Critical Path Method

Farrokh Alemi, Ph.D.


Purpose of CPM

 Finish fast
 Quantify progress
 Communicate effectively

Course on Project Management


Advantages and Disadvantages of
Formal Schedules
 Saves time and money on large
complex projects
 Effective communication tool
 Too much work
 Assessment of duration of tasks
 Assessment of interdependencies

Course on Project Management


Resource Oriented and Time
Oriented Schedules
 Resource oriented
 Time oriented

Course on Project Management


Elements of a Critical Path
Chart
 Activity
 Precedence
 Duration/cost

Course on Project Management


Elements of a Critical Path
Chart
 Activity
 Precedence
 Duration/cost
Activity Description
A Select satisfaction survey tool
B Print survey tool
C Obtaining list of patients
D Sample from list
E Mail surveys to selected patients
F Collect responses
G Analyze data

Course on Project Management


Elements of a Critical Path
Chart
 Activity
 Precedence
 Duration/cost

Course on Project Management


Elements of a Critical Path
Chart
 Activity
 Precedence
 Duration/cost
Activity Description Precedents
A Select satisfaction survey tool
B Print survey tool A
C Select list of patients
D Sample from list C
E Mail surveys to selected patients D
F Collect responses E
G Analyze data F

Course on Project Management


Elements of a Critical Path
Chart
 Activity
 Precedence
 Duration/cost

Course on Project Management


Elements of a Critical Path
Chart
 Activity
 Precedence
 Duration/cost

Activity Description Precedents Duration


A Select satisfaction survey tool 2 weeks
B Print survey tool A 3 weeks
C Select list of patients 1 week
D Sample from list C 1 week
E Mail surveys to selected patients D 2 weeks
F Collect responses E 4 weeks
G Analyze data F 3 weeks

Course on Project Management


Branch and Node Charts

 Activity on branch
 Activity on node

Course on Project Management


Activity In Node
A B E F G

C D

Activity Description Precedents


A Select satisfaction survey tool
B Print survey tool A
C Obtain list of patients
D Sample from list C
E Mail surveys to selected patients D,B
F Collect responses E
G Analyze data F

Course on Project Management


Activity On Branches
A B E F G
1 3 5 6 7 End
Start
C D
2 4

Activity Description Precedents


A Select satisfaction survey tool
B Print survey tool A
C Obtain list of patients
D Sample from list C
E Mail surveys to selected patients D,B
F Collect responses E
G Analyze data F

Course on Project Management


Earliest and Latest Start and
Finish Times

2 3 2 4 3 End
A B E F G

Start

1 1
C D

Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
Forward pass calculates early start and finish

2 3 2 4 3 End
A B E F G

Start

1 1
C D

Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
Backward pass calculates latest start and end times

2 3 2 4 3 End
A B E F G

Start

1 1
C D

Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times

Critical Path includes activities where earliest start


A 2time and 3 E 2time Fare 4equal
B latest start G 3 End

Start

1 1
C D

Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
Activities not on the critical path have “slack.”
The latest start time
3 andEthe2earliest 4startGdate
3 are
A 2 B F End
different
Start

1 1
C D

Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
Start Finish
Early 0
Late

2 3 2 4 3 End
A B E F G

Start

1 1
C D

Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
Start Finish
Early 0 2
Late

2 3 2 4 3 End
A B E F G

Start

1 1
C D

Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F Start Finish
E 0 2 Early 2 5
L Late

2 3 2 4 3 End
A B E F G

Start

1 1
C D

Activity Description
A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F S F
E 0 2 E 2 5
L L

2 3 2 4 3 End
A B E F G

Start

1 1
C D

Start Finish
Early 2 5
Activity Description
Late A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F S F
E 0 2 E 2 5
L L

2 3 2 4 3 End
A B E F G

Start

1 1
C D

S F Start Finish
E 0 1 Early 1
Activity
2
Description
L Late A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F S F Start Finish
E 0 2 E 2 5 Early 5 7
L L Late

2 3 2 4 3 End
A B E F G

Start

1 1
C D

S F S F
E 0 1 E 1 2 Activity Description
L L A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F S F S F S F S F
E 0 2 E 2 5 E 5 7 E 7 11 E 11 14
L L L L L

2 3 2 4 3 End
A B E F G

Start

1 1
C D

S F S F
E 0 1 E 1 2 Activity Description
L L A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F S F S F S F
S F
E 0 2 E 2 5 E 5 7 E 7 11 E 11 14
L L L L L 14

2 3 2 4 3 End
A B E F G

Start

1 1
C D

S F S F
E 0 1 E 1 2
L L

Latest finish is the minimum of latest start of


succeeding tasks. Latest start is the latest finish
minus duration.

Course on Project Management


Earliest and Latest Start and
Finish Times
S F S F S F S F S F
E 0 2 E 2 5 E 5 7 E 7 11 E 11 14
L L L L L 11 14

2 3 2 4 3 End
A B E F G

Start

1 1
C D

S F S F
E 0 1 E 1 2
L L

Latest finish is the minimum of latest start of


succeeding tasks. Latest start is the latest finish
minus duration.

Course on Project Management


Earliest and Latest Start and
Finish Times
S F S F S F S F
S F
E 0 2 E 2 5 E 5 7 E 7 11 E 11 14
L L L L 7 11 L 11 14

2 3 2 4 3 End
A B E F G

Start

1 1
C D

S F S F
E 0 1 E 1 2 Activity Description
L L A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Earliest and Latest Start and
Finish Times
S F S F S F S F S F

E 0 2 E 2 5 E 5 7 E 7 11 E 11 14

L 0 2 L 2 5 L 5 7 L 7 11 L 11 14

2 3 2 4 3 End
A B E F G

Start

1 1
C D

S F S F
Activity Description
E 0 1 E 1 2
L 3 4 L 4 5 A Select satisfaction survey tool
B Print survey tool
C Select list of patients
D Sample from list
E Mail surveys to patients
F Collect responses
Course on Project Management G Analyze data
Slack Time
S F S F S F S F S F
E 0 2 E 2 5 E 5 7 E 7 11 E 11 14
L 0 2 L 2 5 L 5 7 L 7 11 L 11 14

2 3 2 4 3 End
A B E F G

Start

1 1
C D

S F S F
E 0 1 E 1 2
L 3 4 L 4 5

Slack time = Latest start – Earliest start

Course on Project Management


Critical Path
S F S F S F S F S F
E 0 2 E 2 5 E 5 7 E 7 11 E 11 14
L 0 2 L 2 5 L 5 7 L 7 11 L 11 14

2 3 2 4 3 End
A B E F G

Start

1 1
C D

S F S F
E 0 1 E 1 2
L 3 4 L 4 5

Critical path includes activities with no slack.

Course on Project Management


Communicating Project Schedule

 Time scaled network of activities


 Gantt chart
 Time an activity graphs and
completion graphs

Course on Project Management


Communicating Project Schedule

 Time scaled network of activities


 Gantt chart
 Time an activity graphs and
completion graphs

Course on Project Management


Communicating Project Schedule

 Time scaled network of activities


 Gantt chart
 Time an activity graphs and
completion graphs

Course on Project Management


Activity Splitting

A B E F G

C D

Activity Description Precedents


A Select satisfaction survey tool
B Print survey tool A
C Obtain list of patients
D Sample from list C
E Mail surveys to selected patients D,B
F Collect responses E
G Analyze data F

Course on Project Management


Activity Splitting

A B E F G

C D

Activity Description Precedents


A Select satisfaction survey tool
B Print survey tool A
C Obtain list of patients
D Sample from list C
E Mail surveys to selected patients D,B
F Collect responses E
G Analyze data F

Course on Project Management


Activity Splitting

A B E F1 G

C D F2

Activity Description Precedents


A Select satisfaction survey tool
B Print survey tool A
C Obtain list of patients
D Sample from list C
E Mail surveys to selected patients D,B
F Collect responses (F1=early, F2=Late) E
G Analyze data F

Course on Project Management


Software

 Discovery of Critical Path

Course on Project Management


Crashing Schedules

 Cost time tradeoff


 Order of crashing

Course on Project Management


Take Home Lesson

The critical path includes activities


with no slack