3 2 4 3 End
A B E F G
Start
1 1
C D
S F S F
E 0 1 E 1 2 Activity Description
L L A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F S F S F S F
S F
E 0 2 E 2 5 E 5 7 E 7 11 E 11 14
L L L L L 14
2 3 2 4 3 End
A B E F G
Start
1 1
C D
S F S F
E 0 1 E 1 2
L L
2 3 2 4 3 End
A B E F G
Start
1 1
C D
S F S F
E 0 1 E 1 2
L L
2 3 2 4 3 End
A B E F G
Start
1 1
C D
S F S F
E 0 1 E 1 2 Activity Description
L L A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F S F S F S F S F
E 0 2 E 2 5 E 5 7 E 7 11 E 11 14
L 0 2 L 2 5 L 5 7 L 7 11 L 11 14
2 3 2 4 3 End
A B E F G
Start
1 1
C D
S F S F
Activity Description
E 0 1 E 1 2
L 3 4 L 4 5 A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Slack Time
S F S F S F S F S F
E 0 2 E 2 5 E 5 7 E 7 11 E 11 14
L 0 2 L 2 5 L 5 7 L 7 11 L 11 14
2 3 2 4 3 End
A B E F G
Start
1 1
C D
S F S F
E 0 1 E 1 2
L 3 4 L 4 5
2 3 2 4 3 End
A B E F G
Start
1 1
C D
S F S F
E 0 1 E 1 2
L 3 4 L 4 5
A B E F G
C D
A B E F G
C D
A B E F1 G
C D F2