Sunteți pe pagina 1din 12

EMERGING AND SUSTAINABLE ISSUES

PREPARED BY:
GELBURAI RABONG – 2015276478
NATASHA C. LENYA - 2015318313
INTRODUCTION
◦ Construction wastes have become a pressing issue in many developing countries and
have adverse effects on environment, economy and social aspects.
◦ Construction industry plays a key role in socio-economic development of any country.
◦ Nowadays construction industry is rapidly growing because of increase in standard of
living, demands of infrastructure projects, changes in consumption habits, as well as
natural increase in population.
◦ This growth has contributed significantly in waste generation which has become serious
problem for every nation.
SUSTAINABLE ISSUES RELATED TO CONSTRUCTION
WASTE
◦ Construction waste is a prominent
issue globally and has adverse
effect on overall performance of a
project as well as the society and
nature.
◦ Construction waste occurs in the
form of material, time and cost
losses.
◦ It can be categorised to two issue:-
1. Physical construction waste-
Material cost
2. Non-physical waste- Cost and time
overrun Classification of construction waste
1. Materials waste as a physical construction waste
◦ Major physical waste generated from construction activity is identified in the form of
material waste like concrete leftover, demolished debris, steel scrap and others (Nagapan
et. al., 2011)
◦ Material waste has significant impact to the cost of the project as well as an adverse
impact on environment.
◦ One of the implications created from huge quantities of material waste is illegal dumping
which is the unlawful deposit activity of waste onto land.
◦ This activity causes problems to the public in general and to the environment
◦ Wrongly disposal of physical wastes are increasing and this contributes to pollution globally
MALAYSIA
◦ Malaysia is facing the problem of illegal dumping
◦ This implies lack in practice of waste management practices in construction industry.
◦ Malaysia has their own regulatory policies in handling wastes generation such as:-
Solid Waste and Public Cleansing Management Act 2007 (PPSPPA) governed by Ministry of
Housing and Local Government
Standard Specifications for Buildings Works (SBW) governed by Ministry of Works
Environmental Quality Act 1974 (EQA) governed by Ministry of Natural Resources and
Environment
Pembinaan Malaysia Act 1994 (PMA) governed by Construction Industry Development Board
(CIDB)
◦ However, all these policies do not really cover all the aspects of construction waste
management.
◦ For example:-
Solid Waste and Public Cleansing Management Act 2007 (PPSPPA) – Focus on domestic waste
Standard Specifications for Buildings Works (SBW) – For contractors that handles project with
Public Work Department (JKR) under clearing, cleaning and making good on completion
clause, requires garbage and construction waste clearance to be done twice a week and
contractors are needed to dispose the construction waste in landfills or approved sites.
Pembinaan Malaysia Act 1994 (PMA) – To prevent, reduce, control pollution and to enhance
environment. Example of wastes are liquid, solid, gasses and radioactive. The wastes are either
normal waste or schedule waste. The downside of the law is that it considers waste, when it is
deposited and causes pollution to environment. PMA act is to provide functions relating to the
construction works. It gives power to investigate officers at any time for the purpose of
inspection in construction. This enforcement law gives the authority to act upon construction
waste left on site through the term of site clearance
◦ According to the Report on Illegal Dumpsites Identification in Selected Areas of Majlis
Daerah Hulu Selangor in 2007:-
39.3% of construction waste was found in Hulu Selangor District with a total of 87
illegal dumping grounds.
◦ Due to this, Malaysia CIDB and Solid Waste Management and Public Cleansing
Corporation plan for a guideline on management of construction waste in the future.
SINGAPORE
◦ National Environment Agency (NEA) hold the overall responsibility for construction
waste and enforcement of illegal dumping
◦ The government of Singapore is very supportive and giving the maximum matters in
regard of the protection of environment.
◦ Penalties is implemented for any illegal dumping found
◦ However, illegal dumping are still an alarming issues in the country.
◦ The illegal dumiping takes place in remote areas of Lim Chu Kang, Jalan Buroh, Mandai
and Neo Tiew Road.
◦ In order to attain sustainability, the government has established a Singapore Green
Building Council (SGBC) and local construction industry in Singapore are adopting the
ISO 14000 EMS to upgrade the performance of environmental construction
HONG KONG
◦ Few initiatives have been introduced by the Hong Kong government to implement
waste management as below:
1. Waste Disposal Ordinance
2. 10 – Year Plan to Reduce Waste and Pollution
3. Green Manager Scheme
4. Waste Reduction Framework Plan (WFRP)
5. Pay for Safety and Environment Scheme
6. Waste Disposal Charging Scheme
◦ The public sector has absorb the sustainable construction principles into standard
specifications.
◦ Architectural Services Department (ASD) and the Local Housing Department have also
revised their standard specifications with environmental element.
◦ However, all of these initiatives are still not reaching the aim for sustainability because
issues on illegal dumping are still in an alarming stage in the country.
◦ The construction waste has been illegally dumped at Long Keng, Sai Kung and other
sites.
◦ Tai Lam Country Park was used as dumping ground for construction waste such as
rocks, concrete and other construction debris.
◦ In this case, the sustainable effort and action need to be carried out immediately to
protect the country.
Batching plants
Road Work Excavation

Demolition Construction
C&D Waste

Refurbishment

Renovation
2. Cost and time overrun as non physical waste
◦ Non-physical waste normally occurs during the construction process.
◦ It occurs when materials are not physically lost but money and time overrun can lead to
failure for the majority projects.
Example:
35 projects involving 12,000 units house in Malaysia have been abandoned (Ministry of
Housing and Local Government, 2012).
Caused of problems:
i) Poor financial management by the developers
ii) Wrong construction specification
iii) Construction delays
iv) Lack of supervision
v) Lack of enforcement on existing rules and caused dissatisfactions.
This situation has resulted into unhealthy conditions and it give an impact on economic
growth and social development of countries due to dissatisfaction of the buyers of
abandoned homes & social relationship among developers and buyers has become tensed.

S-ar putea să vă placă și