INSTALLATION OF TOWER CRANE SCM-6015 HAMMER TYPE USING TWO 25T MOBILE
CRANE (TANDEM)
INTRODUCTION:
This erection procedures allows to rapidly assemble crane until reaches its telescoping position. It requires an
auxiliary mobile crane, the characteristics of which must correspond to the parts to be handled. Reducing a
minimum time of the auxiliary crane used on site involves good coordination between the erection and
assembling area.
INSTALLATION PROCESS:
1. Installation of hard barricades and signage's. Fixing and setting of Anchor bolts for fixing angle.
2. Installation of fixing angle.
3. Installation of mother mast 1pc. (7.50m x 1.60m x 1.60m) on fixing angle using 25t mobile crane
- Mother mast = 4.087t
5. Install Ring Gear/Turn Table with the operators cabin using 25t mobile crane
- Ring Gear = 4.555t
- Operator Cabin = 310 kgs.
7. Installation of counter jib support tie-bar into the turn table/ring gear
- Counter Jib = 9.580t
10. Connect/reeve the electrical cable and wire rope on the ground after assembling the jib
11. Lift the assembled 50 meters jib and connect to the top mast using two 25t mobile crane (tandem)
- Jib/boom = 9.269t
COOGEE INTERNATIONAL DEVELOPMENT INC.
2nd Flr. Optima Bldg. 221 Salcedo St., Cor. Gamboa St., Legaspi Village, Makati City
13. Install the remaining counter weights to the counter jib as designed
1. All the handling operations using crane must be carried out safely. For this:
- Properly pack up the crane
- Do not overload the crane
- Use sling in good order and of correct lengths according to the weights of the parts to be lifted
- respect the sling points
3. Make sure that protection and safety means are fitted and used, such as; ladders, platforms, guard rails,
safety rope etc.
6. Before starting any telescoping operation, make sure that the pins connecting the tower head to the
telescopic cage are inserted and secured by split pins
7. It is essential that the amount of counter-jib ballast indicated according to the jib lengths are respected
COOGEE INTERNATIONAL DEVELOPMENT INC.
2nd Flr. Optima Bldg. 221 Salcedo St., Cor. Gamboa St., Legaspi Village, Makati City
INSTALLATION PROCESS:
The requirements of meteorological condition during Jacking up tower crane are as follows:
Before each jacking up operation, you should check all following items. And the Jacking up
work should not start until it meets all these requirements:
(Figure 2.1)
COOGEE INTERNATIONAL DEVELOPMENT INC.
2nd Flr. Optima Bldg. 221 Salcedo St., Cor. Gamboa St., Legaspi Village, Makati City
3. The Telescoping Yoke (support beam) has been in right position and the brake-plate has
been set into the Hang Boot of Telescoping Yoke
5. Remove the 8 pins which connect slewing bracket with Mast section, then, instead of them by
4 temporary pins
7. Check the all cables, in order to avoid pulling them apart during jacking up
3. Jacking up procedure
Jacking up work is a joint work with several persons. One person operates the pump station, and
others operates check the pins, cotter pin and to set the temporary pins.
3. To release the Joystick of Supporting claw in Telescoping Cage to the open position. In order to separate
the tower body and Supporting claw.
4. Take the Joystick of Hydraulic-pressure Station upwards, and hydraulic-pressure cylinder takes the
Telescoping Cage and all upper part to move upwards. ( ① in Figure 4.1).
COOGEE INTERNATIONAL DEVELOPMENT INC.
2nd Flr. Optima Bldg. 221 Salcedo St., Cor. Gamboa St., Legaspi Village, Makati City
COOGEE INTERNATIONAL DEVELOPMENT INC.
2nd Flr. Optima Bldg. 221 Salcedo St., Cor. Gamboa St., Legaspi Village, Makati City
5. When the hydraulic-pressure cylinder approaches the down-stopping-point, then, to push the joystick of
Supporting claw, In order to lock the Supporting claw into the arc slot of Mast Section stepping. And, to
assemble safety-pin. Finally, Take the Joystick of Hydraulic-pressure Station downwards, to fix the
telescoping cage and all upper part on Mast Section stepping temporarily. ( ② in Figure 4.1).
COOGEE INTERNATIONAL DEVELOPMENT INC.
2nd Flr. Optima Bldg. 221 Salcedo St., Cor. Gamboa St., Legaspi Village, Makati City
9. At this time, Take the Joystick of Hydraulic-pressure Station upwards very lightly, to let the Hang Boot of
Telescoping Yoke lock into Mast Section stepping very solidly. Then, to set the brake-plate into the Hang
Boot of Telescoping Yoke.
10. Take the Joystick of Hydraulic-pressure Station upwards, to continue to jacking up operation. When the
supporting claw get apart from the crane body, you need to release Joystick of Supporting claw to the
open position immediately. ( ④ in Picture 4.1 ).
COOGEE INTERNATIONAL DEVELOPMENT INC.
2nd Flr. Optima Bldg. 221 Salcedo St., Cor. Gamboa St., Legaspi Village, Makati City
11. To copy this process for three times, the space of Jacking up will be enough for one mast section. ( ⑤ in
Picture 4.1 ).
COOGEE INTERNATIONAL DEVELOPMENT INC.
2nd Flr. Optima Bldg. 221 Salcedo St., Cor. Gamboa St., Legaspi Village, Makati City
1. When the jacking up operation is finished (to do above process for three times), and there is enough
room for leading into one set of Mast Section, you can to pull the Mast Section hanging on the Leading-in
Beam (Monorail) towards the crane slowly and finally get it inside the frame.
2. Take the Joystick of Hydraulic-pressure Station downwards, and to align the lower extreme of the new
Mast Section and upper extreme of the fish-tail-plate on the original Mast Section. Then to insert 8 pins
and to fix it with lock pins.
3. Tear down the 4 bolts of the Leading-in Trolley, and to fix the bolts in the rings of the trolley. And then, to
pull the Leading-in Trolley out of the place of Mast Section.
4. Continue to fall the telescoping cage, until the 4 legs of the slewing bracket get into the upper extreme of
the fish-tail-plates of the new Mast Section. Finally, to connect the Slewing Bracket and new Mast
Section by the 4 temporary pins.
COOGEE INTERNATIONAL DEVELOPMENT INC.
2nd Flr. Optima Bldg. 221 Salcedo St., Cor. Gamboa St., Legaspi Village, Makati City
In order to make jacking up work conveniently, to weld 4 temporary pins on the upper extreme of four squares of
the slewing bracket. The temporary pins’ diameter is smaller than standard Mast Section’s pins’ diameter about
2mm.
And the temporary pins are only used to connect lower bracket with crane body temporarily. When
the crane is running, it is forbidden to use the temporary pins instead of standard Mast section pins.
(Figure 4.2)