Value Stream Mapping

Monthly forecast Market Forecast


Production Customer Customer
Supplier Supplier A B
Control
1 2

Weekly schedule

Production Supervisor
Weekly
Kaizen Shipping
Daily (13 days)

Receiving 1700
Shearing Welding Painting Inspection
2 People 5 People 3 People 1 People
I C/T = 2 min I C/T = 2 min I C/T = 2 min I C/T = 2 min
C/O = 2 hr C/O = 2 hr C/O = 2 hr C/O = 2 hr
200 Batch = 50 1000 Batch = 50 Batch = 50 1500 Batch = 50
Uptime = 74% Uptime = 74% Uptime = 74% Uptime = 74%
5 days 10 days 15 days 8 days 13 days
2 min 4 min 7 min 2 min

Total Lead Time = 51 days


Value added time = 15 min
Value Stream Mapping
Quarterly Forecast Qtrly Forecast = 2,000 Licenses

Dynatrace Sales Team Cebu


LTD pacific

Weekly schedule

Project Management
Quarterly Kaizen
Quarterly ????

Daily Communication

Pre-Sales Project Mgmt Implementation Support Service


1 People 1 People 2 People 2 People
C/T = 4 hrs C/T = 6 hrs C/T = 8 hrs C/T = 5 hrs

Uptime = 70% Uptime = 80% Uptime = 85% Uptime = 70%

1 day 2 days 3 days 2 days 1 day


4 hrs 6 hrs 8 hrs 5 hrs

Total Lead Time = 9 days


Value added time = 23 hrs
Symbols used in VSM

Customer Supplier

I Inventory
Transportation

Kaizen
Kaizen Burst
Manual
Electronic Information
Information

Process Box Material flow


Thank you!
You can use this PowerPoint template for free based on creative commons license.

Follow us on Twitter @slideh or subscribe to our mailing list


Or upload your presentation for free and share online in SlideOnline.com

www.SlideHunter.com

Download Free Templates Upload to Slide Online.com

S-ar putea să vă placă și