Documente Academic
Documente Profesional
Documente Cultură
1
TIME MANAGEMENT
DELAY NOT AFFECTING THE CRITICAL PATH
M J J A
Task Name 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23
1 Task 1 Original Date
for
2 Task 2 Completion
3 Task 3
4 Task 4
5 Task 5
6 Task 6
Delay due to
7 Employer
8 Task 7
2
TIME MANAGEMENT
DELAY DUE TO EACH OF THE PARTIES – CASE 1
M J J A
Task Name 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23
1 Task 1
2 Task 2
Original Date
3 Task 3 for
Delay due to Completion
4 Employer
5 Task 4
6 Task 5
7 Task 6
Delay due to
8 Contractor
9 Task 7
3
TIME MANAGEMENT
DELAY DUE TO EACH OF THE PARTIES – CASE 2
M J J A
Task Name 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23
1 Task 1
2 Task 2
Original Date
3 Task 3 for
Delay due to Completion
4 Employer
5 Task 4
6 Task 5
7 Task 6
Delay due to
8 Contractor
9 Task 7